First Notice | | 8/7/2017 | 8/10/2017 | | DONE |
|
|
|
went out in mail 8-10-17
|
Permanent Occupancy | | | 7/28/2017 | | DONE |
|
|
|
|
Telephone call | | | 7/25/2017 | | DONE |
|
|
|
emailed Ryan at rhill@zwickconstruction.com to let know taht the Temp C of O expires on 7/29/17
|
BLD-Aging Inspection | 7/3/2017 | 7/3/2017 | 7/10/2017 | | PASS |
Jim Storey
|
|
|
Jason Blais ok's a 60 day extension grood from 5/31/17
|
Zoning Approval | 6/27/2017 | 6/27/2017 | 6/27/2017 | | PASS |
Sarah Schafer
|
|
|
Approved.
|
BLD-Aging Inspection | 5/1/2017 | 5/1/2017 | 5/1/2017 | | PASS |
Jim Storey
|
|
|
Jason Blais ok's a 60 day extension grood from 5/31/17
|
Temporary Occupancy | 4/28/2017 | 7/27/2017 | 4/28/2017 | | DONE |
Candy A. Nichols
|
|
|
Jason Blais ok's a 60 day extension grood from 5/31/17
|
Temporary Occupancy | 4/28/2017 | 7/27/2017 | 4/28/2017 | | DONE |
Candy A. Nichols
|
|
|
as per Jason Blais -request for extension is good for 60 days starting from 5/31/2017
|
Temporary Occupancy | 3/2/2017 | 5/31/2017 | 3/2/2017 | | DONE |
Carlos Velazquez
|
|
|
|
FIRE-Final Inspection | 2/27/2017 | 2/27/2017 | 2/27/2017 | A | PASS |
Jim Page
|
|
|
Racking permit inspection complete, final for life fire safety passed/complete
|
BLD-Final | 2/23/2017 | 2/23/2017 | 2/23/2017 | A | PASS |
Jim Storey
|
|
|
This inspection is for a T-CO. Sign off card is on counter of sales area. Phone #: ###-#### Inspection requested via web by Arn Kniffen pending pw and p&z and mech temp.
|
PubWorks Temp Occupancy Appr | 2/23/2017 | 2/23/2017 | 2/23/2017 | | DONE |
Tiffany Lowery
|
|
|
|
FIRE-Final Inspection | 2/17/2017 | 2/21/2017 | 2/21/2017 | A | PART |
Jim Page
|
|
|
Partial life fire safety inspection complete. Final fire sprinkler inspection complete, final fire alarm inspection complete, fire extinguishers are in place with current inspection tags, knox box is in place. There is a building permit for racking associated with this tenant that is not attached to this project (BLD17-00043), this permit is in issued status, the racking permit will need a final inspection performed, when the racking permit inspection is complete and passed BLD15-01997 permit can be finaled for fire life safety. Signage for the FACP room as well as signage for fire sprinkler riser access will be installed, will verify installation of signage during racking permit inspection
|
BLD-Ceiling Grid Inspection | 1/12/2017 | 1/13/2017 | 1/13/2017 | A | PASS |
Jim Storey
|
|
|
arn Phone #: ###-####
|
BLD-Framing/Rough-in | 12/29/2016 | 12/30/2016 | 12/30/2016 | P | PASS |
Jim Storey
|
|
|
arn Phone #: ###-#### ceilling ok pending others
|
BLD-Energy code compliance | 11/18/2016 | 11/21/2016 | 11/21/2016 | P | PASS |
Jim Storey
|
|
|
Arn Phone #: ###-#### insulation ok to cover all walls
|
BLD-Framing/Rough-in | 11/16/2016 | 11/17/2016 | 11/17/2016 | A | PASS |
Jim Storey
|
|
|
Arn Phone #: ###-#### framing a insulation
|
BLD-Framing/Rough-in | 11/10/2016 | 11/14/2016 | 11/14/2016 | A | PASS |
Phil Shearer
|
|
|
Arn-ada in bathrooms Phone #: ###-####
|
BLD-Energy code compliance | 11/10/2016 | 11/14/2016 | 11/14/2016 | A | PASS |
Phil Shearer
|
|
|
Arn Phone #: ###-####
|
BLD-Energy code compliance | 11/4/2016 | 11/7/2016 | 11/7/2016 | A | PASS |
Jim Storey
|
|
|
Arn Phone #: ###-#### office exterior walls ok
|
BLD-Framing/Rough-in | 11/2/2016 | 11/3/2016 | 11/3/2016 | A | PART |
Jim Storey
|
|
|
Part // Arn Phone #: ###-#### office ok one side pending backing ada
|
BLD-Energy code compliance | 9/22/2016 | 9/22/2016 | 9/22/2016 | A | PASS |
Jim Storey
|
|
|
As early as possible Phone #: 3852260488 >> Inspection requested via mobile web by Arn Kniffen foam insulation at grade ok to cover exterior permiter of building
|
BLD-Conference | 9/22/2016 | 9/22/2016 | 9/22/2016 | A | CANC |
Jim Storey
|
|
|
>> Inspection requested via mobile web by Arn Kniffen Inspection cancelled via mobile web on Thursday, September 22, 2016.
