Third Notice | | 12/17/2016 | 12/13/2016 | | DONE |
|
|
|
|
Third Notice | | 10/15/2016 | 11/21/2016 | | DONE |
|
|
|
sent with a letter
|
Third Notice | | 9/24/2016 | 10/10/2016 | | DONE |
|
|
|
|
Third Notice | | 8/16/2016 | 9/19/2016 | | DONE |
|
|
|
|
Second Notice | | 7/21/2016 | 8/11/2016 | | DONE |
|
|
|
mailed 8-11-16
|
First Notice | 6/30/2016 | 6/30/2016 | 7/11/2016 | | DONE |
Jim Storey
|
|
|
Mailed 7-12
|
BLD-Final | 6/30/2016 | 6/30/2016 | 6/30/2016 | P | PASS |
Jim Storey
|
|
|
Jamal Phone #: ###-####
|
DOC - Permit Finaled | 6/30/2016 | 6/30/2016 | 6/30/2016 | P | PASS |
Jim Storey
|
|
|
per the reviewed plans
|
Zoning Approval | 6/30/2016 | 6/30/2016 | 6/30/2016 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Final | 6/29/2016 | 6/29/2016 | 6/29/2016 | P | NR |
Jim Sly
|
|
|
Jamal Phone #: ###-#### No inspection performed. Called Jamal.......Need Zoning final. Not in computer and no card signed.
|
CHANGE STATUS TO (ISS) | | | 6/21/2016 | | DONE |
|
|
|
|
(F) Reprint permit | | | 6/21/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/20/2016 | | DONE |
|
|
|
NEED GC form from Jamal with Zayne Construction and fees need to be paid***PLEASE DO NOT RE ISSUE*******
|
Routing - PLUMBING | 6/14/2016 | | 6/17/2016 | | PASS |
Daryl Spivey
|
|
|
revised scope. caretakers quarters and the three units to the east are the only rooms getting sinks added
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/17/2016 | | DONE |
|
|
|
|
CHANGE STATUS TO (RDY) | | | 6/17/2016 | | DONE |
|
|
|
SEWER IMPACT FEES DUE- DO NOT RE-ISSUE THIS IS A PLAN MOD- also GC is CHANGING- MUST HAVE NEW GC FORM and LETTER FROM CURRENT GC RELEASING HIS NAME BEFORE CHANGING TO ISSUE STATUS- talk to Candy
|
Plan assigned to (TLW) | 6/9/2016 | | 6/17/2016 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 6/14/2016 | | 6/14/2016 | | PASS |
Tim L. Woodard
|
|
|
No change to Building Plan Review. TLW
|
Routing - PUBLIC WORKS | 6/14/2016 | | 6/14/2016 | | PASS |
Rachael Beierle
|
|
|
Adding new sinks in other units. TLW
|
Plan Modification Accepted | | | 6/9/2016 | | DONE |
Christina Prado
|
|
|
Plan Mod to update three rooms to now include kitchenette type settings
|
FIRE-Final Inspection | 3/31/2016 | 3/31/2016 | 3/31/2016 | P | PASS |
Jim Page
|
|
|
Previously noted items addressed/repaired. Final life fire safety inspection passed/complete
|
FIRE-Final Inspection | 3/30/2016 | 3/31/2016 | 3/31/2016 | A | FAIL |
Jim Page
|
|
|
Emergency egress light in the corridor was not attached to wall with wires visible, fire extinguishers need to have an inspection performed by a lisenced contractor and a current inspection tag needs to be attached. Audio/visual device on fire alarm system not attached to finished ceiling. Items need to be addressed beofre next inspection.
|
BLD-Framing/Rough-in | 2/3/2016 | 2/5/2016 | 2/5/2016 | A | PART |
Jim Storey
|
|
|
Jared Phone #: ###-####
|
BLD-Footing | 12/10/2015 | 12/10/2015 | 12/10/2015 | P | NR |
Jim Sly
|
|
|
Matt Phone #: ###-#### Need approved plan with all small docs. Special inspection not done. Footing to the South does not match plans.....Engineer to advise. Provide Stamped engineering details if plans are modified.
