Third Notice | | 10/15/2016 | 11/21/2016 | | DONE |
|
|
|
sent with a letter
|
Third Notice | | 9/24/2016 | 10/10/2016 | | DONE |
|
|
|
|
Third Notice | | 8/16/2016 | 9/19/2016 | | DONE |
|
|
|
|
Second Notice | | 7/21/2016 | 8/11/2016 | | DONE |
|
|
|
mailed 8-12-16
|
First Notice | 6/15/2016 | 6/15/2016 | 7/11/2016 | | DONE |
Jim Storey
|
|
|
Mailed 7-12
|
Letter of compliance/Occupancy | | | 6/17/2016 | | DONE |
|
|
|
|
BLD-Final | 6/14/2016 | 6/15/2016 | 6/15/2016 | A | PASS |
Jim Storey
|
|
|
Jarrod Phone #: ###-####
|
DOC - Permit Finaled | 6/15/2016 | 6/15/2016 | 6/15/2016 | P | PASS |
Jim Storey
|
|
|
|
BLD-Final | 6/6/2016 | 6/7/2016 | 6/7/2016 | A | NR |
Jim Storey
|
|
|
Jamal Phone #: ###-####
|
BLD-Final | 6/3/2016 | 6/3/2016 | 6/6/2016 | P | NR |
Jim Storey
|
|
|
Jared-ask for Jamal ###-#### Phone #: ###-####
|
Zoning Approval | 6/3/2016 | 6/3/2016 | 6/3/2016 | | DONE |
Andrea Tuning
|
|
|
|
FIRE-Final Inspection | 3/25/2016 | 3/25/2016 | 3/25/2016 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarm modifications, point of contact has fire extinguisher to put in fire extingiusher cabinet. Final life fire safety inspection passed/complete.
|
BLD-Final | 3/24/2016 | 3/25/2016 | 3/25/2016 | A | NR |
Jim Sly
|
|
|
Jared Phone #: ###-#### Need Zoning, Fire Alarm and Fire/Life Finals.
|
BLD-Framing/Rough-in | 2/3/2016 | 2/5/2016 | 2/5/2016 | A | PART |
Jim Storey
|
|
|
Jared Phone #: ###-####
|
BLD-Foundation | 12/10/2015 | 12/10/2015 | 12/10/2015 | P | NR |
Jim Sly
|
|
|
Rebar // Jamal Phone #: ###-#### Special insp. required.......No inspection performed. Footing pad to the North.....is not complete per plan......Foundation wall intersects footing and footing not big enough. Engineer to advise. Contractor to provide small docs which were not attached to plan.
|
Meeting | | | 11/5/2015 | | DONE |
|
|
|
as per Jamal Jabari-he will no longer be the GC-Zodak Consruction Inc will take over as of today
|
(F) Reprint permit | | | 11/5/2015 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/21/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/21/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 7/30/2015 | | |
|
|
|
|
Route to Impact Fee Review | 7/29/2015 | 8/3/2015 | 7/30/2015 | | PASS |
Cindy M. Gould
|
|
|
|
Permit Ready to Issue | | | 7/30/2015 | | DONE |
Christina Prado
|
|
|
Need ACHD, RP, GC & Revised cert of value for issuance
****RP IS ONLY THING MISSING NOW****
***ALL REQUIRMENTS MET 8-21-15 //CEV
|
Routing Off Site - STRUCTURAL | 7/6/2015 | | 7/28/2015 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/28/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/6/2015 | | 7/28/2015 | | PASS |
Tim L. Woodard
|
|
|
|
Plan assigned to (TLW) | 5/18/2015 | | 7/28/2015 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - Design Review | 7/6/2015 | | 7/14/2015 | | PASS |
Josh Wilson
|
|
|
|
Routing - FIRE | 7/6/2015 | | 7/6/2015 | | PASS |
Katie Marron
|
|
|
Comments attached to plan
|
Plan resubmittals received | | | 7/6/2015 | | DONE |
|
|
|
|
1st review completed | | | 6/1/2015 | | FAIL |
|
|
|
|
Routing Off Site - STRUCTURAL | 5/13/2015 | | 6/1/2015 | | FAIL |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 5/13/2015 | | 6/1/2015 | | FAIL |
Tim L. Woodard
|
|
|
|
Routing - FIRE | 5/13/2015 | | 5/27/2015 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing PW Solid Waste | 5/13/2015 | | 5/20/2015 | | PASS |
Megan Durrell
|
|
|
|
Plan assigned to (R_H) | 5/13/2015 | 5/13/2015 | 5/15/2015 | | |
Ron Hill
|
|
|
|
Routing - Erosion and Sediment | 5/13/2015 | | 5/14/2015 | | FAIL |
Evan Jenkins
|
|
|
Per BCC 8-17: Commercial Demo's w/ Exterior Work shall submit atleast an ESC Waiver Request Letter with ESC Application form. Evan Jenkins ###-####
|
Routing PW Drainage | 5/13/2015 | | 5/14/2015 | | FAIL |
Jason C. Taylor
|
|
|
Need civil grading plan to show how drainage is to be affected. Please submit civil drawings. Jason Taylor ###-####.
|
Routing PW Street Lights | 5/13/2015 | | 5/14/2015 | | PASS |
Mike D Hedge
|
|
|
No new street lighting required.
|
Routing PW Sewer Rating | 5/13/2015 | | 5/14/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Intake Approval | | | 5/13/2015 | | PASS |
|
|
|
|
Pending Assignment by TLW | 5/13/2015 | | 5/13/2015 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - Design Review | 5/13/2015 | | 5/13/2015 | | PASS |
Andrea Tuning
|
|
|
DRH15-00123
|
Routing - Addressing | 5/13/2015 | | 5/13/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 5/13/2015 | | 5/13/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Application received | | | 5/7/2015 | | DONE |
|
|
|
Application submitted via PDS Online on May 7 2015 11:11AM
|