Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD15-01583
StatusFinaled
Name BOISE BUILDING CO
Site Address 421 S CURTIS RD Unit: 5
Project Name 
Customer Number 
ePlanReviewNo
Description
DO NOT ISSUE A PERMANENT C.O. ON THIS PROPERTY (TCO ONLY) PER JASON BLAIS. Permit for the construction of a new 1,492 sq. ft., one story single family dwelling with 3 bedrooms, 2 bathrooms, approximately 415 sq. ft. of covered patio/porch and a 483 sq. ft. attached garage per the approved plans, ResCheck, ACCA report and any notations. R-2 zoning and setbacks per planning. //leg
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/11/20179/11/20179/11/2017PPASS
DetailsMike Jordan
as per Jason Blais-cnditions have been met and perm C of O can be issued Phone #: ###-####
Print Occupancy Form  9/11/2017 DONE
Letter of compliance/Occupancy  9/11/2017 DONE
as per Jason Blais temp C of O conditions have been met
CHANGE STATUS TO (FNL)  9/11/2017 DONE
as per Jason Blais temp C of O conditions have been met
BLD-Aging Inspection8/30/20178/30/20178/30/2017 PEND
DetailsMike Jordan
Temporary Occupancy7/11/201710/9/20177/11/2017 DONE
DetailsCandy A. Nichols
Jason Blais ok'd extension of Temp C of O
Telephone call  7/10/2017 DONE
emailed Jessica about the temp c of o
Telephone call  7/6/2017 DONE
emailed Jessica that the temp c of o has expired and needs a final or they need to request and extension
BLD-Aging Inspection6/30/20176/30/20176/30/2017 PEND
DetailsMike Jordan
Telephone call  6/20/2017 DONE
emailed Lori that the temp c of o was expired and that she needed to email Jason Blais or call in the final to get the perm c of o
Telephone call  6/7/2017 DONE
emailed Lori that temp c of o will expire on 6/19/17
Temporary Occupancy3/27/20176/25/20173/27/2017 DONE
DetailsCandy A. Nichols
as per Jason B-ok to extend good thru June 19, 2017
Telephone call  3/22/2017 DONE
emailed Lori that the temp c of o is expired-asked if they're not ready for the final- cfan they please request another extension
BLD-Aging Inspection2/13/20172/13/20172/13/2017 PEND
DetailsMike Jordan
Temporary Occupancy1/6/20174/6/20171/6/2017 DONE
DetailsCandy A. Nichols
Jason Nlai approved an extension for 90 days 12/18/16
BLD-Aging Inspection12/14/201612/14/201612/14/2016 PEND
DetailsMike Jordan
Temporary Occupancy9/19/201612/18/20169/19/2016 DONE
DetailsCandy A. Nichols
Pending Water line & hydrant being put in for Suez Water
Temporary Occupancy9/19/201612/18/20169/19/2016 DONE
DetailsCandy A. Nichols
CHANGE STATUS TO (ISS)  9/19/2016 DONE
changed from FNL to ISS until the permanent water line and hydrant are in with Suez Water
BLD-Final10/30/201511/2/201511/2/2015PPART
DetailsPhil Shearer
call for access; Tad Phone #: ###-####
DOC - Permit Finaled11/2/201511/2/201511/2/2015PPART
DetailsPhil Shearer
as per Phil Shearer-no final (C of O) until permanent water line and hydrant is in with Suez Water
Telephone call  10/23/2015 DONE
called John to let know he needs to come pick up plan mod plans. left message-also told him we were putting the permit on hold
BLD-Wall Bracing8/24/20158/25/20158/25/2015PPASS
DetailsPhil Shearer
Ted Phone #: ###-####
BLD-Energy code compliance8/19/20158/19/20158/19/2015PPASS
DetailsPhil Shearer
Tad Phone #: ###-#### Inspection requested via web by Tad Duby
BLD-Energy code compliance8/18/20158/19/20158/19/2015APASS
DetailsPhil Shearer
Insulation // Pad Phone #: ###-####
BLD-Framing/Rough-in8/14/20158/17/20158/17/2015APASS
DetailsPhil Shearer
Pat Phone #: ###-####
BLD-Framing/Rough-in8/13/20158/14/20158/14/2015ANR
DetailsPhil Shearer
Tad Phone #: ###-####
BLD-Other8/7/20158/7/20158/7/2015PPASS
DetailsPhil Shearer
fire rated sofits; Tad Phone #: ###-####
BLD-Wall Bracing7/27/20157/28/20157/28/2015APASS
DetailsPhil Shearer
Tad Phone #: ###-####
Issue PAID IN FULL permit  7/27/2015 DONE
permit was paid for but not issued, issued and scheduled inspections
BLD-Foundation7/6/20157/7/20157/7/2015APART
DetailsPhil Shearer
Heron Phone #: ###-####
OVERRIDE  7/6/2015  
Telephone call  7/6/2015 DONE
Call to John that his Plan Mod is ready and no fees are due.
Routing - PLAN CHECK7/3/2015 7/6/2015 PASS
DetailsTisha Gallop
flipped same house on lot; routed to planning
Routing - PLANNING7/3/2015 7/6/2015 PASS
DetailsSue Cummings
flipped house on lot. Still O.K.
PLANS/APPL TAKEN TO FRONT DESK  7/6/2015 DONE
DetailsTisha Gallop
Case Summary (BLD)  7/6/2015 DONE
Plan assigned to (LEG) Tisha7/3/2015 7/6/2015 DONE
DetailsTisha Gallop
plan modification
Permit Ready to Issue  7/6/2015  
***DO NOT REISSUE PLAN MOD***
Plan resubmittals received  6/30/2015 DONE
Received two sets of full size plans and one 8x10 size- put on Tisha's desk
BLD-Footing6/26/20156/26/20156/26/2015PPART
DetailsPhil Shearer
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
Issue PAID IN FULL permit  6/19/2015 DONE
OVERRIDE  6/17/2015  
Inspection Record Card- Bld  6/17/2015 DONE
Telephone call  6/17/2015 DONE
Left message for John letting him know that we need a letter or receipt from ACHD to determine their impact fees before we can issue the permit
Case Summary (BLD)  6/17/2015 DONE
Routing - PLAN CHECK6/17/2015 6/17/2015 PASS
DetailsTisha Gallop
PLANS/APPL TAKEN TO FRONT DESK  6/17/2015 DONE
Permit Ready to Issue  6/17/2015 DONE
NEED letter or receipt from ACHD about impact fees-- in Brook View Sub. see email from Rita--- DO NOT ISSUE UNTIL RECEIVE THIS INFO
Plan assigned to (LEG) Tisha5/12/2015 6/17/2015 DONE
DetailsTisha Gallop
1st review 5/24; plan check
Routing - PLAN CHECK5/21/2015 5/24/2015 FAIL
DetailsTisha Gallop
1st review completed  5/24/2015 FAIL
Routing - MECHANICAL5/21/2015 5/21/2015 PASS
DetailsTroy James
Routing - MECHANICAL  5/21/2015 FAIL
emailed corrections to western heating
Routing - Addressing5/12/2015 5/14/2015 PASS
DetailsJason C. Taylor
Routing - PUBLIC WORKS5/14/2015 5/14/2015 PASS
DetailsConnie Baumgartner
Routing - PLANNING5/14/2015 5/14/2015 PASS
DetailsSue Cummings
Plans ACCEPTED BY PLAN TECH  5/12/2015 DONE
Intake Approval  5/12/2015 PASS
Recd Pcfee & Taken To Pln CK  5/12/2015 DONE
Application received 5/12/2015