Second Notice | | 9/22/2016 | 10/18/2016 | | DONE |
|
|
|
Mailed 10-18-16
|
First Notice | | 9/11/2016 | 9/12/2016 | | DONE |
|
|
|
Mailed 9-13-16
|
Permanent Occupancy | | | 9/1/2016 | | DONE |
|
|
|
|
BLD-Final | 8/31/2016 | 8/31/2016 | 8/31/2016 | P | PASS |
Mike Jordan
|
|
|
Late PM Phone #: ###-####. Ok for perm occ.
|
BLD-Final | 8/29/2016 | 8/30/2016 | 8/30/2016 | A | PART |
Mike Jordan
|
|
|
Kent Phone #: ###-####. Ok for temp occ. Vertical grab bars mmounted incorrectly.
|
BLD-Final | 8/23/2016 | 8/23/2016 | 8/23/2016 | P | FAIL |
Phil Shearer
|
|
|
Kent// please call before Phone #: ###-####. Missing fire door at kitchen, ADA grab bars in restrooms.
|
FIRE-Final Inspection | 8/23/2016 | 8/23/2016 | 8/23/2016 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 8/19/2016 | 8/22/2016 | 8/22/2016 | A | CANC |
Jim Page
|
|
|
Inspection request will be rescheduled for 23AUG2016 to coincide with FIR sprinkler permit final inspection.
|
PubWorks Occupancy Approval | 8/12/2016 | 8/12/2016 | 8/12/2016 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval | 8/11/2016 | 8/11/2016 | 8/11/2016 | | PASS |
Josh Wilson
|
|
|
|
CHANGE STATUS TO (ISS) | | | 7/26/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/26/2016 | | DONE |
|
|
|
|
(F) Reprint permit | | | 7/26/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 6/23/2016 | | |
|
|
|
|
Plan assigned to (CDM) | 6/15/2016 | 6/15/2016 | 6/23/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 6/23/2016 | | 6/23/2016 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/23/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/23/2016 | | DONE |
|
|
|
DO NOT REISSUE PLAN MOD
|
Plan Modification Accepted | | | 6/15/2016 | | DONE |
Christina Prado
|
|
|
Plan mod for new statue placement
|
BLD-Other | 6/2/2016 | 6/6/2016 | 6/6/2016 | A | PASS |
Mike Jordan
|
|
|
would like call ahead; Brian Phone #: ###-####. base layer of 5/8 type x rock for roof/ceiling assembly ok.
|
BLD-Framing/Rough-in | 6/2/2016 | 6/2/2016 | 6/2/2016 | P | PASS |
Mike Jordan
|
|
|
Kent Phone #: ###-####
|
OVERRIDE | | | 5/16/2016 | | |
|
|
|
|
Plan assigned to (CDM) | 5/5/2016 | 5/5/2016 | 5/16/2016 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 5/11/2016 | | 5/16/2016 | | PASS |
Carl D Madsen
|
|
|
|
CHANGE STATUS TO (ISS) | | | 5/16/2016 | | DONE |
|
|
|
|
(F) Reprint permit | | | 5/16/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/16/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/16/2016 | | DONE |
|
|
|
plan mod fees due - DO NOT RE-ISSUE
|
Routing - MECHANICAL | 5/11/2016 | | 5/13/2016 | | PASS |
Troy James
|
|
|
|
Plan Modification Accepted | | | 5/5/2016 | | DONE |
Christina Prado
|
|
|
As requested by Arch firm to update review recent mechanical changes
|
BLD-Energy code compliance | 5/2/2016 | 5/2/2016 | 5/2/2016 | P | PASS |
Mike Jordan
|
|
|
would like call ahead; Kent Phone #: ###-####. Ok to sheet rock the public side only.
|
BLD-Energy code compliance | 4/19/2016 | 4/19/2016 | 4/19/2016 | P | PEND |
Mike Jordan
|
|
|
Kent Phone #: ###-####. Energy code ok. Pending resolution of mech. issues.
|
BLD-Conference | 4/18/2016 | 4/18/2016 | 4/18/2016 | A | DONE |
Mike Jordan
|
|
|
Went over Roof ceiling assembly with contractor.
