BLD-Final | 8/26/2016 | 8/26/2016 | 8/26/2016 | P | PASS |
Dave Hannah
|
|
|
Justin Phone #: ###-####
|
Zoning Approval | 8/26/2016 | 8/26/2016 | 8/26/2016 | | PASS |
Josh Wilson
|
|
|
|
PubWorks Occupancy Approval | 8/26/2016 | 8/26/2016 | 8/26/2016 | | DONE |
Jason C. Taylor
|
|
|
|
Print Occupancy Form | | | 8/26/2016 | | DONE |
|
|
|
|
Telephone call | | | 8/26/2016 | | DONE |
|
|
|
per Gary Cooper ok once Jason Tayler signs off-per Jason Tayler good for perm c of o
|
Permanent Occupancy | | | 8/26/2016 | | DONE |
|
|
|
|
Zoning Approval Temp | 7/13/2016 | 7/13/2016 | 7/13/2016 | | PASS |
Josh Wilson
|
|
|
|
BLD-Final | 5/26/2016 | 5/27/2016 | 5/27/2016 | A | PEND |
Dave Hannah
|
|
|
Exterior stair railing Inspection requested via web by Justin Toothman ok for temp ok for perm occ after pw and zoning oks
|
BLD-Final | 5/24/2016 | 5/26/2016 | 5/26/2016 | P | FAIL |
Mike Jordan
|
|
|
I need to schedule the Structural for Occupancy Phone #: ###-#### Inspection requested via web by Justin Toothman. HAndrail extensionsneed to return to ground or post. Everything else ok.
|
PubWorks Temp Occupancy Appr | 5/26/2016 | 5/26/2016 | 5/26/2016 | | DONE |
Tiffany Lowery
|
|
|
|
FIRE-Final Inspection | 5/13/2016 | 5/17/2016 | 5/17/2016 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete (FIR15-00701), final fire alarm inspection complete (FIR15-00849), final life fire safety inspection passed/complete.
|
BLD-Other | 5/10/2016 | 5/11/2016 | 5/11/2016 | A | DONE |
Dave Hannah
|
|
|
Conference prior to Final occupancy. Phone #: ###-#### Inspection requested via web by Justin Toothman
|
BLD-Aging Inspection | 3/22/2016 | 3/22/2016 | 3/28/2016 | | PEND |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 3/23/2016 | 3/23/2016 | 3/28/2016 | | PEND |
Dave Hannah
|
|
|
|
OVERRIDE | | | 1/19/2016 | | |
|
|
|
|
Plan assigned to (CDM) | 1/15/2016 | 1/15/2016 | 1/19/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 1/15/2016 | | 1/19/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing - MECHANICAL | 1/15/2016 | | 1/19/2016 | | PASS |
Troy James
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/19/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/19/2016 | | DONE |
Christina Prado
|
|
|
|
CHANGE STATUS TO (ISS) | | | 1/19/2016 | | DONE |
Christina Prado
|
|
|
|
Plan Modification Accepted | | | 1/15/2016 | | DONE |
Christina Prado
|
|
|
Plan mod requested for changes to the HVAC support and system
|
BLD-Other | 12/29/2015 | 12/30/2015 | 12/30/2015 | A | PASS |
Dave Hannah
|
|
|
Densglass west end building 3 - Fire life/safety? Inspection requested via web by Justin Toothman
|
BLD-Wall Bracing | 11/9/2015 | 11/9/2015 | 11/9/2015 | A | PASS |
Dave Hannah
|
|
|
|
BLD-Framing/Rough-in | 11/5/2015 | 11/6/2015 | 11/9/2015 | P | PEND |
Dave Hannah
|
|
|
Phone #: 2087211504 >> Inspection requested via mobile web by Justin Toothman shearwalls ok to cover
|
Place hold on job | 8/31/2015 | | 9/1/2015 | | DONE |
Carlos Velazquez
|
|
|
NO NOT ISSUE WITH BLD15-01846, BLD15-01847
|
Issue PAID IN FULL permit | | | 9/1/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/1/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 8/31/2015 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 8/31/2015 | | 8/31/2015 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 8/31/2015 | | 8/31/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/31/2015 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 8/31/2015 | | |
