Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD15-01729
StatusFinaled
Name RRC CONTRACTORS
Site Address 755 W FRONT ST Unit: 200
Project NameQuest Groups LLC T.I.
Customer Number 
ePlanReviewYes
Description
(QUEST GROUP LLC)(SUITE 200) OCCUPANCY OF PATIO IS EXCUDED/DEFERRED FROM THIS PERMIT. Permit to convert an existing second floor tenant space with perimeter offices to an open-office plan. Remove walls to create lounge spaces; add accent wall features; new paint and carpet throughout. Mechanical engineer to redesign the ventilation and mechanical inspector to verify the balance report. Previously occupied under BLD06-01831. This building is fully fire sprinklered with an approved fire alarm system. Separate permits will be required for any necessary modifications to the building fire protection systems; as regulated by the Fire Department.**ajs**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice 1/22/20161/20/2016 DONE
This permit finaled on the web by derek cooper
First Notice 1/8/20161/12/2016 DONE
Mailed 1-13-16
Permanent Occupancy  12/29/2015 DONE
BLD-Final9/28/20159/28/20159/28/2015PPASS
DetailsMike Jordan
Zach Phone #: ###-####. Ok for perm occ.
BLD-Final9/24/20159/25/20159/25/2015ANR
DetailsMike Jordan
Zach Phone #: ###-####. Needs plumbing final first.
FIRE-Final Inspection8/13/20158/14/20158/14/2015PPASS
DetailsJim Page
Life fire safety passed/complete
BLD-Final8/13/20158/14/20158/14/2015PPART
DetailsDave Hannah
Zack Phone #: ###-#### ok for temp occ phase one
FIRE-Final Inspection8/12/20158/13/20158/13/2015PCANC
DetailsJim Page
Spoke to on-site point of contact, Dex Phone #: ###-####, informed him the the FIR permit for fire alarms is still in review status, cannot perform life fire safety inspection until alarms FIR is issued and the fire alarm system passes inspection.
BLD-Wall cover7/31/20157/31/20157/31/2015PPASS
DetailsDave Hannah
Zack Phone #: ###-####
BLD-Conference7/24/20157/24/20157/24/2015PDONE
DetailsDave Hannah
Zach Phone #: ###-####
FIRE-Conference7/24/20157/24/20157/24/2015PDONE
DetailsJim Page
Zach Phone #: ###-####, informed me that the tenant that will be occupying this space is being "Kicked Out" of their current tenant space at the end of next week. He is requesting that we approve them to occupy half of the space after August 1st, providing that the half they occupy is inspected and those area’s pass inspection. I instructed Zach that I will talk to Scott Arellano about the issue, and that I did not have the authority to give an approval. Zach instructed to me that he will be calling in inspections next week for the area's they are requesting to occupy.
BLD-Conference7/8/20157/8/20157/9/2015ADONE
DetailsJim Page
Spoke to point of contact for project, Zach Phone #: ###-####. Had questions on the fire alarm horn strobe locations, did not see an alarm FIR permit for this project at time of this conference, instructed Zach that an alarm contractor will need to be contacted and an alarm permit issued for this project.
Print Occupancy Form  6/24/2015 DONE
Issue PAID IN FULL permit  6/24/2015 DONE
Plan assigned to (AJS)5/27/20155/27/20156/16/2015 PASS
DetailsAdele J Schaffeld-Griffin
1st review completed Quest Groups LLC
Routing - PLAN CHECK6/16/2015 6/16/2015 PASS
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  6/16/2015 DONE
Permit Ready to Issue  6/16/2015 DONE
DetailsChristina Prado
Need GC & Revised certificate of value for issuance
1st review completed  6/9/2015 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - PLAN CHECK5/27/2015 6/9/2015 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - FIRE5/27/20155/27/20156/2/2015 PASS
DetailsScott Arellano
Attached comments to plans.
Routing - MECHANICAL5/27/2015 6/2/2015 PASS
DetailsTroy James
See discription and floor plan for mechanical requirements.
Routing - Addressing5/27/2015 5/27/2015 PASS
DetailsEmily Dixon
Routing - PUBLIC WORKS5/27/2015 5/27/2015 PASS
DetailsBeverly Mountain
Intake Approval  5/27/2015 PASS
DetailsAdele J Schaffeld-Griffin
Intake Approval  5/26/2015 FAIL
DetailsAdele J Schaffeld-Griffin
The check list that us uploaded has not been completed. Please complete the check list. The pre screen will be done once it is received.
Please upload the 304 form.
Application received  5/21/2015 DONE
Application submitted via PDS Online on May 21 2015 4:53PM