BLD-Final | 12/9/2015 | 12/10/2015 | 12/10/2015 | A | NR |
Dave Hannah
|
|
|
If no answer please try ###-#### Thank You. Phone #: ###-#### Inspection requested via web by Rock Self
|
FIRE-Final Inspection | 12/9/2015 | 12/9/2015 | 12/9/2015 | P | PASS |
Jim Page
|
|
|
Fire alarm inspection complete, no fire sprinklers. Life fire safety inspection passed/complete
|
BLD-Ceiling Grid Inspection | 11/28/2015 | 11/30/2015 | 11/30/2015 | A | PASS |
Dave Hannah
|
|
|
If no answer please call ###-#### Thank You Phone #: ###-#### Inspection requested via web by Rock Self
|
Issue PAID IN FULL permit | | | 6/4/2015 | | DONE |
|
|
|
|
Plan assigned to (AJS) | 5/20/2015 | 5/20/2015 | 5/27/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed SLHS
|
Routing - PLAN CHECK | 5/27/2015 | | 5/27/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Case Summary (BLD) | | | 5/27/2015 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/27/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/27/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/27/2015 | | DONE |
Christina Prado
|
|
|
Need GC Form and Revised Cert of Value
All requirements met
|
Telephone call | | | 5/27/2015 | | DONE |
|
|
|
called Scott to let permit is ready and that we need the GC and rev cert of val
|
1st review completed | | | 5/26/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 5/19/2015 | | 5/26/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Plan assigned to (TLW) | 5/19/2015 | | 5/20/2015 | | DEFR |
Tim L. Woodard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/19/2015 | | DONE |
|
|
|
|
Intake Approval | | | 5/19/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/19/2015 | | DONE |
|
|
|
|
Application received | | 5/19/2015 | | | |
|
|
|
|