BLD-Conference | 12/5/2016 | 12/6/2016 | 12/6/2016 | A | PART |
Dave Hannah
|
|
|
Call 15minutes before // TJ Phone #: ###-#### ok to sheetrock garage also needs to vent roof.
|
BLD-Conference | 10/31/2016 | 10/31/2016 | 11/1/2016 | P | PEND |
Tony Young
|
|
|
TJ Phone #: ###-####,,TJ is taking over job,, need to verify historical,, etc
|
BLD-Framing/Rough-in | 8/22/2016 | 8/23/2016 | 8/23/2016 | P | NR |
Tony Young
|
|
|
Mike Phone #: ###-####,, needs mech permit
|
BLD-Conference | 3/8/2016 | 3/9/2016 | 3/9/2016 | A | PASS |
Tony Young
|
|
|
Mandi Phone #: ###-####,, general ?s on permit
|
Meeting | | | 3/8/2016 | | DONE |
Christina Prado
|
|
|
Permits reverted back to homeowner as GC is no longer performing work. No inspections are to be called in by anyone other than homeowners Micheal & Mindi Hastings. Contact Christina with questions
|
BLD-Footing | 10/2/2015 | 10/2/2015 | 10/2/2015 | P | PART |
Tony Young
|
|
|
Phone #: ###-####,, work in progress
|
Routing Walk-In (Zoning) | 9/2/2015 | 9/2/2015 | 9/2/2015 | A | PASS |
Sue Cummings
|
|
|
modification to height- historic
|
Routing Walk-In (BLD) | 9/2/2015 | 9/2/2015 | 9/2/2015 | A | DONE |
David Ferguson
|
|
|
Height mod.
|
Plan assigned to (DAF) | 9/2/2015 | 9/2/2015 | 9/2/2015 | | PASS |
David Ferguson
|
|
|
Plan modification for the stemwall.
|
Inspection Record Card- Bld | | | 9/2/2015 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 9/2/2015 | | DONE |
|
|
|
|
(F) Reprint permit | | | 9/2/2015 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 9/2/2015 | | DONE |
|
|
|
received (2) sets of Wall Section Plans- (change in height)
|
Routing Walk-In (BLD) | 7/8/2015 | 7/8/2015 | 7/8/2015 | P | PASS |
Javier Guzman
|
|
|
|
Inspection Record Card- Bld | | | 7/8/2015 | | DONE |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 7/8/2015 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/8/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/8/2015 | | DONE |
|
|
|
all requirments met
|
Issue PAID IN FULL permit | | | 7/8/2015 | | DONE |
Christina Prado
|
|
|
|
Routing Walk-In (Zoning) | 6/19/2015 | 6/19/2015 | 6/19/2015 | A | PASS |
Matthew A Halitsky
|
|
|
|
Routing Walk-In (BLD) | 6/19/2015 | 6/19/2015 | 6/19/2015 | A | FAIL |
Tisha Gallop
|
|
|
need more framing details, possible engineering
|
Routing Walk-In (Zoning) | 5/26/2015 | 5/26/2015 | 5/26/2015 | P | FAIL |
Sue Cummings
|
|
|
Submitted C of A application on 5/26/15. App. has not been approved yet
|
1st review completed | | | 5/26/2015 | | FAIL |
Javier Guzman
|
|
|
|
Application received | | 5/26/2015 | | | |
|
|
|
|