BLD-Final | 3/31/2016 | 4/1/2016 | 4/1/2016 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
DOC - Permit Finaled | 4/1/2016 | 4/1/2016 | 4/1/2016 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Energy code compliance | 2/5/2016 | 2/8/2016 | 2/8/2016 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 2/2/2016 | 2/4/2016 | 2/4/2016 | A | PEND |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall. pending fireplace rough in
|
BLD-Wall Bracing | 1/12/2016 | 1/12/2016 | 1/12/2016 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Foundation | 10/7/2015 | 10/7/2015 | 10/7/2015 | P | PASS |
Phil Shearer
|
|
|
Phone #: ###-####
|
BLD-Footing | 10/5/2015 | 10/6/2015 | 10/6/2015 | P | PASS |
Phil Shearer
|
|
|
Sergio Phone #: ###-####
|
BLD-Foundation | 8/25/2015 | 8/26/2015 | 8/26/2015 | P | PASS |
Phil Shearer
|
|
|
Inspection request time 12:30 Phone #: ###-#### Inspection requested via web by tony L
|
BLD-Foundation | 8/25/2015 | 8/25/2015 | 8/25/2015 | P | NR |
Phil Shearer
|
|
|
Inspection request time 3:30 Phone #: ###-#### Inspection requested via web by tony L
|
BLD-Footing | 8/24/2015 | 8/24/2015 | 8/24/2015 | P | PASS |
Phil Shearer
|
|
|
inspection request time 2:00 Phone #: ###-#### Inspection requested via web by tony L
|
Issue PAID IN FULL permit | | | 8/11/2015 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 6/1/2015 | | |
|
|
|
|
Inspection Record Card- Bld | | | 6/1/2015 | | DONE |
|
|
|
|
Telephone call | | | 6/1/2015 | | DONE |
|
|
|
Call to Leonard
|
Permit Ready to Issue | | | 6/1/2015 | | DONE |
|
|
|
requirements met
|
Plan assigned to (JG) | 5/29/2015 | 5/29/2015 | 5/29/2015 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 5/29/2015 | | DONE |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 5/29/2015 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/29/2015 | | DONE |
|
|
|
|
Plan assigned to (LEG) Tisha | | | 5/29/2015 | | DEFR |
Tisha Gallop
|
|
|
5/29
|
Routing - PLAN CHECK | 5/27/2015 | | 5/29/2015 | | PASS |
Javier Guzman
|
|
|
|
Routing - PUBLIC WORKS | 5/20/2015 | | 5/29/2015 | | PASS |
Jennifer Bruner
|
|
|
signed off in PW review report by Jennifer Bruner
|
Routing - MECHANICAL | 5/21/2015 | | 5/27/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | | | 5/21/2015 | | PASS |
|
|
|
|
Routing - Addressing | 5/19/2015 | | 5/20/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/19/2015 | | DONE |
|
|
|
|
Intake Approval | | | 5/19/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/19/2015 | | DONE |
|
|
|
|
Application received | | | | | |
|
|
|
|