Second Notice | | 5/21/2016 | 6/15/2016 | | DONE |
|
|
|
|
First Notice | | 4/25/2016 | 5/11/2016 | | DONE |
|
|
|
Mailed 5-12-16
|
Permanent Occupancy | | | 4/15/2016 | | DONE |
|
|
|
|
BLD-Final | 4/13/2016 | 4/14/2016 | 4/14/2016 | A | PASS |
Mike Jordan
|
|
|
Jake Phone #: ###-####. Ok for perm occ.
|
BLD-Final | 8/27/2015 | 8/28/2015 | 8/28/2015 | A | PART |
Mike Jordan
|
|
|
Please call 30 min prior so we can meet. Temp CO per Jason Blais Phone #: ###-#### Inspection requested via web by Kyle Buzzell. OK for temp occ
|
BLD-Final | 8/21/2015 | 8/24/2015 | 8/24/2015 | P | NR |
Mike Jordan
|
|
|
Please call prior to inspection so we can be onsite. Thanks Phone #: ###-#### Inspection requested via web by Kyle Buzzell. Needs to have electrical, plumbing and electrical finals first.
|
BLD-Other | 8/21/2015 | 8/24/2015 | 8/24/2015 | A | PASS |
Mike Jordan
|
|
|
Tim-steel beam-please call to meet Phone #: ###-####. Reviewed engineering for owner supplied calcs and inspected the in place work per the engineering.
|
Plan Reviewer's activity | | | 8/6/2015 | | DONE |
Javier Guzman
|
|
|
added into case documents the engineering for the crane and engineering letter
|
BLD-Conference | 7/2/2015 | 7/7/2015 | 7/7/2015 | A | DONE |
Mike Jordan
|
|
|
would like call ahead; Ron Phone #: ###-####. Discussed equipment issues and what is required to be submitted.
|
BLD-Final | 6/25/2015 | 6/26/2015 | 6/26/2015 | A | PART |
Mike Jordan
|
|
|
Ron Phone #: ###-####. Called and left message for ron, will need additional engineering for both structures being installed inside of building.
|
FIRE-Final Inspection | 6/11/2015 | 6/12/2015 | 6/12/2015 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 6/11/2015 | 6/12/2015 | 6/12/2015 | A | CANC |
Troy Cobbley
|
|
|
Per Ron Phone #: ###-####
|
FIRE-Final Inspection | 6/9/2015 | 6/9/2015 | 6/9/2015 | P | FAIL |
Troy Cobbley
|
|
|
Need the fire alarm permit finaled and the exit signs/emergency lights installed per the approved plans. Also need the single action hardware installed.
|
Issue PAID IN FULL permit | | | 6/4/2015 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 6/4/2015 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 6/3/2015 | | DONE |
|
|
|
All requirements met
|
Routing - FIRE | 5/28/2015 | 5/28/2015 | 6/2/2015 | | PASS |
Scott Arellano
|
|
|
Attached revised comments to plans.
|
Plan assigned to (JG) | 5/11/2015 | 5/11/2015 | 6/2/2015 | | PASS |
Javier Guzman
|
|
|
1st review completed, 5/28 (Anodizers INC) Pending Fire
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/2/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 5/28/2015 | | 5/28/2015 | | PASS |
Javier Guzman
|
|
|
resubmittals
|
1st review completed | | | 5/27/2015 | | FAIL |
Javier Guzman
|
|
|
Fire
|
Routing PW Environmental | 5/12/2015 | | 5/27/2015 | | PASS |
Rick Christenson
|
|
|
Signed off in ePlan by Rick Christenson
|
Routing - FIRE | 5/11/2015 | 5/11/2015 | 5/21/2015 | | FAIL |
Scott Arellano
|
|
|
Emailed plan review report with comments to architect. Attached report to case.
|
Routing - PLAN CHECK | 5/11/2015 | | 5/14/2015 | | PASS |
Javier Guzman
|
|
|
|
Routing - Addressing | 5/11/2015 | | 5/13/2015 | | PASS |
Emily Dixon
|
|
|
Address changed to 400 N Five Mile Rd.
|
Routing - PUBLIC WORKS | 5/11/2015 | | 5/12/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Sewer Rating | 5/12/2015 | | 5/12/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Intake Approval | | | 5/11/2015 | | PASS |
|
|
|
|
Application received | | | 5/8/2015 | | DONE |
|
|
|
Application submitted via PDS Online on May 8 2015 4:44PM
|