PubWorks Occupancy Approval | 5/29/2019 | 5/29/2019 | 5/29/2019 | | DONE |
Tiffany Lowery
|
|
|
Street Lights are bonded for per Jason Taylor
|
BLD-Final | 3/7/2018 | 3/8/2018 | 3/8/2018 | P | PASS |
Dave Hannah
|
|
|
Jason Phone #: ###-####
|
PubWorks Temp Occupancy Appr | 2/20/2018 | 2/20/2018 | 2/20/2018 | | DONE |
Tiffany Lowery
|
|
|
For onsite drainage only.
|
BLD-Wall cover | 12/1/2017 | 12/4/2017 | 12/4/2017 | A | PASS |
Dave Hannah
|
|
|
Inspection request for shaft covering in trash room level 1. Phone #: ###-#### Inspection requested via web by Guillaume Chatelus
|
BLD-Energy code compliance | 10/31/2017 | 11/1/2017 | 11/1/2017 | A | PASS |
Dave Hannah
|
|
|
Inspection request for Fire Caulking at the 1st and 2nd floors. Phone #: ###-#### Inspection requested via web by Carl Benjamin
|
BLD-Other | 10/17/2017 | 10/18/2017 | 10/18/2017 | A | PASS |
Dave Hannah
|
|
|
Inspection request for drop ceiling cover. Phone #: ###-#### Inspection requested via web by Carl Benjamin
|
Plan Reviewer's activity | | | 10/18/2017 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
Uploaded cable barrier approval from engineer and special inspection firm into ePlan.
|
BLD-Other | 10/13/2017 | 10/16/2017 | 10/16/2017 | A | PEND |
Dave Hannah
|
|
|
Inspection request for the vehicle Cable Barrier sign off. Phone #: ###-#### Inspection requested via web by Carl Benjamin
|
BLD-Wall cover | 10/10/2017 | 10/11/2017 | 10/10/2017 | A | CANC |
Dave Hannah
|
|
|
Inspection request for the soffit sheetrock at the 3rd floor. Phone #: ###-#### >> Inspection requested via web by Carl Benjamin Inspection cancelled from web by: Carl Benjamin
|
BLD-Conference | 10/4/2017 | 10/5/2017 | 10/5/2017 | A | PEND |
Dave Hannah
|
|
|
Inspection request for vehicle barrier cable code compliance in the parking garage. Phone #: ###-#### Inspection requested via web by Guillaume Chatelus
|
BLD-Energy code compliance | 8/11/2017 | 8/14/2017 | 8/14/2017 | A | PASS |
Dave Hannah
|
|
|
Inspection request for Insulation Barrier at the 4th floor of Tower A and 3rd Floor of Tower B. Phone #: ###-#### Inspection requested via web by Carl Benjamin
|
BLD-Framing/Rough-in | 8/3/2017 | 8/4/2017 | 8/4/2017 | A | PASS |
Dave Hannah
|
|
|
Inspection request for duct chases. Phone #: ###-#### Inspection requested via web by Carl Benjamin
|
BLD-Other | 8/1/2017 | 8/2/2017 | 8/3/2017 | A | NR |
Dave Hannah
|
|
|
Inspection request for the base of the 2 hour shaft assemblies. Phone #: ###-#### Inspection requested via web by Carl Benjamin
|
BLD-Other | 7/26/2017 | 7/27/2017 | 7/28/2017 | A | PASS |
Dave Hannah
|
|
|
Inspection request for Intumescent Paint at the Live Works Unit Columns per ASI 81 and Structural Shaft at Unit 725. Thank you. Phone #: ###-#### Inspection requested via web by Carl Benjamin
|
BLD-Framing/Rough-in | 7/25/2017 | 7/26/2017 | 7/26/2017 | A | PART |
Dave Hannah
|
|
|
Inspection request for the structural wall framing where the plumbing compromised the structural integrity at multiple areas. Reference RFI #300 Phone #: ###-#### Inspection requested via web by Carl Benjamin
|
BLD-Energy code compliance | 7/13/2017 | 7/14/2017 | 7/14/2017 | A | PART |
Dave Hannah
|
|
|
Inspection request is for the 4th floor of Tower B. Fire Caulking. Phone #: ###-#### Inspection requested via web by Carl Benjamin ok to insulate but the plumbing walls the studs have been over cut on some walls needs engineer to ok
|
BLD-Aging Inspection | 7/7/2017 | 7/7/2017 | 7/7/2017 | | PASS |
Dave Hannah
|
|
|
|
BLD-Conference | 3/20/2017 | 3/21/2017 | 3/21/2017 | A | DONE |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Benjamin
|
BLD-Conference | 3/14/2017 | 3/15/2017 | 3/15/2017 | A | DONE |
Dave Hannah
|
|
|
Inspection request for Live Works Area 2hr rated walls Conference Phone #: ###-#### Inspection requested via web by Carl Benjamin
|
BLD-Conference | 2/24/2017 | 2/27/2017 | 2/27/2017 | A | DONE |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Carl Benjamin
|
BLD-Framing/Rough-in | 2/22/2017 | 2/22/2017 | 2/23/2017 | P | PART |
Dave Hannah
|
|
|
Chris Phone #: ###-#### ext framing first and second floor ok to cover ext.
