First Notice | | 10/2/2015 | 10/12/2015 | | DONE |
|
|
|
Mailed 10-13-15
|
Permanent Occupancy | | | 9/24/2015 | | DONE |
|
|
|
|
BLD-Final | 9/21/2015 | 9/22/2015 | 9/22/2015 | A | PASS |
Mike Jordan
|
|
|
Larry Phone #: ###-####. ok for perm occ.
|
Permanent Occupancy | | | 9/22/2015 | | DONE |
|
|
|
|
BLD-Final | 9/21/2015 | 9/21/2015 | 9/21/2015 | P | DEFR |
Phil Shearer
|
|
|
Larry Phone #: ###-####. Out of time
|
Zoning Approval | 9/18/2015 | 9/18/2015 | 9/18/2015 | | DONE |
Matthew A Halitsky
|
|
|
OK per Sarah Schafer.
|
FIRE-Final Inspection | 9/16/2015 | 9/16/2015 | 9/16/2015 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Conference | 9/8/2015 | 9/8/2015 | 9/8/2015 | P | DONE |
Jim Page
|
|
|
Conference complete, ready for final inspection to be scheduled by contractor.
|
Issue PAID IN FULL permit | | | 6/15/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 6/15/2015 | | DONE |
|
|
|
|
Plan assigned to (AJS) | 5/27/2015 | 5/27/2015 | 6/8/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
MY REVIEW COMPLETED Great Western BBQ Supply
|
Routing - Design Review | 6/4/2015 | | 6/8/2015 | | PASS |
Matthew A Halitsky
|
|
|
Per DRH15-00178.
|
1st review completed | | | 6/8/2015 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/8/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/8/2015 | | DONE |
|
|
|
Need GC form and Certificate of Value
ALL REQUIREMENTS MET. OWNER IS LETTING LARRY ROSE ACT AS THE GC
|
Routing - PLAN CHECK | 5/27/2015 | | 6/4/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - Addressing | 5/27/2015 | | 5/28/2015 | | PASS |
Emily Dixon
|
|
|
|
Application received | | | 5/27/2015 | | DONE |
|
|
|
Application submitted via PDS Online on May 27 2015 10:55AM
|
Intake Approval | | | 5/27/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PUBLIC WORKS | 5/27/2015 | | 5/27/2015 | | PASS |
Jennifer Bruner
|
|
|
|