Second Notice | | 11/19/2015 | 12/24/2015 | | DONE |
|
|
|
This permit finaled on the web by Curtis Weedop
|
First Notice | 10/7/2015 | 10/7/2015 | 11/9/2015 | | DONE |
Dave Hannah
|
|
|
Mailed 11-10-15
|
BLD-Final | 10/6/2015 | 10/7/2015 | 10/7/2015 | A | PASS |
Dave Hannah
|
|
|
Jay Phone #: ###-####
|
DOC - Permit Finaled | 10/7/2015 | 10/7/2015 | 10/7/2015 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 9/23/2015 | 9/23/2015 | 9/23/2015 | P | PASS |
Jim Page
|
|
|
Life fire safety passed/complete
|
BLD-Framing/Rough-in | 8/28/2015 | 8/31/2015 | 8/31/2015 | A | PASS |
Dave Hannah
|
|
|
would like call ahead; Jay Phone #: ###-####
|
BLD-Framing/Rough-in | 8/10/2015 | 8/11/2015 | 8/11/2015 | A | PASS |
Dave Hannah
|
|
|
Jay Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/4/2015 | | DONE |
|
|
|
|
Plan assigned to (AJS) | 5/20/2015 | 5/20/2015 | 5/27/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed SLHS
|
1st review completed | | | 5/27/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 5/27/2015 | | 5/27/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Case Summary (BLD) | | | 5/27/2015 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/27/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 5/27/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/27/2015 | | DONE |
Christina Prado
|
|
|
need GC and rev cert of val
All requirements met
|
Telephone call | | | 5/27/2015 | | DONE |
|
|
|
Spoke with Scott and informed him what was needed. He said he will speak with Curtis
|
Routing - PLAN CHECK | 5/19/2015 | | 5/27/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
emialed Scott 5/27/15
Scott, I have completed the review for BLD15-01689.
In order to approve the plans please provide a completed #310 special inspection form completed by the engineer of record and signed by the building owner. As no revised drawings are necessary you can email me this completed form.
Thank you
Adele Schaffeld-Griffin
Plans Examiner II
Planning and Development Services
City of Boise
###-####
|
Plan assigned to (TLW) | 5/19/2015 | | 5/20/2015 | | DEFR |
Tim L. Woodard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/19/2015 | | DONE |
|
|
|
|
Intake Approval | | | 5/19/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/19/2015 | | DONE |
|
|
|
|
Application received | | 5/19/2015 | | | |
|
|
|
|