BLD-Final | 2/19/2016 | 2/22/2016 | 2/22/2016 | P | PASS |
Jim Sly
|
|
|
Please call ahead for access - Mary Phone #: ###-####
|
DOC - Permit Finaled | 2/22/2016 | 2/22/2016 | 2/22/2016 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 2/11/2016 | 2/17/2016 | 2/17/2016 | P | FAIL |
Mike Jordan
|
|
|
Chris Phone #: ###-####. Needs blower door test, provide code compliant step from garage.
|
BLD-Energy code compliance | 8/26/2015 | 8/28/2015 | 8/28/2015 | A | PASS |
Mike Jordan
|
|
|
Chris Phone #: ###-####
|
BLD-Framing/Rough-in | 8/26/2015 | 8/26/2015 | 8/26/2015 | P | PASS |
Mike Jordan
|
|
|
Chris Phone #: ###-####
|
BLD-Wall Bracing | 8/10/2015 | 8/10/2015 | 8/10/2015 | P | PASS |
Mike Jordan
|
|
|
Chrisian Phone #: ###-####
|
BLD-Foundation | 7/21/2015 | 7/22/2015 | 7/22/2015 | A | PART |
Mike Jordan
|
|
|
Paul-wall-would like mid morning if poss Phone #: ###-####
|
BLD-Footing | 7/21/2015 | 7/21/2015 | 7/21/2015 | P | PART |
Mike Jordan
|
|
|
Paul Phone #: ###-####
|
Telephone call | | | 7/20/2015 | | DONE |
Tisha Gallop
|
|
|
spoke with Mary Baker (owner). Told her rebar in footing/foundation is not called out on this plan and is not required for this project.
|
Issue PAID IN FULL permit | | | 7/2/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 6/30/2015 | | |
|
|
|
|
Inspection Record Card- Bld | | | 6/30/2015 | | DONE |
|
|
|
|
Telephone call | | | 6/30/2015 | | DONE |
|
|
|
called Mary- left message that permit is ready and fees due
|
Meeting | | | 6/30/2015 | | DONE |
|
|
|
as per Bob Archibald charge $2500.00 for the fee that should have been paid for the demo of the manufactured home.
|
Case Summary (BLD) | | | 6/30/2015 | | DONE |
|
|
|
|
Telephone call | | | 6/30/2015 | | DONE |
Tisha Gallop
|
|
|
spoke to Mary Baker on phone to discuss plan deficiencies. She said wants to do continuous footing same as house around perimeter of patio instead of sonotubes at each post and beam over mechanical bay in garage is (2) 1-3/4" x 7-1/4" Microlam beam. I redlined this information on plans.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/30/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 6/30/2015 | | DONE |
|
|
|
all requirements met
|
Plan assigned to (LEG) Tisha | 6/15/2015 | | 6/30/2015 | | DONE |
Tisha Gallop
|
|
|
6/26
|
Routing - PLAN CHECK | 6/22/2015 | | 6/30/2015 | | PASS |
Tisha Gallop
|
|
|
|
1st review completed | | | 6/30/2015 | | DONE |
Tisha Gallop
|
|
|
|
Plan resubmittals received | | | 6/26/2015 | | DONE |
|
|
|
resubmittals-received 2 sheets of 2-took to Tisha
|
Routing - MECHANICAL | 6/22/2015 | | 6/22/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 6/19/2015 | | 6/22/2015 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 6/16/2015 | | 6/19/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 6/19/2015 | | 6/19/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/16/2015 | | DONE |
|
|
|
|
Intake Approval | | | 6/16/2015 | | PASS |
|
|
|
as per Carl M ready to take in once the manual's have are ready
|
Recd Pcfee & Taken To Pln CK | | | 6/16/2015 | | DONE |
|
|
|
|
Application received | | 6/16/2015 | | | |
|
|
|
|