|
BLD-Footing | 9/16/2016 | 9/16/2016 | 9/16/2016 | A | PASS |
Jim Storey
|
|
|
ft at loading dock pass with si pending
|
CHANGE STATUS TO (ISS) | | | 9/14/2016 | | DONE |
|
|
|
|
(F) Reprint permit | | | 9/14/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 9/8/2016 | | |
|
|
|
|
Plan assigned to (AJS) | 8/29/2016 | 8/29/2016 | 9/8/2016 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed
|
Permit Ready to Issue | | | 9/8/2016 | | DONE |
|
|
|
PLAN MOD DO NOT RE-ISSUE
|
Routing Off Site - STRUCTURAL | 9/6/2016 | | 9/7/2016 | | PASS |
Ron Hill
|
|
|
|
Routing - PLAN CHECK | 8/29/2016 | | 9/2/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
pending structural approval
|
Routing Off Site - STRUCTURAL | 8/29/2016 | | 9/2/2016 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
1hr
|
Plan Modification Accepted | | | 8/29/2016 | | DONE |
Christina Prado
|
|
|
Per Ron Hill - to add previous deferred wash bay to submittal
|
BLD-Footing | 8/24/2016 | 8/25/2016 | 8/25/2016 | A | PASS |
Jim Storey
|
|
|
Ron Phone #: ###-#### ft ok
|
BLD-Concrete | 8/10/2016 | 8/10/2016 | 8/10/2016 | P | PASS |
Jim Storey
|
|
|
|
BLD-Footing | 6/29/2016 | 6/30/2016 | 6/30/2016 | A | PASS |
Jim Storey
|
|
|
Arn-partial inspection-grid C & 8 spot footings thru shop ingrid C-pour time 11:00 Phone #: ###-#### si mti
|
OVERRIDE | | | 4/26/2016 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 4/26/2016 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/26/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 4/26/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/26/2016 | | DONE |
Christina Prado
|
|
|
Need RP for issuance, all other requirements met
|
Plan assigned to (TLW) | 4/13/2016 | | 4/26/2016 | | PASS |
Tim L. Woodard
|
|
|
1st Review Complete. TLW
|
Routing - PUBLIC WORKS | 4/18/2016 | | 4/26/2016 | | PASS |
Jennifer Bruner
|
|
|
Modification to civil plans. Changes sidewalk sizes. TLW
Approved in E-Plan. TLW
|
Routing PW Street Lights | 4/18/2016 | | 4/26/2016 | | PASS |
Tom Marshall
|
|
|
Approved in E-Plan. TLW
|
Routing PW Environmental | 4/18/2016 | | 4/25/2016 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Drainage | 4/18/2016 | | 4/20/2016 | | PASS |
Brian Murphy
|
|
|
|
Routing - Design Review | 4/18/2016 | | 4/20/2016 | | PASS |
Josh Wilson
|
|
|
DRH15-00093. Plan mod reduces sidewalk size. TLW
|
Routing PW Solid Waste | 4/18/2016 | | 4/19/2016 | | PASS |
Megan Durrell
|
|
|
|
Routing PW Sewer Design | 4/18/2016 | | 4/18/2016 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing - PLAN CHECK | 4/18/2016 | | 4/18/2016 | | PASS |
Tim L. Woodard
|
|
|
Plan mod doesn't affect building. Civil and Lanscape only. TLW
|
Plan Modification Accepted | | | 4/13/2016 | | DONE |
Christina Prado
|
|
|
PLan Mod for changes to civil plans
|
OVERRIDE | | | 3/15/2016 | | |
|
|
|
|
Permit Ready to Issue | | | 3/15/2016 | | DONE |
Christina Prado
|
|
|
Need RP for issuance
|
Routing - PLAN CHECK | 2/24/2016 | | 3/14/2016 | | PASS |
Tim L. Woodard
|
|
|
|
Routing Off Site - STRUCTURAL | 2/24/2016 | | 3/14/2016 | | PASS |
Tim L. Woodard
|
|
|
|
Routing PW Street Lights | 3/14/2016 | | 3/14/2016 | | PASS |
Mike D Hedge
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/14/2016 | | DONE |
|
|
|
|
Plan assigned to (TLW) | 6/24/2015 | | 3/14/2016 | | PASS |
Tim L. Woodard
|
|
|
1st Review Completed. TLW
|
Plan resubmittals received | | | 2/24/2016 | | DONE |
|
|
|
|
Extend Review Timeline | | | 12/7/2015 | | DONE |
Jason Blais
|
|
|
|
Routing PW Drainage | 9/18/2015 | | 10/27/2015 | | PASS |
Jim Wyllie
|
|
|
|
Routing Off Site - STRUCTURAL | 9/18/2015 | | 9/30/2015 | | FAIL |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 9/18/2015 | | 9/30/2015 | | FAIL |
Tim L. Woodard
|
|
|
Defered Submittal not allowed on canopy structure. TLW
|
Routing PW Environmental | 9/18/2015 | | 9/29/2015 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Sewer Design | 9/18/2015 | | 9/25/2015 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing PW Sewer Rating | 9/18/2015 | | 9/23/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Street Lights | 9/18/2015 | | 9/22/2015 | | FAIL |
Mike D Hedge
|
|
|
|
Routing - FIRE | 9/18/2015 | 9/18/2015 | 9/21/2015 | | PASS |
Katie Marron
|
|
|
Updated report attached to case.
