BLD-Final | 12/11/2015 | 12/11/2015 | 12/11/2015 | P | PASS |
Jim Sly
|
|
|
After 3:00 PM if possible Please call Dan for Access instructions Phone #: ###-#### Inspection requested via web by Daniel Appel
|
DOC - Permit Finaled | 12/11/2015 | 12/11/2015 | 12/11/2015 | P | PASS |
Jim Sly
|
|
|
|
BLD-Energy code compliance | 11/3/2015 | 11/4/2015 | 11/4/2015 | A | PASS |
Jim Storey
|
|
|
Early AM if possible Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Framing/Rough-in | 11/3/2015 | 11/4/2015 | 11/4/2015 | A | PASS |
Jim Storey
|
|
|
Early AM if possible Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Framing/Rough-in | 10/28/2015 | 10/29/2015 | 10/29/2015 | A | PART |
Phil Shearer
|
|
|
Engineered fix. Replace damaged hanger for beam over stairs, fire blocking MEC. chace. OK to insulate.
|
Plan Modification Accepted | | | 10/26/2015 | | DONE |
|
|
|
new manual j
|
Routing - MECHANICAL | 10/26/2015 | | 10/26/2015 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 10/14/2015 | 10/16/2015 | 10/15/2015 | A | PASS |
Jim Storey
|
|
|
Dan Phone #: ###-#### Inspection requested via web by Daniel Appel
|
BLD-Conference | 9/9/2015 | 9/10/2015 | 9/10/2015 | A | PASS |
Tony Young
|
|
|
Per Tony Young and Phil Shearer Foundation approved to pour. No entry in PDS system Phone #: ###-#### Inspection requested via web by Daniel Appel,, foundation was work in progress,, ok
|
BLD-Footing | 9/1/2015 | 9/2/2015 | 9/2/2015 | P | PASS |
Jim Storey
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 8/31/2015 | 9/1/2015 | 9/1/2015 | P | NR |
Jim Storey
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 8/28/2015 | 8/31/2015 | 8/31/2015 | P | NR |
Jim Storey
|
|
|
Dane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 8/20/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/20/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 7/24/2015 | | |
|
|
|
|
Plan assigned to (DAF) | 7/15/2015 | 7/15/2015 | 7/24/2015 | | PASS |
David Ferguson
|
|
|
Waiting for engineering response.
|
Routing - PLAN CHECK | 7/24/2015 | | 7/24/2015 | | PASS |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/24/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/24/2015 | | DONE |
Christina Prado
|
|
|
All requirements met
|
1st review completed | | | 7/23/2015 | | FAIL |
David Ferguson
|
|
|
Waiting for engineering response.
|
Routing - PLAN CHECK | 6/23/2015 | | 7/23/2015 | | FAIL |
David Ferguson
|
|
|
Waiting for engineering response.
|
Routing - MECHANICAL | 6/23/2015 | | 6/29/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 6/23/2015 | | 6/23/2015 | | PASS |
Andrea Tuning
|
|
|
Approved per DRH15-00237
|
Routing - Addressing | 6/23/2015 | | 6/23/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 6/23/2015 | | 6/23/2015 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 6/23/2015 | | PASS |
|
|
|
|
Application received | | | 6/22/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 22 2015 8:46AM
|
BLD-Foundation | 9/2/2015 | 9/3/2015 | | P | |
|
|
|
Wes ###-####
|