Third Notice | | 8/17/2016 | 9/19/2016 | | DONE |
|
|
|
This permit finaled on the web by Curtis Weedop
|
Third Notice | | 7/16/2016 | 8/12/2016 | | DONE |
|
|
|
|
Third Notice | | 6/15/2016 | 7/11/2016 | | DONE |
|
|
|
|
Third Notice | | 5/16/2016 | 6/10/2016 | | DONE |
|
|
|
|
Second Notice | | 4/22/2016 | 5/11/2016 | | DONE |
|
|
|
Mailed 5-12-16
|
First Notice | | 3/10/2016 | 4/12/2016 | | DONE |
|
|
|
Mailed 4-13-16
|
Permanent Occupancy | | | 2/29/2016 | | DONE |
Christina Prado
|
|
|
|
BLD-Final | 2/25/2016 | 2/26/2016 | 2/26/2016 | P | PASS |
Jim Storey
|
|
|
Rocky Phone #: ###-####
|
FIRE-Final Inspection | 2/25/2016 | 2/26/2016 | 2/26/2016 | A | PASS |
Jim Page
|
|
|
Fire sprinkler inspection complete, fire alarm inspection complete, fire extinguishers have curent inspection tags. Life fire safety inspection passed/complete.
|
BLD-Ceiling Grid Inspection | 1/29/2016 | 2/1/2016 | 2/1/2016 | A | PASS |
Jim Storey
|
|
|
Rocky Phone #: ###-#### pending trades
|
BLD-Ceiling Grid Inspection | 1/6/2016 | 1/7/2016 | 1/7/2016 | A | PASS |
Jim Storey
|
|
|
Rocky Phone #: ###-#### hardlid track and wire supports ok to cover
|
BLD-Framing/Rough-in | 12/22/2015 | 12/23/2015 | 12/23/2015 | P | PART |
Jim Storey
|
|
|
Rocky Phone #: ###-#### storage walls nothing in walls ok to cover.
|
Issue PAID IN FULL permit | | | 8/3/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/22/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/22/2015 | | DONE |
Christina Prado
|
|
|
All requirements met///cdp 7/24/15
Need GC Form and Revised Cert of Value
|
Telephone call | | | 7/22/2015 | | DONE |
|
|
|
called Scott- told him permit is ready and we need GC form and Certificate of Value and then we'll add final fees
|
Routing - PLAN CHECK | 7/10/2015 | | 7/21/2015 | | PASS |
Tim L. Woodard
|
|
|
|
1st review completed | | | 7/21/2015 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/21/2015 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 7/21/2015 | | DONE |
|
|
|
|
Plan assigned to (TLW) | | | 7/21/2015 | | PASS |
Tim L. Woodard
|
|
|
1st Review Completed. TLW
|
Plan resubmittals received | | | 7/10/2015 | | DONE |
|
|
|
received (2) sets of; Floor Plan (A111), Ceiling Plan (A121), Door Frame (A601), HVAC Plan (M1.2), Power Plan (E2.0), Lighting Plan (E3.0), Comm Plan (E4.0)
|
1st review completed | | | 6/25/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/15/2015 | | 6/25/2015 | | FAIL |
Tim L. Woodard
|
|
|
Refer to attached Plan Review Report. TLW
|
Plan resubmittals received | | | 6/17/2015 | | DONE |
|
|
|
received (2) copies of; Index G001, Electrical Plan ED2.0, Lighting Plan ED3.0 & E3.0, Comm Plan E4.0
|
Routing - PUBLIC WORKS | 6/15/2015 | | 6/15/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 6/15/2015 | | 6/15/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/12/2015 | | DONE |
|
|
|
|
Intake Approval | | | 6/12/2015 | | PASS |
Tim L. Woodard
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/12/2015 | | DONE |
|
|
|
|
Application received | | 6/12/2015 | | | |
|
|
|
|