Letter of compliance/Occupancy | | | 1/25/2016 | | DONE |
|
|
|
|
Letter of compliance/Occupancy | | | 1/25/2016 | | DONE |
|
|
|
|
BLD-Final | 1/21/2016 | 1/21/2016 | 1/21/2016 | P | PASS |
Tony Young
|
|
|
Matt Phone #: ###-####
|
DOC - Permit Finaled | 1/21/2016 | 1/21/2016 | 1/21/2016 | P | PASS |
Tony Young
|
|
|
|
BLD-Energy code compliance | 10/5/2015 | 10/6/2015 | 10/6/2015 | P | PASS |
Dave Hannah
|
|
|
Change to PM per Matt // Insulation // Matt Phone #: ###-####
|
BLD-Framing/Rough-in | 9/28/2015 | 9/29/2015 | 9/29/2015 | A | PART |
Tony Young
|
|
|
Matt Phone #: ###-####,, need fire blocking,, ok to insulate
|
BLD-Wall Bracing | 8/25/2015 | 8/25/2015 | 8/25/2015 | P | PASS |
Tony Young
|
|
|
Matt Phone #: ###-####
|
BLD-Foundation | 6/29/2015 | 6/29/2015 | 6/29/2015 | P | PASS |
Tony Young
|
|
|
Avarro Phone #: ###-####
|
BLD-Footing | 6/18/2015 | 6/19/2015 | 6/19/2015 | A | PART |
Tony Young
|
|
|
Avarro Phone #: ###-####
|
BLD-Footing | 6/18/2015 | 6/18/2015 | 6/18/2015 | P | NR |
Tony Young
|
|
|
Avarro Phone #: ###-####
|
PubWorks Subgrade Approval | 6/11/2015 | 6/11/2015 | 6/11/2015 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
OVERRIDE | | | 6/5/2015 | | |
|
|
|
|
Routing Walk-In (BLD) | 6/5/2015 | 6/5/2015 | 6/5/2015 | P | PASS |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 6/5/2015 | | DONE |
Javier Guzman
|
|
|
|
Inspection Record Card- Bld | | | 6/5/2015 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/5/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/5/2015 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/5/2015 | | DONE |
|
|
|
|
Routing Walk-In (PW Hillside) | 6/4/2015 | 6/4/2015 | 6/4/2015 | A | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Routing Walk-In (Zoning) | 6/4/2015 | 6/4/2015 | 6/4/2015 | A | PASS |
Colleen T Carroll
|
|
|
deck posts cannot extend into 15' rear setback
|
Routing Walk-In (BLD) | 6/4/2015 | 6/4/2015 | 6/4/2015 | A | FAIL |
Javier Guzman
|
|
|
needs engineering for the new hillside footing
|
1st review completed | | | 6/4/2015 | | FAIL |
Javier Guzman
|
|
|
|
Application received | | 6/4/2015 | | | |
|
|
|
|