BLD-Final | 12/8/2015 | 12/10/2015 | 12/10/2015 | A | PASS |
Tony Young
|
|
|
Key for house is in garage hanging on a nail by man door -- garage code is 0713. Please call with any questions. Thanks, Kim Phone #: ###-#### Inspection requested via web by Kim Winkle
|
DOC - Permit Finaled | 12/10/2015 | 12/10/2015 | 12/10/2015 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Final | 12/9/2015 | 12/9/2015 | 12/9/2015 | P | PASS |
Tony Young
|
|
|
Key for house is in garage hanging on a nail by man door -- garage code is 0713. Please call with any questions. Thanks, Kim Phone #: ###-#### Inspection requested via web by Kim Winkle
|
BLD-Final | 11/30/2015 | 12/4/2015 | 12/4/2015 | A | NR |
Tony Young
|
|
|
Key for house is in garage hanging on a key next to man door. Garage code is 0713. Thx Phone #: ###-#### Inspection requested via web by Kim Winkle,, all ok,, just need fire place final
|
BLD-Energy code compliance | 8/31/2015 | 9/1/2015 | 9/1/2015 | A | PASS |
Mike Jordan
|
|
|
Steve Phone #: ###-####
|
BLD-Framing/Rough-in | 8/31/2015 | 9/1/2015 | 9/1/2015 | A | PASS |
Mike Jordan
|
|
|
Steve Phone #: ###-####
|
BLD-Framing/Rough-in | 8/27/2015 | 8/28/2015 | 8/28/2015 | A | PART |
Tony Young
|
|
|
Steve Phone #: ###-####,, c/n on a couple things,, ok to cover
|
BLD-Wall Bracing | 8/24/2015 | 8/25/2015 | 8/25/2015 | A | PASS |
Tony Young
|
|
|
Inspection requested via web by Andrew George
|
BLD-Wall Bracing | 8/24/2015 | 8/25/2015 | 8/25/2015 | A | PASS |
Tony Young
|
|
|
Inspection requested via web by Andrew George
|
BLD-Wall Bracing | 8/21/2015 | 8/24/2015 | 8/24/2015 | A | FAIL |
Tony Young
|
|
|
Inspection requested via web by Andrew George not ready,, also already covered with building paper
|
BLD-Foundation | 7/23/2015 | 7/24/2015 | 7/24/2015 | A | DEFR |
Mike Jordan
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron. foundation already placed when on site.
|
BLD-Footing | 7/19/2015 | 7/20/2015 | 7/20/2015 | P | PART |
Mike Jordan
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron. Garage footing completed, work in progress on house.
|
BLD-Footing | 7/15/2015 | 7/16/2015 | 7/16/2015 | A | NR |
Tony Young
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 7/15/2015 | 7/15/2015 | 7/15/2015 | P | NR |
Tony Young
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
OVERRIDE | | | 7/13/2015 | | |
|
|
|
|
Telephone call | | | 7/13/2015 | | DONE |
|
|
|
Left message for Steve informing him that his permit is ready and the amount of fees that are due.
|
Issue PAID IN FULL permit | | | 7/13/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/13/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/13/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/13/2015 | | DONE |
|
|
|
requirements met
|
Plan assigned to (JG) | 7/11/2015 | 7/11/2015 | 7/11/2015 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/11/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/6/2015 | | 7/11/2015 | | PASS |
Tisha Gallop
|
|
|
Review finished by Javier, applicant called requesting this project to be finished ASAP, Tisha had a note on these plans stating resubmittals ok and only needed to review truss engineering loads
|
Case Summary (BLD) | | | 7/11/2015 | | DONE |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/11/2015 | | DONE |
|
|
|
|
Plan assigned to (LEG) Tisha | 6/12/2015 | | 7/11/2015 | | DEFR |
Tisha Gallop
|
|
|
1st review 6/27; plan check
|
Plan resubmittals received | | | 7/6/2015 | | DONE |
|
|
|
received (2) sets; truss plan & calculations, Cover (1), Foundation (2), Floor Plan (3), Shear (4), Upper Floor (5), Floor Plan (6), Roof (7), Wall Section (8), Elevations (9), Electrical (10)
|
Routing - PLAN CHECK | | | 6/27/2015 | | FAIL |
Tisha Gallop
|
|
|
e-mailed comments to Steve Hanson
|
1st review completed | | | 6/27/2015 | | DONE |
Tisha Gallop
|
|
|
1st review not entered by Tisha at the time of me finishing this review i entered the 1st review and back dated to the date the plan check failed
|
Routing - MECHANICAL | 6/16/2015 | | 6/18/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 6/16/2015 | | 6/16/2015 | | PASS |
Sue Cummings
|
|
|
|
Routing - PUBLIC WORKS | 6/15/2015 | | 6/16/2015 | | PASS |
Beverly Mountain
|
|
|
|
Routing - Addressing | 6/12/2015 | | 6/15/2015 | | PASS |
Emily Dixon
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/12/2015 | | DONE |
|
|
|
|
Intake Approval | | | 6/12/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/12/2015 | | DONE |
|
|
|
|
Application received | | 6/11/2015 | | | |
|
|
|
|