Print Statement | | | 10/18/2016 | | DONE |
|
|
|
|
Third Notice | | 9/24/2016 | 10/10/2016 | | DONE |
|
|
|
sent with a letter
|
Third Notice | | 8/16/2016 | 9/19/2016 | | DONE |
|
|
|
|
Third Notice | | 7/16/2016 | 8/11/2016 | | DONE |
|
|
|
|
Third Notice | | 6/15/2016 | 7/11/2016 | | DONE |
|
|
|
|
Second Notice | | 5/21/2016 | 6/10/2016 | | DONE |
|
|
|
Mailed 6-13-16
|
First Notice | | 4/28/2016 | 5/11/2016 | | DONE |
|
|
|
mailed 5/12/16
|
BLD-Final | 4/18/2016 | 4/18/2016 | 4/18/2016 | P | DONE |
Jim Sly
|
|
|
Ok per Jim Sly
|
Permanent Occupancy | | | 4/18/2016 | | DONE |
|
|
|
|
FIRE-Final Inspection | 4/4/2016 | 4/4/2016 | 4/4/2016 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
PubWorks Occupancy Approval | 3/25/2016 | 3/25/2016 | 3/25/2016 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 3/23/2016 | 3/24/2016 | 3/24/2016 | P | CANC |
Jim Sly
|
|
|
Bill Phone #: ###-####
|
BLD-Final | 3/23/2016 | 3/25/2016 | 3/24/2016 | A | PART |
Jim Sly
|
|
|
Bill Phone #: ###-#### OK for Temp. Occ. OK for Perm Occ when Fire perms.
|
Zoning Approval | 3/24/2016 | 3/24/2016 | 3/24/2016 | | PASS |
Josh Wilson
|
|
|
|
BLD-Final | 3/22/2016 | 3/23/2016 | 3/23/2016 | P | NR |
Jim Sly
|
|
|
Bill Phone #: ###-#### Need Zoning Note.....Fire Temp.
|
FIRE-Final Inspection | 3/22/2016 | 3/23/2016 | 3/23/2016 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy is being given with Romeo's permission until the LP dispencer has been reviewed/approved by the Fire Dept. All other corrections have been addressed.
|
BLD-Final | 3/15/2016 | 3/16/2016 | 3/16/2016 | P | CANC |
Jim Sly
|
|
|
Phone #: ###-#### Inspection cancelled from web by: Letitia Gallop // did not want to reschedule at this time
|
FIRE-Final Inspection | 3/15/2016 | 3/16/2016 | 3/16/2016 | A | FAIL |
Troy Cobbley
|
|
|
Need single action hardware on the west and the east facing double doors (door schedule was unavailable), need address numbers, need fencing/gates installed, need pavement installed, need operational permits from fire dept., need signage at the fill station. See the redlines on the fire dept plan review comments for all corrections needed.
|
BLD-Framing/Rough-in | 2/10/2016 | 2/11/2016 | 2/11/2016 | A | PART |
Jim Sly
|
|
|
Bill Phone #: ###-#### Framing on wash bay and canopy on wash bay....OK
|
BLD-Energy code compliance | 12/22/2015 | 12/22/2015 | 12/22/2015 | P | PASS |
Jim Sly
|
|
|
Nate Phone #: ###-####
|
BLD-Framing/Rough-in | 12/18/2015 | 12/21/2015 | 12/21/2015 | A | PASS |
Jim Sly
|
|
|
nate Phone #: ###-####
|
FIRE-Conference | 10/19/2015 | 10/19/2015 | 10/19/2015 | P | DONE |
Troy Cobbley
|
|
|
Discussed bollard placement with Nate. The bollards at either end are spaced too far apart and all of the bollards, per Nate, will be less than 3'-0" to the equipment which does not meet IFC 312
|
BLD-Foundation | 10/7/2015 | 10/8/2015 | 10/8/2015 | A | PASS |
Jim Sly
|
|
|
Nate Phone #: ###-#### OK pending MTI special insp, tests and approvals.