|
Routing - PLUMBING | 9/18/2015 | | 9/21/2015 | | PASS |
Daryl Spivey
|
|
|
grease interceptor approved through public works pretreatment
|
Plan resubmittals received | | | 9/18/2015 | | DONE |
|
|
|
|
Routing - Design Review | 9/18/2015 | | 9/18/2015 | | PASS |
Josh Wilson
|
|
|
|
Routing - Erosion and Sediment | 9/18/2015 | | 9/18/2015 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)
(THERMO KING INTERMOUNTAIN) New construction of office and shop space for Thermo King Intermountain; which includes sales; service and repair of over-the-road refrigeration equipment. Truck and trailer service shop and parts warehouse.
|
Route to Impact Fee Review | 9/16/2015 | 9/19/2015 | 9/17/2015 | | PASS |
Stephanie Jensen
|
|
|
|
1st review completed | | | 7/23/2015 | | DONE |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 6/24/2015 | | 7/23/2015 | | FAIL |
Tim L. Woodard
|
|
|
|
Routing PW Solid Waste | 6/25/2015 | | 7/20/2015 | | PASS |
Megan Durrell
|
|
|
Approved in E-Plan Review. TLW
|
Routing PW Sewer Design | 6/25/2015 | | 7/13/2015 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Spoke with Civil Engineer Week of July 6-10. Engineer plans to revise sewer connection and use existing sewer stubs.
|
Routing PW Drainage | 6/25/2015 | | 7/8/2015 | | FAIL |
Jim Wyllie
|
|
|
NEEDS POND DETAIL WIT C33 INTO CLEAN LAVA ROCK L XW SNOUTS NEEDED O M SEDIMENT LEVEL
|
Routing Off Site - STRUCTURAL | 6/24/2015 | | 7/8/2015 | | FAIL |
Tim L. Woodard
|
|
|
|
Routing - PUBLIC WORKS | 7/2/2015 | | 7/2/2015 | | PASS |
Jennifer Bruner
|
|
|
PW Drainage reassigned to BGM
|
Routing PW Sewer Rating | 6/25/2015 | | 6/29/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - FIRE | 6/24/2015 | | 6/29/2015 | | FAIL |
Scott Arellano
|
|
|
Comments attached to case and emailed to architect.
|
Routing - Design Review | 6/24/2015 | | 6/29/2015 | | PASS |
Josh Wilson
|
|
|
|
Routing - MECHANICAL | 6/24/2015 | | 6/26/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 6/24/2015 | | 6/26/2015 | | PASS |
Daryl Spivey
|
|
|
1) see SP-100 for exterior rain water piping
2) water to eyewash to be upstream of r.p.
3) vent chamber of flammable liquids interceptor
|
Routing - PLANNING Land Div | 6/24/2015 | | 6/25/2015 | | PASS |
Dave Abo
|
|
|
Approved in E-Plan By Todd Tucker. TLW
|
Routing - PUBLIC WORKS | 6/24/2015 | | 6/25/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 6/24/2015 | | 6/25/2015 | | FAIL |
Evan Jenkins
|
|
|
Per BCC 8-17, a Full ESC Narrative is required for Approval. Since your project is over 1 Acre, you will need to file an eNOI with the EPA and develop a Full SWPPP. You may Submit that SWPPP to the City for Review and Approval. Evan Jenkins 794.3958
New construction of office and shop space for Thermo King Intermountain; which includes sales; service and repair of over-the-road refrigeration equipment. Truck and trailer service shop and parts warehouse.
|
Routing PW Environmental | 6/25/2015 | | 6/25/2015 | | PASS |
Rick Christenson
|
|
|
Wash Bay connnected to Sand and Oil Interceptor
|
Routing PW Street Lights | 6/25/2015 | | 6/25/2015 | | FAIL |
Mike D Hedge
|
|
|
Required Info missing.
|
Routing - Addressing | 6/24/2015 | | 6/24/2015 | | PASS |
Emily Dixon
|
|
|
|
Intake Approval | | | 6/24/2015 | | PASS |
|
|
|
|
Pending Assignment by TLW | 6/24/2015 | | 6/24/2015 | | DONE |
Tim L. Woodard
|
|
|
|
Application received | | | 6/11/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 11 2015 4:43PM
|