BLD-Final | 9/28/2015 | 9/29/2015 | 9/29/2015 | A | PASS |
Mike Jordan
|
|
|
Brett Phone #: ###-####
|
DOC - Permit Finaled | 9/29/2015 | 9/29/2015 | 9/29/2015 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Energy code compliance | 8/10/2015 | 8/10/2015 | 8/10/2015 | P | PASS |
Mike Jordan
|
|
|
Dan Phone #: ###-####
|
BLD-Energy code compliance | 8/6/2015 | 8/7/2015 | 8/7/2015 | A | NR |
Mike Jordan
|
|
|
Dan Phone #: ###-####
|
BLD-Framing/Rough-in | 8/5/2015 | 8/6/2015 | 8/6/2015 | P | PASS |
Mike Jordan
|
|
|
Dan Phone #: ###-####
|
BLD-Wall Bracing | 7/30/2015 | 7/31/2015 | 7/31/2015 | A | DONE |
Mike Jordan
|
|
|
Brett Phone #: ###-####. inspection done yesterday.
|
BLD-Wall Bracing | 7/30/2015 | 7/30/2015 | 7/30/2015 | P | PASS |
Mike Jordan
|
|
|
All issues were resolved. ok to cover exterior.
|
BLD-Wall Bracing | 7/28/2015 | 7/29/2015 | 7/29/2015 | P | FAIL |
Mike Jordan
|
|
|
Early afternoon - Brett Phone #: ###-####. Install missing blocks and staple missed shear panels.
|
BLD-Foundation | 7/10/2015 | 7/13/2015 | 7/13/2015 | A | PART |
Mike Jordan
|
|
|
Dane-wall Phone #: ###-####
|
BLD-Footing | 7/9/2015 | 7/10/2015 | 7/10/2015 | P | PASS |
Mike Jordan
|
|
|
Jerry Phone #: ###-####
|
Issue PAID IN FULL permit | | | 6/30/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/30/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 6/26/2015 | | |
|
|
|
|
Plan assigned to (JG) | 6/17/2015 | 6/17/2015 | 6/26/2015 | | PASS |
Javier Guzman
|
|
|
1st review completed,
|
Routing - PLAN CHECK | 6/26/2015 | | 6/26/2015 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/26/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/26/2015 | | DONE |
|
|
|
all requirments met
|
Routing - PLAN CHECK | 6/24/2015 | | 6/24/2015 | | FAIL |
Javier Guzman
|
|
|
corrections not made
|
Routing PW Flood Plain | 6/18/2015 | | 6/23/2015 | | PASS |
Jim Wyllie
|
|
|
signed off in ePlan review by Jim Wyllie
|
1st review completed | | | 6/23/2015 | | FAIL |
|
|
|
ePlan was not routed to floodplain
|
Routing - PLAN CHECK | 6/2/2015 | | 6/18/2015 | | FAIL |
Javier Guzman
|
|
|
ePlan
|
Routing - PLANNING | 6/2/2015 | | 6/18/2015 | | PASS |
Sue Cummings
|
|
|
signed of with conditions in ePlan review by Sue Cummings
|
Plan assigned to (LEG) Tisha | 6/2/2015 | | 6/17/2015 | | DEFR |
Tisha Gallop
|
|
|
6/12 floodplain
|
Routing - MECHANICAL | 6/2/2015 | | 6/9/2015 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 6/2/2015 | | 6/2/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 6/2/2015 | | 6/2/2015 | | PASS |
Connie Baumgartner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/2/2015 | | DONE |
|
|
|
|
Intake Approval | | | 6/2/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/2/2015 | | DONE |
|
|
|
|
Application received | | | 6/1/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 1 2015 2:24PM
|