BLD-Final | 2/1/2016 | 2/1/2016 | 2/1/2016 | P | PASS |
Mike Jordan
|
|
|
Josh Phone #: ###-####
|
DOC - Permit Finaled | 2/1/2016 | 2/1/2016 | 2/1/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 1/29/2016 | 1/29/2016 | 1/29/2016 | P | CANC |
Mike Jordan
|
|
|
Josh-please call 30 minutes prior to meet Phone #: ###-####
|
BLD-Final | 1/26/2016 | 1/27/2016 | 1/27/2016 | P | NR |
Mike Jordan
|
|
|
Josh Phone #: ###-####. Adress not posted, exterior wall weather envelope not completed. No access, but noted that spindels at stairway for guards not completed. No further inspection was completed.
|
Case Summary (BLD) | | | 1/26/2016 | | DONE |
|
|
|
|
BLD-Energy code compliance | 11/6/2015 | 11/9/2015 | 11/9/2015 | A | PASS |
Mike Jordan
|
|
|
Josh Phone #: ###-####
|
BLD-Framing/Rough-in | 11/6/2015 | 11/9/2015 | 11/9/2015 | A | PASS |
Mike Jordan
|
|
|
Josh Phone #: ###-####
|
BLD-Framing/Rough-in | 11/4/2015 | 11/4/2015 | 11/4/2015 | P | FAIL |
Mike Jordan
|
|
|
Call when on your way to meet // Josh Phone #: ###-####. Complete lateralbracing on T12 trusses, nail off 2ply T22 and T25 trusses per the engineering. The 6x6 post by the furnance requires full bearing to the foundation system.
|
BLD-Framing/Rough-in | 10/30/2015 | 11/2/2015 | 11/2/2015 | P | NR |
Mike Jordan
|
|
|
Josh Phone #: ###-####. Mech. and electrical roough in inspection haver failed.
|
Plan Modification Accepted | | | 10/23/2015 | | DONE |
|
|
|
new manual j
|
Routing - MECHANICAL | 10/23/2015 | | 10/23/2015 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall cover | 10/22/2015 | 10/22/2015 | 10/22/2015 | P | PASS |
Mike Jordan
|
|
|
Shear // Josh Phone #: ###-####
|
BLD-Wall Bracing | 10/21/2015 | 10/21/2015 | 10/21/2015 | P | FAIL |
Mike Jordan
|
|
|
Josh Phone #: ###-####. Remove tyvek for wall bracing inspection.
|
BLD-Foundation | 9/21/2015 | 9/21/2015 | 9/21/2015 | P | PASS |
Mike Jordan
|
|
|
J.R. Phone #: ###-####
|
BLD-Footing | 9/17/2015 | 9/18/2015 | 9/18/2015 | P | PART |
Mike Jordan
|
|
|
Josh Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/17/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 9/16/2015 | | |
|
|
|
|
Plan assigned to (BJM) | 7/29/2015 | 7/29/2015 | 9/16/2015 | | DONE |
Brian McGowan
|
|
|
First review completed
|
Inspection Record Card- Bld | | | 9/16/2015 | | DONE |
|
|
|
|
Telephone call | | | 9/16/2015 | | DONE |
|
|
|
called George- left message that permit is ready for pick up and fees due--- called another number and talked to Josh- told him permit is ready and fees due
|
Routing - PLAN CHECK | 9/15/2015 | | 9/16/2015 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 9/16/2015 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 9/16/2015 | | 9/16/2015 | | PASS |
David Ferguson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/16/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/16/2015 | | DONE |
|
|
|
All Requirements Met
|
Plan resubmittals received | | | 9/15/2015 | | DONE |
|
|
|
received two copies of truss engineering, sheets 2, 3, 4, and 5- put on Brian's desk
|
Routing - PUBLIC WORKS | 9/14/2015 | | 9/15/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 9/11/2015 | | 9/14/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Plan resubmittals received | | | 9/11/2015 | | DONE |
|
|
|
resubmittals received 3 sets of sheet 5- customer said the address lot/block are wrong so we fixed and i sent to addressing 1st then it'll go to Brian
|
Routing - PLAN CHECK | 7/22/2015 | | 8/26/2015 | | FAIL |
Brian McGowan
|
|
|
Requested Truss package and Truss Layout. Plans to be revised to match (specifically Sheet 5)
|
Routing - MECHANICAL | | | 8/21/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | | | 8/21/2015 | | PASS |
Sue Cummings
|
|
|
Setbacks met now. driveway cannot be more than 33 ft. wide in front setback. see redlines
|
Routing - PUBLIC WORKS | | | 8/21/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Plan resubmittals received | | | 8/19/2015 | | DONE |
|
|
|
resubmittals recievced two sets of a new home since old would not fit on lot-2 each sheets 1-7, res check, manuals, small site plan, new permit app and checklist-got plans from Brian M and took to addressing
|
Plan assigned to (LEG) Tisha | 7/14/2015 | | 7/29/2015 | | DEFR |
Tisha Gallop
|
|
|
7/28
|
Routing - MECHANICAL | 7/20/2015 | | 7/22/2015 | | PASS |
Troy James
|
|
|
|
1st review completed | | | 7/22/2015 | | FAIL |
Brian McGowan
|
|
|
|
Routing - Addressing | 7/14/2015 | | 7/17/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PUBLIC WORKS | 7/17/2015 | | 7/17/2015 | | PASS |
Connie Baumgartner
|
|
|
|
Intake Approval | | | 7/14/2015 | | PASS |
|
|
|
Customer brought in most of what was needed to start review so I started it around today
|
Plans ACCEPTED BY PLAN TECH | | | 7/14/2015 | | DONE |
|
|
|
|
Telephone call | | | 7/9/2015 | | DONE |
|
|
|
called again ###-####-left message on phone-need section drawing, crawl and attic detail and also need state reg #
|
Telephone call | | | 7/7/2015 | | DONE |
|
|
|
called again to let know permit still needs drawings to start the process- left message
|
Meeting | | | 7/7/2015 | | DONE |
|
|
|
sent email asking them to please bring in the needed drawings, that we couldn't start project until we had that
|
Telephone call | | | 7/2/2015 | | DONE |
|
|
|
callede George to let know that we still have information needed before we can start the plans around. Called both #'ers on app-left message on both
|
Telephone call | | | 6/26/2015 | | DONE |
|
|
|
called Westminster homes to let know we can not start plan review until we have the drawings that are needed. left message
|
Recd Pcfee & Taken To Pln CK | | | 6/23/2015 | | DONE |
|
|
|
|
Application received | | 7/14/2015 | | | |
|
|
|
|
Routing - PLANNING | 7/17/2015 | | | | FAIL |
|
|
|
Does not meet side yard setbacks of 10'. Left 2 messages with George on 7-17-15.
|