|
|
|
|
Permit Ready to Issue | | | 8/31/2015 | | DONE |
Christina Prado
|
|
|
Need Gc form & Rp for issuance, no new value as applicant is GC
|
Routing - PLANNING | 7/29/2015 | | 8/31/2015 | | PASS |
Susan Riggs
|
|
|
|
Plan assigned to (CDM) | 6/12/2015 | | 8/31/2015 | | PASS |
Carl D Madsen
|
|
|
First review completed
|
Routing - Design Review | 8/24/2015 | | 8/24/2015 | | PASS |
Josh Wilson
|
|
|
|
Routing - PLAN CHECK | 7/29/2015 | | 8/16/2015 | | FAIL |
Carl D Madsen
|
|
|
|
Routing Off Site - STRUCTURAL | 7/29/2015 | | 8/16/2015 | | FAIL |
Carl D Madsen
|
|
|
|
Routing PW Solid Waste | 6/15/2015 | | 8/16/2015 | | PASS |
Megan Durrell
|
|
|
|
Routing - Design Review | 8/3/2015 | | 8/3/2015 | | PASS |
Josh Wilson
|
|
|
Add six Vanderwolf Pines or Austrian Pines to the landcape buffer- redlines sheet L1.0
|
Routing - MECHANICAL | 7/29/2015 | | 7/30/2015 | | PASS |
Troy James
|
|
|
|
Routing - PUBLIC WORKS | 7/29/2015 | | 7/30/2015 | | PASS |
Beverly Mountain
|
|
|
|
Route to Impact Fee Review | 7/6/2015 | 7/9/2015 | 7/13/2015 | | PASS |
Cindy M. Gould
|
|
|
|
Routing - PLANNING | 6/12/2015 | | 7/6/2015 | | FAIL |
Susan Riggs
|
|
|
CUP14-00076 Fitness Center
CUP03-00066 Condo's
Bonding required for fitness center, parking stalls need to identify which condo they are associated with for the 40 condos with single-car garages. Fencing must be constructed along south aeaseroperty line prior to final inspection. Please see change marks on eplan.
|
Routing - Design Review | 7/6/2015 | | 7/6/2015 | | FAIL |
Josh Wilson
|
|
|
Design Review Modification to DRH03-00124 required.
|
1st review completed | | | 7/6/2015 | | FAIL |
|
|
|
|
Routing Off Site - STRUCTURAL | 6/12/2015 | | 7/6/2015 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 6/12/2015 | | 7/5/2015 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - FIRE | 6/12/2015 | | 6/23/2015 | | PASS |
Scott Arellano
|
|
|
Report attached to case
|
Routing - PLUMBING | 6/12/2015 | | 6/19/2015 | | PASS |
Daryl Spivey
|
|
|
DCVA approved for use for building backflow protection.
|
Routing - MECHANICAL | 6/12/2015 | | 6/17/2015 | | FAIL |
Troy James
|
|
|
|
Routing PW Sewer Rating | 6/15/2015 | | 6/17/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Drainage | 6/15/2015 | | 6/16/2015 | | PASS |
Brian Murphy
|
|
|
PREVIOUSLY APPROVED
|
Routing PW Sewer Design | 6/15/2015 | | 6/16/2015 | | PASS |
Kyle S. Rosenmeyer
|
|
|
All sewer mains are existing. No sewer extension is included in this permit.
|
Routing - PUBLIC WORKS | 6/12/2015 | | 6/15/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 6/12/2015 | | 6/12/2015 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to Earth Disturbance per BCC 8-17)
Bldg. 3: We are completing 4 remaining buildings. Bldg. 3 - 8 units, Bldg. 4 - 9 units, Bldg. 5 - 11 units, and Bldg. 6 - Rec. facility.
(FALLING BROOK CONDOS – Building #3) Permit is to construct a 8 unit 13,583 square foot residential apartment building.
|
Routing - PLANNING Land Div | 6/12/2015 | | 6/12/2015 | | PASS |
Dave Abo
|
|
|
Bulilding #3 of Falling Brook Condominiums
|
Routing - Addressing | 6/12/2015 | | 6/12/2015 | | PASS |
Emily Dixon
|
|
|
|
Pending Assignment by TLW | 6/12/2015 | | 6/12/2015 | | DONE |
Tim L. Woodard
|
|
|
|
Intake Approval | | | 6/9/2015 | | PASS |
Tim L. Woodard
|
|
|
|
Application received | | | 6/2/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 2 2015 9:06AM
|
First Notice | | 9/5/2016 | | | |
|
|
|
|