|
BLD-Footing | 10/2/2015 | 10/5/2015 | 10/5/2015 | P | PASS |
Jim Storey
|
|
|
Austin Phone #: ###-#### pending si report
|
Issue PAID IN FULL permit | | | 9/9/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/9/2015 | | DONE |
|
|
|
|
Plan resubmittals received | | | 8/27/2015 | | DONE |
|
|
|
resubmittals received 1 response letter and 2 sets of sheets C100, C200, C300, C400, C500, C600- Took to Carl M
|
OVERRIDE | | | 8/26/2015 | | |
|
|
|
|
Plan assigned to (CDM) | 6/23/2015 | 6/23/2015 | 8/26/2015 | | PASS |
Carl D Madsen
|
|
|
Level 3 TI - ePlanReview - Tates Rents
First review completed
|
Routing - Design Review | 8/5/2015 | | 8/26/2015 | | PASS |
Josh Wilson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/26/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/26/2015 | | DONE |
Christina Prado
|
|
|
***ALL REQUIRMENTS MET 9-9-15 //CEV Need Revised Certificate of value, GC form for issuance
|
Routing - FIRE | 8/5/2015 | 8/5/2015 | 8/11/2015 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans.
|
Routing - PLAN CHECK | 8/5/2015 | | 8/11/2015 | | PASS |
Carl D Madsen
|
|
|
|
Route to Impact Fee Review | 7/12/2015 | 7/15/2015 | 7/13/2015 | | PASS |
Cindy M. Gould
|
|
|
|
1st review completed | | | 7/12/2015 | | FAIL |
|
|
|
|
Routing PW Solid Waste | 6/24/2015 | | 7/12/2015 | | PASS |
Megan Durrell
|
|
|
E-Plan
|
Routing - PLAN CHECK | 6/23/2015 | | 7/12/2015 | | FAIL |
Carl D Madsen
|
|
|
|
Routing PW Drainage | 6/24/2015 | | 7/9/2015 | | PASS |
Jim Wyllie
|
|
|
|
Routing - Design Review | 6/23/2015 | | 7/2/2015 | | FAIL |
Josh Wilson
|
|
|
REvise Sheet L101 to provide a mix of coniferous and deciduous trees along shared property line with residence to north.
|
Routing - PUBLIC WORKS | 7/2/2015 | | 7/2/2015 | | PASS |
Jennifer Bruner
|
|
|
PW Drainage reassigned to BGM
|
Routing - FIRE | 6/23/2015 | 6/23/2015 | 6/26/2015 | | FAIL |
Scott Arellano
|
|
|
Report attached to case and emailed to architect.
|
Routing PW Sewer Rating | 6/24/2015 | | 6/25/2015 | | PASS |
|
|
|
|
Routing PW Environmental | 6/24/2015 | | 6/25/2015 | | PASS |
Rick Christenson
|
|
|
Sand and Oil Interceptor shown
|
Routing - PLUMBING | 6/23/2015 | | 6/25/2015 | | PASS |
Bill VanDegrift
|
|
|
see redline notes on sand and oil interceptor venting.
|
Routing - Addressing | 6/23/2015 | | 6/24/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 6/23/2015 | | 6/24/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 6/23/2015 | | 6/24/2015 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)
(TATES RENTS) To demolish portions of the building including an existing greenhouse, remodeling an existing 4,815 sq. ft. building for an equipment rental facility per approved plans. Scope will include site work, a propane filling station, complete interior remodel of existing building and the construction of a separate 1,672 sq. ft. wash bay/covered storage structure on the site.
|
Plan Reviewer's activity | | | 6/23/2015 | | DONE |
Jason Blais
|
|
|
Emailed architect to contact ACHD to evaluate if any additional impact fees are due. Written verification from ACHD shall be provided to our Permit Counter prior to the building permit being issued.
|
Plan Reviewer's activity | | | 6/23/2015 | | PASS |
|
|
|
Plan intake approved
|
Pending Assignment by JCB | 6/23/2015 | | 6/23/2015 | | DONE |
Jason Blais
|
|
|
|
Intake Approval | | | 6/23/2015 | | PASS |
Jason Blais
|
|
|
|
Intake Approval | | | 6/1/2015 | | FAIL |
|
|
|
(6-1-15) Please refer to the redlines on the plan intake checklist and resolve each item as noted.
|
Application received | | | 5/28/2015 | | DONE |
|
|
|
Application submitted via PDS Online on May 28 2015 8:39AM
|