|
BLD-Conference | 12/7/2016 | 12/8/2016 | 12/8/2016 | A | PASS |
Dave Hannah
|
|
|
Chris Phone #: ###-####
|
BLD-Conference | 6/6/2016 | 6/6/2016 | 6/6/2016 | P | PASS |
Dave Hannah
|
|
|
Chris Phone #: ###-####
|
BLD-Conference | 5/31/2016 | 6/1/2016 | 6/1/2016 | A | DONE |
Dave Hannah
|
|
|
Chris Phone #: ###-#### talked about sprinklers in roof
|
BLD-Foundation | 4/5/2016 | 4/8/2016 | 4/9/2016 | P | PEND |
Dave Hannah
|
|
|
Rebar // Chris Phone #: ###-####
|
BLD-Foundation | 4/5/2016 | 4/6/2016 | 4/7/2016 | P | PEND |
Dave Hannah
|
|
|
Chris Phone #: ###-####
|
BLD-Foundation | 4/5/2016 | 4/5/2016 | 4/7/2016 | P | PEND |
Dave Hannah
|
|
|
Chris-Rebar Phone #: ###-####
|
BLD-Foundation | 3/30/2016 | 3/31/2016 | 3/31/2016 | A | PEND |
Dave Hannah
|
|
|
Rebar // Chris Phone #: ###-#### on site 2;30 crews are placing walls and one grade beam mti will do final inspection of rebar
|
BLD-Conference | 3/28/2016 | 3/29/2016 | 3/30/2016 | A | PART |
Dave Hannah
|
|
|
Inspection ow wall rebar and column rebar--Pour at 2pm MTI also will be here to inspect Phone #: ###-#### Inspection requested via web by Tom Hayes
|
BLD-Foundation | 3/25/2016 | 3/28/2016 | 3/29/2016 | A | PART |
Dave Hannah
|
|
|
Chris-rebar Phone #: ###-#### column pads elev. foundation spec inspecion will do final and pull concrete test cyl.
|
BLD-Conference | 3/24/2016 | 3/25/2016 | 3/25/2016 | A | PART |
Mike Jordan
|
|
|
Wall and footing rebar inspection am. Concrete pour at 1 pm Contact Tom Hayes with Andersen Construction for any questions, phone number is listed above Phone #: ###-#### Inspection requested via web by Tom Hayes. Work in progress, pend. special inspection.
|
BLD-Conference | 3/9/2016 | 3/10/2016 | 3/10/2016 | A | PASS |
Dave Hannah
|
|
|
Footing Rebar inspections Grids 2-9 and B-H Note:: Pouring real early today, Dave Hannah Looked at Wednesday afternoon Contact: Tom Hayes Phone #: ###-#### Inspection requested via web by Tom Hayes
|
BLD-Conference | 2/25/2016 | 3/1/2016 | 3/1/2016 | A | DONE |
Dave Hannah
|
|
|
Duel Phone #: ###-####
|
Issue PAID IN FULL permit | | | 1/8/2016 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/8/2016 | | DONE |
|
|
|
|
Extend Review Timeline | | | 11/25/2015 | | DONE |
|
|
|
1st 180 days granted by Jason B. See documents
|
Expiration Notice | 11/18/2015 | 12/10/2015 | 11/18/2015 | | DONE |
Brittany Hill
|
|
|
|
Print Statement | | | 9/18/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 9/2/2015 | | |
|
|
|
|
Plan assigned to (TLW) | 6/23/2015 | | 9/2/2015 | | PASS |
Tim L. Woodard
|
|
|
Due 7/24
|
Routing - PLAN CHECK | 8/25/2015 | | 9/2/2015 | | PASS |
Tim L. Woodard
|
|
|
Approved. Comments and Concerns will be addressed with the Shell and Core Permit. TLW
|
Routing PW Sewer Design | 8/25/2015 | | 9/2/2015 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Routing PW Geothermal | 8/25/2015 | | 9/2/2015 | | PASS |
Tim L. Woodard
|
|
|
Approved in E-Plan Review. TLW
|
Routing Off Site - STRUCTURAL | 8/25/2015 | | 9/2/2015 | | PASS |
Tim L. Woodard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/2/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/2/2015 | | DONE |
Christina Prado
|
|
|
All requirements met
|
Plan resubmittals received | | | 8/25/2015 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 7/24/2015 | | 8/13/2015 | | FAIL |
Tim L. Woodard
|
|
|
Refer to changemarks on the drawings. TLW
|
Routing PW Environmental | 7/24/2015 | | 8/13/2015 | | PASS |
Rick Christenson
|
|
|
Approved in E-Plan. TLW
|
Routing - PLAN CHECK | 7/24/2015 | | 8/13/2015 | | PASS |
Tim L. Woodard
|
|
|
|
Route to Impact Fee Review | 7/21/2015 | 7/24/2015 | 8/12/2015 | | PASS |
Cindy M. Gould
|
|
|
Waiting for shell and core permit.
|
Routing PW Drainage | 7/24/2015 | | 8/6/2015 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Sewer Design | 7/24/2015 | | 8/6/2015 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Add contractor note: Contact Boise Public Works 48 hours prior to capping existing sewer services or connecting new services to the sewer main to schedule an inspection and obtain plug/tap permits.
