Second Notice | | 11/19/2015 | 12/10/2015 | | DONE |
|
|
|
Mailed 12-11-15
|
First Notice | | 11/5/2015 | 11/9/2015 | | DONE |
|
|
|
Mailed 11-10-15
|
BLD-Final | 10/23/2015 | 10/26/2015 | 10/26/2015 | A | PASS |
Jim Sly
|
|
|
Chris Phone #: ###-#### OK for perm occ.
|
Permanent Occupancy | | | 10/26/2015 | | DONE |
|
|
|
|
FIRE-Final Inspection | 10/22/2015 | 10/23/2015 | 10/23/2015 | A | PASS |
Jim Page
|
|
|
Life fire safety passed/complete
|
Issue PAID IN FULL permit | | | 9/11/2015 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 6/18/2015 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
1st review completed | | | 6/18/2015 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/18/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/18/2015 | | DONE |
|
|
|
Need GC Form and Revised Cert of Value
|
Print Occupancy Form | | | 6/18/2015 | | DONE |
|
|
|
|
Telephone call | | | 6/18/2015 | | DONE |
|
|
|
called Milo- left voicemail that permit is ready for pick up and we still need GC form and Certificate of value and we can't add fees until we receive those forms
|
Plan assigned to (AJS) | 6/3/2015 | | 6/18/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Starbucks Addition inside Target
|
Routing - PLAN CHECK | 6/17/2015 | | 6/18/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - MECHANICAL | 6/10/2015 | | 6/18/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 6/4/2015 | | 6/17/2015 | | PASS |
Daryl Spivey
|
|
|
Provide adequate backflow protection on all installed equipment per ISPC.
|
Routing PW Environmental | 6/8/2015 | | 6/10/2015 | | PASS |
Rick Christenson
|
|
|
|
Routing - PUBLIC WORKS | 6/8/2015 | | 6/10/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Sewer Rating | 6/8/2015 | | 6/8/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 6/4/2015 | | 6/8/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/3/2015 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 6/3/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/3/2015 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 5/26/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Please see change marks on 518 check list.
|
Application received | | | 5/8/2015 | | DONE |
|
|
|
Application submitted via PDS Online on May 8 2015 4:28PM
|