BLD-Final | 7/31/2015 | 8/3/2015 | 8/3/2015 | P | PASS |
Jim Storey
|
|
|
Project has a tight schedule to re-open. We are hoping all permits will show passed by Monday afternoon, so I can ask you for Final occupancy. Thank you, Dan Phone #: ###-#### Inspection requested via web by Daniel Cook
|
DOC - Permit Finaled | 8/3/2015 | 8/3/2015 | 8/3/2015 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 7/31/2015 | 8/3/2015 | 8/3/2015 | A | PASS |
Jim Page
|
|
|
Life fire safety passed/complete
|
BLD-Conference | 7/30/2015 | 7/31/2015 | 8/3/2015 | P | CANC |
Jim Storey
|
|
|
Jim, It''s a tight schedule to re-open restroom on Monday 8/3. Just wanted you to look at before we opened. BLD final will be early next week. thx Dan Phone #: ###-#### >> Inspection requested via web by Daniel Cook Inspection cancelled from web by: Daniel Cook
|
Permit Ready to Issue | | | 7/8/2015 | | DONE |
|
|
|
all requirments met
|
Issue PAID IN FULL permit | | | 7/8/2015 | | DONE |
|
|
|
|
Intake Approval | | | 6/25/2015 | | PASS |
|
|
|
|
Plan assigned to (TLW) | 6/25/2015 | | 6/25/2015 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 6/25/2015 | | 6/25/2015 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - FIRE | 6/25/2015 | | 6/25/2015 | | PASS |
Katie Marron
|
|
|
Approved on Site. TLW
|
1st review completed | | | 6/25/2015 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/25/2015 | | DONE |
|
|
|
|
Application received | | | 6/19/2015 | | DONE |
|
|
|
This permit was created on the web by Jack Fieselman
|
Plan assigned from Web | 6/19/2015 | 6/29/2015 | | | |
|
|
|
|