Also, update sewer notes on cover page.
|
Routing - Addressing | 8/6/2015 | | 8/6/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing PW Geothermal | 7/24/2015 | | 7/30/2015 | | FAIL |
Javier Guzman
|
|
|
Geothermal service application required. Contact Boise Public Works, Jon Gunnerson, 208.384.3935.
|
Routing - FIRE | 7/27/2015 | 7/27/2015 | 7/29/2015 | | PASS |
Scott Arellano
|
|
|
Attached comments to plans. Final approval pending approved code alternate request.
|
Routing - Addressing | 7/24/2015 | | 7/28/2015 | | FAIL |
Emily Dixon
|
|
|
Parcels need to be consolidated.
|
Routing - PLANNING Land Div | 7/24/2015 | | 7/27/2015 | | PASS |
Dave Abo
|
|
|
Parcel A of ROS 10162. (ROS15-00053) N.O.B.P signed by Planning Director on 7/8/15.
|
Routing PW Solid Waste | 6/23/2015 | | 7/20/2015 | | PASS |
Megan Durrell
|
|
|
Approved in E-Plan. TLW
|
Routing - PLUMBING | 7/20/2015 | | 7/20/2015 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
1st review completed | | | 7/20/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 6/23/2015 | | 7/20/2015 | | FAIL |
Tim L. Woodard
|
|
|
Refer to corrections in E-Plan Review. TLW
|
Routing - PUBLIC WORKS | 6/23/2015 | | 7/20/2015 | | PASS |
Tim L. Woodard
|
|
|
Refer to E-Plan Review. TLW
|
Routing Off Site - STRUCTURAL | 6/23/2015 | | 7/20/2015 | | FAIL |
Tim L. Woodard
|
|
|
|
Routing - PLANNING Land Div | 7/17/2015 | | 7/17/2015 | | PASS |
Dave Abo
|
|
|
ROS recorded on July 7, 2015 ROS10162
Notice of Buildable Parcel recorded on 7/8/15.
Todd Tucker signed off in ePlan on 6/25/15.
|
Routing PW Environmental | 6/23/2015 | | 7/14/2015 | | PASS |
Rick Christenson
|
|
|
Contacted for verification of exterior interceptors, will review when plumbing fixtures are added.
|
Routing - FIRE | 7/6/2015 | | 7/8/2015 | | FAIL |
Katie Marron
|
|
|
Report attached to case and emailed to architect.
|
Routing PW Drainage | 6/23/2015 | | 7/6/2015 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Sewer Design | 6/23/2015 | | 6/30/2015 | | FAIL |
Kyle S. Rosenmeyer
|
|
|
Add contractor note: Contact Boise Public Works 48 hours prior to capping existing sewer services or connecting new services to the sewer main to schedule an inspection and obtain plug/tap permits.
Also, update sewer notes on cover page.
|
Routing - MECHANICAL | 6/23/2015 | | 6/29/2015 | | PASS |
Troy James
|
|
|
No mechanical review. Reference only sheets.
|
Routing - PLUMBING | 6/23/2015 | | 6/29/2015 | | FAIL |
Daryl Spivey
|
|
|
An engineered stamped set of plans required for plumbing review.
|
Routing PW Geothermal | 6/23/2015 | | 6/25/2015 | | FAIL |
Jon R. Gunnerson
|
|
|
Application for geothermal service required. Contact Public Works Geothermal, Jon Gunnerson @ ###-####.
|
Routing - Design Review | 6/23/2015 | | 6/23/2015 | | PASS |
Sarah Schafer
|
|
|
Approved per DRH15-00152.
|
Pending Assignment by TLW | 6/23/2015 | | 6/23/2015 | | DONE |
Tim L. Woodard
|
|
|
|
Routing PW Street Lights | 6/23/2015 | | 6/23/2015 | | PASS |
Mike D Hedge
|
|
|
Street light information to be on next plan submission.
|
Routing - Addressing | 6/23/2015 | | 6/23/2015 | | FAIL |
Emily Dixon
|
|
|
Parcels need to be consolidated.
|
Routing - Erosion and Sediment | 6/23/2015 | | 6/23/2015 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to Any Earth Disturbance)
Podium Permit Application for a new 7 story mixed use project. Also includes site improvements/landscaping and parking areas. New sewer mains, power etc...
|
Intake Approval | | | 6/19/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
Please complete and upload the completed 502 check list. Once this is receive I will begin the prescreen.
|
Intake Approval | | | 6/19/2015 | | PASS |
Tim L. Woodard
|
|
|
|
Application received | | | 6/15/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 15 2015 3:10PM
|