BLD-Aging Inspection | 10/14/2016 | 10/14/2016 | 10/17/2016 | | PASS |
Dave Hannah
|
|
|
|
BLD-Aging Inspection | 10/13/2016 | 10/13/2016 | 10/17/2016 | | PASS |
Dave Hannah
|
|
|
|
DOC - Permit Finaled | 10/17/2016 | 10/17/2016 | 10/17/2016 | A | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 5/31/2016 | 6/1/2016 | 6/1/2016 | A | PASS |
Dave Hannah
|
|
|
Call me when you are on your way. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
FIRE-Final Inspection | 5/31/2016 | 5/31/2016 | 5/31/2016 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, smoke detectors are stand alone detectors, final life fire safety inspection passed/complete.
|
BLD-Conference | 5/25/2016 | 5/26/2016 | 5/26/2016 | A | DONE |
Dave Hannah
|
|
|
Please call a few minutes before you arrive. I''m not always on site Phone #: ###-#### Inspection requested via web by Bob Thornton
|
Zoning Approval | 5/26/2016 | 5/26/2016 | 5/26/2016 | | DONE |
Matthew A Halitsky
|
|
|
|
BLD-Aging Inspection | 4/14/2016 | 4/14/2016 | 4/21/2016 | | PASS |
Dave Hannah
|
|
|
|
BLD-Energy code compliance | 12/2/2015 | 12/2/2015 | 12/2/2015 | P | PASS |
Dave Hannah
|
|
|
Call Bob when you are on your way. Phone #: ###-#### Inspection requested via web by Bob Thornton
|
Issue PAID IN FULL permit | | | 10/27/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/27/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 7/6/2015 | | |
|
|
|
|
Permit Ready to Issue | | | 7/6/2015 | | DONE |
Christina Prado
|
|
|
All other requirements met
|
Route to Impact Fee Review | 7/1/2015 | 7/4/2015 | 7/2/2015 | | PASS |
Cindy M. Gould
|
|
|
Existing building that once was a dwelling no impact fees CMG
|
Plan assigned to (CJW) | 6/9/2015 | 6/9/2015 | 7/2/2015 | | PASS |
Carl Westfall
|
|
|
CARRIAGE HOUSE (June 29 - 15 days) Level 3 TI - ePlanReview
|
Routing - FIRE | 7/2/2015 | | 7/2/2015 | | PASS |
Katie Marron
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/2/2015 | | DONE |
|
|
|
|
1st review completed | | | 7/1/2015 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 7/1/2015 | | DONE |
|
|
|
|
Routing - Design Review | 7/1/2015 | | 7/1/2015 | | PASS |
Matthew A Halitsky
|
|
|
|
Routing - PLAN CHECK | 6/9/2015 | | 7/1/2015 | | PASS |
Carl Westfall
|
|
|
Drawings approved with redlines
|
Routing - PUBLIC WORKS | 6/9/2015 | | 6/11/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Sewer Rating | 6/11/2015 | | 6/11/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - FIRE | 6/9/2015 | 6/9/2015 | 6/10/2015 | | FAIL |
Scott Arellano
|
|
|
Comments attached to plans and emailed to architect
|
Routing - Design Review | 6/9/2015 | | 6/10/2015 | | FAIL |
Matthew A Halitsky
|
|
|
Matt Halitsky - DRH15-00187
Windows do not match DR approval.
|
Routing - PLUMBING | 6/9/2015 | | 6/10/2015 | | PASS |
Bill VanDegrift
|
|
|
|
Routing - MECHANICAL | 6/9/2015 | | 6/10/2015 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 6/9/2015 | | 6/9/2015 | | PASS |
Emily Dixon
|
|
|
|
Intake Approval | | | 6/9/2015 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Tim Woodard and plan review fees paid.
|
Pending Assignment by JCB | 6/9/2015 | | 6/9/2015 | | DONE |
Jason Blais
|
|
|
|
Routing - Erosion and Sediment | 6/9/2015 | | 6/9/2015 | | PASS |
Evan Jenkins
|
|
|
(CARRIAGE HOUSE) COMPLETE RESTORATION AND REHABILITATION OF HISTORIC CARRIAGE HOUSE STRUCTURE FOR OCCUPANCY AS A DWELLING UNIT. PROJECT INCLUDES NEW DOORS, WINDOWS, FINISHES, STAIRWAY AND NEW MECHANICAL AND ELECTRICAL SYSTEMS.
|
Application received | | | 6/8/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 8 2015 11:22AM
|