Third Notice | | 9/20/2015 | 10/1/2015 | | DONE |
|
|
|
This permit finaled on the web by Richard Schultz
|
Second Notice | | 8/21/2015 | 9/15/2015 | | DONE |
|
|
|
Mailed 9/16/15
|
First Notice | | 7/27/2015 | 8/11/2015 | | DONE |
|
|
|
Mailed 8-11
|
Permanent Occupancy | | | 7/17/2015 | | DONE |
|
|
|
|
BLD-Final | 7/14/2015 | 7/15/2015 | 7/15/2015 | P | PASS |
Mike Jordan
|
|
|
Thanks Matt, Phone #: ###-#### Inspection requested via web by Richard Schultz. Ok for perm occ.
|
FIRE-Final Inspection | 7/14/2015 | 7/15/2015 | 7/15/2015 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 7/13/2015 | 7/14/2015 | 7/14/2015 | A | CANC |
Troy Cobbley
|
|
|
Thanks Matt, Phone #: ###-#### Inspection requested via web by Richard Schultz
|
BLD-Ceiling Grid Inspection | 7/2/2015 | 7/2/2015 | 7/2/2015 | P | PART |
Mike Jordan
|
|
|
Thanks Matt Phone #: ###-#### Inspection requested via web by Richard Schultz. grid ok, pending electrical and mech. rough in inspections.
|
BLD-Framing/Rough-in | 6/8/2015 | 6/8/2015 | 6/8/2015 | P | PASS |
Mike Jordan
|
|
|
Matt Phone #: ###-####. Interior steel stud framed walss and hardlids only.
|
Issue PAID IN FULL permit | | | 6/1/2015 | | DONE |
Christina Prado
|
|
|
|
Print Occupancy Form | | | 6/1/2015 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 5/20/2015 | | |
|
|
|
|
Plan assigned to (AJS) | 5/18/2015 | 5/18/2015 | 5/20/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
Mathnasium TI
|
Routing - PLAN CHECK | 5/18/2015 | | 5/20/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing PW Sewer Rating | 5/18/2015 | | 5/20/2015 | | PASS |
Jennifer Bruner
|
|
|
signed off in e plan
|
1st review completed | | | 5/20/2015 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/20/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/20/2015 | | DONE |
Christina Prado
|
|
|
Need GC, RP & Revised Certificate of Value
|
Routing - Design Review | 5/18/2015 | | 5/18/2015 | | PASS |
Sarah Schafer
|
|
|
|
Routing - Addressing | 5/18/2015 | | 5/18/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 5/18/2015 | | 5/18/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Intake Approval | | | 5/18/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Application received | | | 5/15/2015 | | DONE |
|
|
|
Application submitted via PDS Online on May 15 2015 2:27PM
|