BLD-Final | 9/11/2015 | 9/11/2015 | 9/11/2015 | P | PASS |
Jim Sly
|
|
|
Mika Phone #: ###-####
|
DOC - Permit Finaled | 9/11/2015 | 9/11/2015 | 9/11/2015 | P | PASS |
Jim Sly
|
|
|
|
CHANGE STATUS TO (ISS) | | | 9/2/2015 | | DONE |
|
|
|
|
(F) Reprint permit | | | 9/2/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 8/27/2015 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/27/2015 | | DONE |
|
|
|
|
Telephone call | | | 8/27/2015 | | DONE |
|
|
|
called Biltmore- told secretary permit is ready and fees due
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/27/2015 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 8/27/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/27/2015 | | DONE |
|
|
|
DO NOT REISSUE ALL REQUIREMENTS MET
|
Plan assigned to (LEG) Tisha | 8/19/2015 | | 8/27/2015 | | DONE |
Tisha Gallop
|
|
|
8/19 plan mod; same house new lot routing to all depts
|
Routing - PLAN CHECK | 8/25/2015 | | 8/27/2015 | | PASS |
Tisha Gallop
|
|
|
|
Routing - MECHANICAL | 8/21/2015 | | 8/25/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 8/20/2015 | | 8/21/2015 | | PASS |
Josh Wilson
|
|
|
|
Routing - Addressing | 8/19/2015 | | 8/20/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 8/20/2015 | | 8/20/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Plan Modification Accepted | | | 8/19/2015 | | DONE |
|
|
|
received complete set of plans and documents. house was permitted and constructed on the incorrect lot. address was changed to reflect the correct address the house is being built on
|
BLD-Energy code compliance | 7/22/2015 | 7/23/2015 | 7/23/2015 | A | PASS |
Jim Sly
|
|
|
Mike Phone #: ###-####
|
BLD-Framing/Rough-in | 7/21/2015 | 7/21/2015 | 7/21/2015 | P | PASS |
Jim Sly
|
|
|
Mike Phone #: ###-####
|
BLD-Wall Bracing | 7/16/2015 | 7/17/2015 | 7/17/2015 | A | PASS |
Jim Sly
|
|
|
Austin Phone #: ###-####
|
BLD-Wall Bracing | 7/7/2015 | 7/8/2015 | 7/8/2015 | A | PASS |
Jim Sly
|
|
|
Austin Phone #: ###-####
|
BLD-Foundation | 6/22/2015 | 6/23/2015 | 6/24/2015 | P | PASS |
Jim Sly
|
|
|
Dane Phone #: ###-####
|
BLD-Foundation | 6/22/2015 | 6/23/2015 | 6/23/2015 | A | PASS |
Jim Sly
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 6/19/2015 | 6/22/2015 | 6/22/2015 | P | PASS |
Tony Young
|
|
|
Dane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/17/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 6/12/2015 | | |
|
|
|
|
Telephone call | | | 6/12/2015 | | DONE |
|
|
|
called Kevin- to let know permit is ready and how much is owed-left message on his phone
|
Routing - PLAN CHECK | 6/9/2015 | | 6/12/2015 | | PASS |
Tisha Gallop
|
|
|
|
Case Summary (BLD) | | | 6/12/2015 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/12/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/12/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/12/2015 | | DONE |
|
|
|
All Requirements Met
|
Plan assigned to (LEG) Tisha | 5/27/2015 | | 6/12/2015 | | DONE |
Tisha Gallop
|
|
|
1st review 6/8; plan check
|
Plan resubmittals received | | | 6/9/2015 | | DONE |
|
|
|
Two copies of sheets A-1, A-2, A-3, A-4, A-5, A-6 and A-7. Taken to Tisha
|
Routing - PLAN CHECK | 6/5/2015 | | 6/8/2015 | | FAIL |
Tisha Gallop
|
|
|
|
1st review completed | | | 6/8/2015 | | FAIL |
|
|
|
|
Routing - MECHANICAL | 5/29/2015 | | 6/5/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 5/28/2015 | | 5/29/2015 | | PASS |
Josh Wilson
|
|
|
Ok per DRH13-00339.
|
Routing - Addressing | 5/27/2015 | | 5/28/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 5/28/2015 | | 5/28/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 5/27/2015 | | DONE |
|
|
|
|
Intake Approval | | | 5/27/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/27/2015 | | DONE |
|
|
|
|
Application received | | 5/27/2015 | | | |
|
|
|
|