Permit Information
Permit NumberBLD15-02108
StatusFinaled
Name BLUE RIDGE CONSTRUCTION
Site Address 2146 S BROADWAY AVE
Project NamePho Le
Customer NumberBLD15-01841 & BLD15-02107
ePlanReviewNo
Description
(PHO LE)(BROADWAY PARK)Name change request recieved from architect on 3-4-16 see file. **ajs**Core and shell under BLD15-01841. Permit to construct a 2 hour fire barrier between St. Vincent (BLD-15-02107) and Wok King (BLD15-02108). This fire barrier is constructed in lieu of fire sprinklering the building . Scope of work to include 2 new ADA restrooms, hi/low drinking fountain, new commercial kitchen with walk in cooler, storage room and dining area. Mechanical, Plumbing and Electrical as shown on approved plans. This building is NOT fire sprinklered. **ajs**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  8/2/2016 DONE
Second Notice 5/22/20167/14/2016 DONE
Mailed 7-15-16
First Notice 5/7/20165/12/2016 DONE
Mailed 5-13-16
BLD-Final4/26/20164/27/20164/27/2016APASS
DetailsJim Storey
Larry Phone #: ###-####
Permanent Occupancy  4/27/2016 DONE
FIRE-Final Inspection4/25/20164/25/20164/25/2016PPASS
DetailsJim Page
Previously noted items addressed/repaired. Occupancy sign was being printed at time of inspection, will be installed by general contractor. No fire sprinklers, duct detector is stand alone and tested correctly, commercial hood suppression system inspection complete, fire extinguishers are in place with current inspection tags. Final life fire safety inspection passed/complete.
FIRE-Final Inspection4/22/20164/22/20164/22/2016PFAIL
DetailsTroy Cobbley
Rear door exit discharge light can not be connected to a photo cell or timer, duct smoke detector did not shut down the hvac unit upon activation, need occupant load sign at the main exit.
FIRE-Final Inspection4/1/20164/4/20164/4/2016AFAIL
DetailsTroy Cobbley
Can't perform life safety until the project related hood suppression permit is finaled. Per scott and my discussion the new hood and duct smoke detector do not need to be connected to the existing fire alarm system in the day care at the south end of the building due to an existing 4 hour wall that provides separation.
BLD-Ceiling Grid Inspection3/30/20163/31/20164/1/2016PPASS
DetailsJim Storey
Larry Phone #: ###-####
(F) Reprint permit  2/17/2016 DONE
BLD-Ceiling Grid Inspection2/3/20162/3/20162/3/2016PPASS
DetailsJim Storey
Larry Phone #: ###-####
Zoning Approval1/7/20161/7/20161/7/2016 PASS
DetailsJosh Wilson
BLD-Energy code compliance12/16/201512/17/201512/17/2015PPASS
DetailsJim Storey
Larry Phone #: ###-####
BLD-Framing/Rough-in12/15/201512/16/201512/16/2015PPASS
DetailsJim Storey
Larry Phone #: ###-####
Print Occupancy Form  8/31/2015 DONE
Issue PAID IN FULL permit  8/31/2015 DONE
OVERRIDE  8/13/2015  
Plan assigned to (AJS)6/18/20156/18/20158/13/2015 PASS
DetailsAdele J Schaffeld-Griffin
1st review completed New Structure Wok King
Routing - PLAN CHECK8/6/2015 8/13/2015 PASS
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  8/13/2015 DONE
Permit Ready to Issue  8/13/2015 DONE
NEED GC form, Certificate of Value, RP, and ACHD
Routing Off Site - C.D.H8/6/2015 8/6/2015 PASS
DetailsAdele J Schaffeld-Griffin
recieved approved sign off uploaded in documents
Routing - PLAN CHECK7/24/2015 7/30/2015 FAIL
DetailsAdele J Schaffeld-Griffin
Routing Off Site - C.D.H7/24/2015 7/30/2015 FAIL
DetailsAdele J Schaffeld-Griffin
Routing Off Site - STRUCTURAL7/24/2015 7/30/2015 PASS
DetailsAdele J Schaffeld-Griffin
Routing Off Site - STRUCTURAL6/18/2015 7/21/2015 FAIL
DetailsAdele J Schaffeld-Griffin
Routing PW Environmental6/19/2015 7/21/2015 PASS
DetailsRick Christenson
Exterior Grease Interceptor 1500 gallon located out back
Routing Off Site - C.D.H7/21/2015 7/21/2015 FAIL
DetailsAdele J Schaffeld-Griffin
We require the food facility application, plan review and food license fee, pre-operational plan review form completed and a complete plan review. Facility owners need to contact CDHD to submit all paperwork
1st review completed  7/21/2015 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - PLAN CHECK6/18/2015 7/21/2015 FAIL
DetailsAdele J Schaffeld-Griffin
Routing - FIRE6/18/20156/18/20156/19/2015 PASS
DetailsKatie Marron
Comments attached to case
Routing PW Sewer Rating6/19/2015 6/19/2015 PASS
DetailsConnie Baumgartner
Routing - MECHANICAL6/18/2015 6/19/2015 PASS
DetailsTroy James
Redlined drawing
Routing - PLUMBING6/18/2015 6/19/2015 PASS
DetailsDaryl Spivey
See notes under bld15-01841
Routing - Addressing6/18/2015 6/19/2015 PASS
DetailsEmily Dixon
Address corrected to 2146 S Broadway Ave.
Routing - PUBLIC WORKS6/18/2015 6/19/2015 PASS
DetailsJennifer Bruner
Routing - Erosion and Sediment6/18/2015 6/19/2015 PASS
DetailsEvan Jenkins
REBUILD THE STRUCTURE BACK FROM A FIRE
Routing - Design Review6/18/2015 6/18/2015 PASS
DetailsJosh Wilson
Intake Approval  6/18/2015 PASS
DetailsAdele J Schaffeld-Griffin
Application received 6/18/2015