PubWorks Subgrade Approval | 11/1/2017 | 11/1/2017 | 11/1/2017 | | DONE |
Melissa Jannusch
|
|
|
Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Aging Inspection | 10/28/2016 | 10/28/2016 | 11/1/2016 | | FAIL |
Tony Young
|
|
|
|
CHANGE STATUS TO (ISS) | | | 7/21/2016 | | DONE |
|
|
|
|
(F) Reprint permit | | | 7/21/2016 | | DONE |
|
|
|
|
OVERRIDE | | | 7/19/2016 | | |
|
|
|
|
Plan assigned to (LEG) Tisha | 7/14/2016 | | 7/19/2016 | | DONE |
Tisha Gallop
|
|
|
7/14 plan modification, routed to Jason Taylor
|
Routing - PLAN CHECK | 7/18/2016 | | 7/19/2016 | | PASS |
Tisha Gallop
|
|
|
|
Case Summary (BLD) | | | 7/19/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/19/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/19/2016 | | DONE |
|
|
|
DO NOT REISSUE PLAN MOD. NO FEES DUE PER TISHA
|
Routing PW Grading-Hillside | 7/18/2016 | | 7/18/2016 | | PASS |
Jason C. Taylor
|
|
|
Walls approved by structural engineer. JCT
|
Plan Modification Accepted | | | 7/14/2016 | | DONE |
|
|
|
received two copies of engineering- GC said they were requested from Jason Taylor- put them Tisha's desk
|
BLD-Final | 6/28/2016 | 7/7/2016 | 7/7/2016 | A | PEND |
Tony Young
|
|
|
Josh Phone #: ###-####,, status review
|
BLD-Final | 6/22/2016 | 6/28/2016 | 6/28/2016 | P | PEND |
Tony Young
|
|
|
Josh Phone #: ###-####
|
BLD-Final | 6/21/2016 | 6/22/2016 | 6/22/2016 | A | PEND |
Tony Young
|
|
|
Josh Phone #: ###-####,, still need hillside approval
|
BLD-Final | 6/20/2016 | 6/21/2016 | 6/21/2016 | A | PEND |
Tony Young
|
|
|
Josh Phone #: ###-####
|
BLD-Final | 6/17/2016 | 6/20/2016 | 6/20/2016 | A | PEND |
Tony Young
|
|
|
Josh Phone #: ###-####
|
BLD-Final | 6/17/2016 | 6/17/2016 | 6/17/2016 | P | PEND |
Tony Young
|
|
|
Josh Phone #: ###-####
|
BLD-Final | 6/16/2016 | 6/17/2016 | 6/17/2016 | A | PEND |
Tony Young
|
|
|
Josh Phone #: ###-####,, needs hillside final,, then ok
|
BLD-Final | 6/15/2016 | 6/16/2016 | 6/16/2016 | A | FAIL |
Tony Young
|
|
|
Josh Phone #: ###-####,, need public works,, glass guard rail approval,, fire caulking
|
BLD-Conference | 6/10/2016 | 6/13/2016 | 6/13/2016 | A | PEND |
Tony Young
|
|
|
Josh Phone #: ###-####,, need contact publuic works,, drainage ?s
|
BLD-Foundation | 6/2/2016 | 6/2/2016 | 6/2/2016 | P | DONE |
Tony Young
|
|
|
Chris
|
BLD-Footing | 6/1/2016 | 6/1/2016 | 6/1/2016 | P | PEND |
Tony Young
|
|
|
Chris Phone #: ###-####,, retaining wall footings
|
Routing PW Grading-Hillside | 5/23/2016 | | 5/24/2016 | | PASS |
Jason C. Taylor
|
|
|
Taller retaining wall engineering accepted and approved for construction. JCT
|
Routing - PLAN CHECK | 5/23/2016 | | 5/24/2016 | | PASS |
Tisha Gallop
|
|
|
plan mod for retaining wall revision
|
Plan assigned to (LEG) Tisha | 5/23/2016 | | 5/24/2016 | | DONE |
Tisha Gallop
|
|
|
Plan mod 5/23, revised garage drive retaining wall footing
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/24/2016 | | DONE |
|
|
|
no fee
|
CHANGE STATUS TO (ISS) | | | 5/24/2016 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 5/24/2016 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 5/23/2016 | | DONE |
|
|
|
received structural engineering calcs for revised footing at garage driveway wall
|
BLD-Energy code compliance | 2/1/2016 | 2/1/2016 | 2/1/2016 | P | PASS |
Tony Young
|
|
|
Josh Phone #: ###-####
|
BLD-Framing/Rough-in | 1/26/2016 | 1/27/2016 | 1/27/2016 | A | PART |
Tony Young
|
|
|
Josh Phone #: ###-####,, house ok to insulate,, porch not done yet on south side
|
Telephone call | | | 1/22/2016 | | DONE |
Tisha Gallop
|
|
|
Telephone call with Aaron McGee to change deck joists from 2x12 FRT @ 24" oc to 4x8 DF#2 @ 19.2" oc. Told him 4x8 DF#2 @ 19.2" oc ok for bearing and meets WUI code requirements. Will redline on office set of plans.
