Permit Information
Permit NumberBLD15-02076
StatusFinaled
Name ST LUKES HEALTH SYSTEM LTD
Site Address 100 E IDAHO ST
Project NameST LUKES MSTI Pharmacy
Customer Number 
ePlanReviewYes
Description
(ST. LUKES - MSTI)(PHARMACY - 1ST FLOOR) Fire sprinkler system used for floor level over 55 feet above grade. The remodel of the existing pharmacy located on the 1st floor. The pharmacy will be expanded into a portion of the 1st floor where an existing stair used to be located and was removed under BLD14-03434 creating a 975 sq ft pharmacy space. Structural work for mechanical occurring on rooftop. New door access will be provided out of the 3rd floor stair enclosure. A new 2 hour shaft will be constructed adjacent to an existing shaft for the new hoods in the pharmacy. Special inspection is required for steel construction as listed on form 310 and for spray applied fire proofing. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **ajs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 8/15/20169/19/2016 DONE
This permit finaled on the web by Curtis Weedop
Print Statement  9/19/2016 DONE
Second Notice 7/21/20168/10/2016 DONE
Mailed 8-11
First Notice6/8/20166/8/20167/11/2016 DONE
DetailsCandy A. Nichols
mailed 7/12/16
BLD-Final6/7/20166/8/20166/8/2016APASS
DetailsMike Jordan
If know answer on my cell number please call me on my desk phone ###-#### Thanks Phone #: ###-#### Inspection requested via web by Rock Self
DOC - Permit Finaled6/8/20166/8/20166/8/2016PPASS
DetailsMike Jordan
BLD-Final6/6/20166/7/20166/7/2016ACANC
DetailsDave Hannah
If know answer on my cell number please call me on my desk phone ###-#### Thanks Phone #: ###-#### Inspection requested via web by Rock Self
BLD-Final5/18/20165/19/20165/19/2016ANR
DetailsJim Storey
Kelly Phone #: ###-#### need mech final
FIRE-Final Inspection5/18/20165/19/20165/19/2016APASS
DetailsJim Page
Fire sprinkler inspection complete (FIR15-00572), fire alarm inspection complete (FIR15-00475), final life fire safety inspection passed/complete.
BLD-Ceiling Grid Inspection1/22/20161/25/20161/25/2016APASS
DetailsDave Hannah
Kelly Phone #: ###-####
BLD-Framing/Rough-in1/14/20161/15/20161/15/2016APASS
DetailsDave Hannah
KELLY Phone #: ###-#### ceiling grid
BLD-Wall cover11/20/201511/20/201511/20/2015PPART
DetailsTony Young
If no answer at ###-#### please try ###-#### Thank You. Phone #: ###-#### Inspection requested via web by Rock Self,, walls ok to cover,, need to get fix on roof penetration,, ok for wall pop out from architect
Issue PAID IN FULL permit  8/20/2015 DONE
Inspection Record Card- Bld  8/20/2015 DONE
Plan assigned to (AJS)6/23/20156/23/20158/13/2015 PASS
DetailsAdele J Schaffeld-Griffin
1st review completed 7/20 Level 3 TI - ePlanReview - St. Lukes MSTI Pharmacy
Routing - PLAN CHECK8/6/2015 8/13/2015 PASS
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  8/13/2015 DONE
Permit Ready to Issue  8/13/2015 DONE
all requirments met
Plan Reviewer's activity  8/11/2015 DONE
DetailsAdele J Schaffeld-Griffin
Called Joe Bruce as change mark 1 and 2 were not addressed. I am going to keep the task and wait for Joe to email me the signed 310 for with the SAFP included on the check list.
Routing - PLAN CHECK6/23/2015 7/22/2015 FAIL
DetailsAdele J Schaffeld-Griffin
1st review completed  7/22/2015 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - MECHANICAL6/23/2015 6/29/2015 PASS
DetailsTroy James
Routing PW Sewer Rating6/25/2015 6/25/2015 PASS
DetailsJennifer Bruner
Routing - PUBLIC WORKS6/23/2015 6/25/2015 PASS
DetailsJennifer Bruner
Routing - FIRE6/23/20156/23/20156/24/2015 PASS
DetailsScott Arellano
Comments attached to case
Routing - PLUMBING6/23/2015 6/24/2015 PASS
DetailsBill VanDegrift
Per plan and ISPC.
Routing - Design Review6/23/2015 6/23/2015 PASS
DetailsJosh Wilson
OK PER CZC15-00135
Routing - Addressing6/23/2015 6/23/2015 PASS
DetailsEmily Dixon
Pending Assignment by JCB6/23/2015 6/23/2015 DONE
DetailsJason Blais
Intake Approval  6/22/2015 PASS
DetailsJason Blais
Intake Approval  6/18/2015 FAIL
Please provide the structural calculations for the structural alterations and additions. A form 310 special inspection for may also be required.
Application received  6/17/2015 DONE
Application submitted via PDS Online on Jun 17 2015 10:25AM