BLD-Final | 10/21/2015 | 10/21/2015 | 10/21/2015 | P | PASS |
Mike Jordan
|
|
|
|
DOC - Permit Finaled | 10/21/2015 | 10/21/2015 | 10/21/2015 | P | PASS |
Mike Jordan
|
|
|
|
Routing Walk-In (Zoning) | 7/9/2015 | 7/9/2015 | 10/21/2015 | A | PASS |
Ted Vanegas
|
|
|
|
BLD-Final | 10/19/2015 | 10/19/2015 | 10/19/2015 | P | NR |
Mike Jordan
|
|
|
Mirela Phone #: ###-####. Needs zoning final. Inspection ok, will sign off after zoning has passed. A correction notice was issued.
|
BLD-Framing/Rough-in | 9/9/2015 | 9/9/2015 | 9/9/2015 | P | PASS |
Jim Sly
|
|
|
Sem Phone #: ###-####
|
BLD-Wall Bracing | 8/10/2015 | 8/11/2015 | 8/11/2015 | P | PASS |
Mike Jordan
|
|
|
Sudin Phone #: ###-####
|
OVERRIDE | | | 7/20/2015 | | |
|
|
|
|
BLD-Foundation | 7/8/2015 | 7/8/2015 | 7/8/2015 | P | PASS |
Mike Jordan
|
|
|
Rob Phone #: ###-####
|
BLD-Footing | 7/7/2015 | 7/7/2015 | 7/7/2015 | P | PART |
Mike Jordan
|
|
|
Rob Phone #: ###-####
|
BLD-Footing | 6/30/2015 | 7/1/2015 | 7/1/2015 | P | NR |
Mike Jordan
|
|
|
Matt Phone #: ###-####
|
BLD-Footing | 6/30/2015 | 6/30/2015 | 6/30/2015 | P | CANC |
Mike Jordan
|
|
|
Matt Phone #: ###-####. Cancelled by contractor via phone call.
|
Routing Walk-In (Zoning) | 6/18/2015 | 6/18/2015 | 6/18/2015 | A | DONE |
Ted Vanegas
|
|
|
|
Routing Walk-In (BLD) | 6/18/2015 | 6/18/2015 | 6/18/2015 | A | PASS |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 6/18/2015 | | DONE |
|
|
|
|
1st review completed | | | 6/18/2015 | | DONE |
|
|
|
|
Plan assigned to (LEG) Tisha | 6/18/2015 | | 6/18/2015 | | DONE |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/18/2015 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/18/2015 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 6/18/2015 | | DONE |
Brittany Hill
|
|
|
|
Permit Ready to Issue | | | 6/18/2015 | | DONE |
Brittany Hill
|
|
|
|
Application received | | 6/18/2015 | | | |
|
|
|
|