|
BLD-Framing/Rough-in | 4/14/2016 | 4/14/2016 | 4/14/2016 | P | PASS |
Mike Jordan
|
|
|
Kent-early if possible Phone #: ###-####. All framing issues have been resolved. Ok to insulate. Advise Kent to reschedule mech. rough in inspection and noted to him the correction notice from mech. to resubmit plans.
|
BLD-Conference | 4/7/2016 | 4/7/2016 | 4/7/2016 | P | PEND |
Bill VanDegrift
|
|
|
needed contact number to tell contractor I left a correction notice for dampers.
|
BLD-Framing/Rough-in | 4/6/2016 | 4/7/2016 | 4/7/2016 | P | PART |
Mike Jordan
|
|
|
would like call ahead; Kent Phone #: ###-####. Transfer showers have been replaced and our now compliant. Anchor bolts installed on interior bearing walls. Fire dampers still need to be installed on resident/living side and plate washers on exterior shear walls.
|
BLD-Framing/Rough-in | 3/2/2016 | 3/3/2016 | 3/3/2016 | A | PART |
Mike Jordan
|
|
|
would like call 30min ahead; Kent Phone #: ###-####. . ok to insulate interior walls. Transfer shower issue not yet resolved. Provide fix from enginner of record on miising anchor bolts and interior bearing walls. BAthroom vent fans in residence require fire dampers. All other issues have been resolved.
|
BLD-Conference | 2/5/2016 | 2/8/2016 | 2/8/2016 | A | DONE |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 2/5/2016 | 2/5/2016 | 2/5/2016 | P | FAIL |
Mike Jordan
|
|
|
Kent Phone #: ###-####. Provide truss enginering for framing inspection. Providte the required48 inch clearance on transfer shower from control wall. Provide membrane penetration protection on can lights. Provide additional details on how to provide continous 1hr. protection on ceiling at archway. All penetrating items through the double top plates shall be protected with an approved 1hr. listed fire stop. Correction notice posted.
|
BLD-Framing/Rough-in | 12/29/2015 | 12/29/2015 | 12/29/2015 | P | NR |
Mike Jordan
|
|
|
Kent Phone #: ###-####. Needs sprinkler rough in inspection.
|
OVERRIDE | | | 12/28/2015 | | |
|
|
|
|
Plan assigned to (CDM) | 12/17/2015 | 12/17/2015 | 12/28/2015 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 12/28/2015 | | 12/28/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/28/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/28/2015 | | DONE |
Christina Prado
|
|
|
Plan mod approved, no fees due per CDM
|
CHANGE STATUS TO (ISS) | | | 12/28/2015 | | DONE |
Christina Prado
|
|
|
Plan mod approved, no fees due per CDM
|
Plan Modification Accepted | | | 12/17/2015 | | DONE |
|
|
|
|
BLD-Wall Bracing | 11/12/2015 | 11/12/2015 | 11/12/2015 | P | PASS |
Mike Jordan
|
|
|
Kent Phone #: ###-####. Exterior shear walls only ok.
|
BLD-Conference | 11/10/2015 | 11/12/2015 | 11/12/2015 | A | PART |
Mike Jordan
|
|
|
Ken Phone #: ###-####. Ok to set windows. No approved plans on site. contractor to recall inspection.
|
BLD-Footing | 10/29/2015 | 10/30/2015 | 10/30/2015 | A | PASS |
Mike Jordan
|
|
|
Jerry Phone #: ###-####
|
BLD-Energy code compliance | 9/23/2015 | 9/24/2015 | 9/24/2015 | A | PASS |
Mike Jordan
|
|
|
Insultaion // Rob Phone #: ###-####. Rigid insulation ok. Contacted rob to let him know that there is vegetation on interior portion of pad that will need to bo removed prior to backfilling.
