BLD-Final | 6/26/2015 | 6/29/2015 | 6/29/2015 | A | PASS |
Jim Sly
|
|
|
David Phone #: ###-#### OK for Perm Occ.....Pending Zoning approval ....if required.
|
FIRE-Final Inspection | 6/26/2015 | 6/26/2015 | 6/26/2015 | P | PASS |
Jim Page
|
|
|
Life fire safety passed/complete
|
Issue PAID IN FULL permit | | | 6/23/2015 | | DONE |
|
|
|
|
Plan assigned to (CDM) | | 6/10/2015 | 6/19/2015 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLAN CHECK | 6/12/2015 | | 6/19/2015 | | PASS |
Carl D Madsen
|
|
|
|
Routing - PLANNING | 6/19/2015 | | 6/19/2015 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLAN CHECK | 6/19/2015 | | 6/19/2015 | | PASS |
Carl D Madsen
|
|
|
|
1st review completed | | | 6/19/2015 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/19/2015 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 6/19/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/19/2015 | | DONE |
|
|
|
All requirements met///cdp 6/23
Need GC and Revised Cert of Value
|
Print Occupancy Form | | | 6/19/2015 | | DONE |
|
|
|
|
Telephone call | | | 6/19/2015 | | DONE |
|
|
|
called Rob-left message with Crystal that permit is ready for pick up, need GC form and Certificate of value
|
Routing - PUBLIC WORKS | 6/12/2015 | | 6/12/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 6/12/2015 | | 6/12/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Routing PW Sewer Rating | 6/12/2015 | | 6/12/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/10/2015 | | DONE |
|
|
|
|
Intake Approval | | | 6/10/2015 | | PASS |
Carl D Madsen
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/10/2015 | | DONE |
|
|
|
|
Application received | | 6/10/2015 | | | |
|
|
|
|