|
BLD-Foundation | 12/10/2015 | 12/10/2015 | 12/10/2015 | P | CANC |
Jim Sly
|
|
|
Rebar // Matt Phone #: ###-####
|
Meeting | | | 11/5/2015 | | DONE |
|
|
|
as per Jamal Jabari-he will no longer be the GC-Zodak Consruction Inc will take over as of today
|
(F) Reprint permit | | | 11/5/2015 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/21/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/21/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/6/2015 | | 7/28/2015 | | PASS |
Tim L. Woodard
|
|
|
|
Routing Off Site - STRUCTURAL | 7/6/2015 | | 7/28/2015 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/28/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/28/2015 | | DONE |
|
|
|
need ACHD, GC, rev cert of val & RP
****RP IS ONLY THING MISSING NOW****
***ALL REQUIRMENTS MET 8/21/15 //CEV
|
Plan assigned to (TLW) | 5/18/2015 | | 7/28/2015 | | PASS |
Tim L. Woodard
|
|
|
1st Review Complete
|
Routing - Design Review | 7/6/2015 | | 7/14/2015 | | PASS |
Josh Wilson
|
|
|
|
Routing - FIRE | 7/6/2015 | 7/6/2015 | 7/6/2015 | | PASS |
Katie Marron
|
|
|
Revised comments attached to plan. A Fire Sprinkler System is not present and modifications do not require one.
|
Routing PW Drainage | 6/15/2015 | | 6/15/2015 | | PASS |
Jason C. Taylor
|
|
|
No grading plan/permit required. Jason Taylor ###-####
|
Routing - FIRE | 5/13/2015 | | 5/22/2015 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing PW Solid Waste | 5/13/2015 | | 5/20/2015 | | PASS |
Megan Durrell
|
|
|
|
1st review completed | | | 5/20/2015 | | DONE |
|
|
|
|
Plan assigned to (R_H) | 5/13/2015 | 5/13/2015 | 5/18/2015 | | DONE |
Ron Hill
|
|
|
|
Routing - PLAN CHECK | 5/13/2015 | | 5/18/2015 | | FAIL |
Tim L. Woodard
|
|
|
Cannot add onto existing non-compliant building. Fire Sprinklers required. Called and discussed with architect he is redesigning and resubmitting through DR. TLW
|
Routing Off Site - STRUCTURAL | 5/13/2015 | | 5/18/2015 | | PASS |
Ron Hill
|
|
|
Cannot add onto existing non-compliant building. Fire Sprinklers required. Called and discussed with architect he is redesigning and resubmitting through DR. TLW
|
Routing PW Drainage | 5/13/2015 | | 5/14/2015 | | FAIL |
Jason C. Taylor
|
|
|
Need grading plan. Jason Taylor ###-####
|
Routing PW Street Lights | 5/13/2015 | | 5/14/2015 | | PASS |
Mike D Hedge
|
|
|
No new street lighting required.
|
Routing PW Sewer Rating | 5/13/2015 | | 5/14/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 5/13/2015 | | 5/14/2015 | | CANC |
Evan Jenkins
|
|
|
No ESC Permit Required
EEJ---
|
Routing - Addressing | 5/13/2015 | | 5/13/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 5/13/2015 | | 5/13/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Design Review | 5/13/2015 | | 5/13/2015 | | PASS |
Andrea Tuning
|
|
|
DRH15-00123
|
Intake Approval | | | 5/13/2015 | | PASS |
|
|
|
|
Pending Assignment by TLW | 5/13/2015 | | 5/13/2015 | | DONE |
Tim L. Woodard
|
|
|
|
Application received | | | 5/7/2015 | | DONE |
|
|
|
Application submitted via PDS Online on May 7 2015 9:35AM
|