|
BLD-Foundation | 9/21/2015 | 9/22/2015 | 9/22/2015 | P | PASS |
Mike Jordan
|
|
|
Jerry Phone #: ###-####
|
BLD-Footing | 9/18/2015 | 9/21/2015 | 9/21/2015 | P | PASS |
Mike Jordan
|
|
|
Jerry Phone #: ###-####
|
BLD-Conference | 9/16/2015 | 9/17/2015 | 9/17/2015 | A | DONE |
Mike Jordan
|
|
|
Jerry Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/11/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 9/9/2015 | | |
|
|
|
|
Plan assigned to (CDM) | 6/16/2015 | 6/16/2015 | 9/9/2015 | | PASS |
Carl D Madsen
|
|
|
First review completed
|
Routing - PLAN CHECK | 9/9/2015 | | 9/9/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/9/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/9/2015 | | DONE |
Christina Prado
|
|
|
Need GC, RP & Revised cert of value for issuance 9-10-15 received RP CAN
|
Routing - MECHANICAL | 8/10/2015 | | 9/9/2015 | | PASS |
Troy James
|
|
|
per E-Plan
|
Routing PW Drainage | 9/8/2015 | | 9/8/2015 | | PASS |
Brian Murphy
|
|
|
|
Routing - PUBLIC WORKS | 9/8/2015 | | 9/8/2015 | | PASS |
Beverly Mountain
|
|
|
|
Routing Off Site - STRUCTURAL | 8/10/2015 | | 8/17/2015 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 8/10/2015 | | 8/17/2015 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - Design Review | 8/10/2015 | | 8/14/2015 | | PASS |
Josh Wilson
|
|
|
Ok per revised site and landscape plans
|
Routing - FIRE | 8/10/2015 | 8/10/2015 | 8/13/2015 | | PASS |
Scott Arellano
|
|
|
Revised comments attached to case.
|
Routing PW Sewer Design | 8/10/2015 | | 8/12/2015 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing PW Drainage | 8/10/2015 | | 8/11/2015 | | FAIL |
Jason C. Taylor
|
|
|
needs geo depth to free draining stucture 10 feet? swale letter
|
Routing - PUBLIC WORKS | 8/10/2015 | | 8/10/2015 | | PASS |
Beverly Mountain
|
|
|
|
Route to Impact Fee Review | 7/21/2015 | 7/24/2015 | 7/23/2015 | | PASS |
Cindy M. Gould
|
|
|
|
Routing Off Site - STRUCTURAL | 6/16/2015 | | 7/21/2015 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 7/21/2015 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 6/16/2015 | | 7/21/2015 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - FIRE | 6/16/2015 | | 6/29/2015 | | FAIL |
Scott Arellano
|
|
|
Comments attached to case and emailed to architect.
|
Routing - MECHANICAL | 6/16/2015 | | 6/22/2015 | | FAIL |
Troy James
|
|
|
|
Routing - Erosion and Sediment | 6/16/2015 | | 6/18/2015 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to any Earth Disturbance)
(LING THU'U TEMPLE) New Religious Institution with associated Caretaker Residence on undeveloped site
|
Routing - Design Review | 6/16/2015 | | 6/17/2015 | | FAIL |
Josh Wilson
|
|
|
Sheet A.10 Relocate the ceremonail gate or reduce the overhang to protrude no more than 2 feet into the required 10 foot street setback.
Sheet LS-1 Upload revised landscape plan to match revised site plan.
|
Routing PW Sewer Rating | 6/16/2015 | | 6/17/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Drainage | 6/16/2015 | | 6/16/2015 | | FAIL |
Brian Murphy
|
|
|
NEED SHEET C1.1
|
Routing PW Sewer Design | 6/16/2015 | | 6/16/2015 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Indicate point of connection to public sewer.
|
Routing - PLUMBING | 6/16/2015 | | 6/16/2015 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - PLANNING Land Div | 6/16/2015 | | 6/16/2015 | | PASS |
Dave Abo
|
|
|
Lot 7, Block 1 of Calderwood West Subdivision
|
Routing - Addressing | 6/16/2015 | | 6/16/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 6/16/2015 | | 6/16/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Pending Assignment by TLW | 6/16/2015 | | 6/16/2015 | | DONE |
Tim L. Woodard
|
|
|
|
Intake Approval | | | 6/12/2015 | | PASS |
Tim L. Woodard
|
|
|
|
Intake Approval | | | 6/10/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Please see comments on check list for additional information needed
|
Application received | | | 6/5/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 5 2015 3:26PM
|