|
BLD-Wall Bracing | 1/14/2016 | 1/15/2016 | 1/15/2016 | A | PART |
Tony Young
|
|
|
Aaron Phone #: ###-####,, exterior ok,, per plan
|
Telephone call | | | 1/15/2016 | | DONE |
Tisha Gallop
|
|
|
phone call with contractor (Josh) wants to change deck beam from 5-1/2x13 to 3-1/2x11-7/8 Glulam. Ok for bearing, but need to submit Glulam calc for fire resistance or approval from Fire Marshal for WUI Zone A requirements.
|
BLD-Footing | 11/20/2015 | 11/20/2015 | 11/20/2015 | P | PART |
Tony Young
|
|
|
Aaron Phone #: ###-####,, deck footings ok,, slab
|
PubWorks Subgrade Approval | 11/18/2015 | 11/18/2015 | 11/18/2015 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Plan resubmittals received | | | 11/12/2015 | | DONE |
|
|
|
received two copies of new ResCheck and plan sheets A1.0 basement floor plan, A1.1 main floor plan and sheet A3.1 building sections.
|
Routing - PLAN CHECK | 11/12/2015 | | 11/12/2015 | | PASS |
Tisha Gallop
|
|
|
plan mod to upgrade insulation in basement walls and ceiling per new ResCheck. no fee
|
CHANGE STATUS TO (ISS) | | | 11/12/2015 | | DONE |
|
|
|
|
BLD-Foundation | 10/16/2015 | 10/16/2015 | 10/16/2015 | P | PART |
Dave Hannah
|
|
|
Chris Phone #: ###-####
|
BLD-Footing | 10/15/2015 | 10/15/2015 | 10/15/2015 | P | PASS |
Jim Storey
|
|
|
Scott Phone #: ###-####
|
PubWorks Subgrade Approval | 10/12/2015 | 10/12/2015 | 10/12/2015 | | DONE |
Jason C. Taylor
|
|
|
* NORTH SIDE RETAINING WALLS/FOOTINGS ONLY***A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Foundation | 9/8/2015 | 9/9/2015 | 9/9/2015 | A | PASS |
Jim Sly
|
|
|
Wall // Chris Phone #: ###-####
|
BLD-Footing | 8/27/2015 | 8/28/2015 | 8/28/2015 | A | PASS |
Jim Sly
|
|
|
Pour time at 10 // Scott Phone #: ###-####
|
BLD-Footing | 8/24/2015 | 8/25/2015 | 8/25/2015 | P | CANC |
Tony Young
|
|
|
Canceled per Scott Phone #: ###-####
|
PubWorks Subgrade Approval | 8/19/2015 | 8/19/2015 | 8/19/2015 | | DONE |
Jason C. Taylor
|
|
|
****Main House & Grage Footings only**A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 7/30/2015 | | DONE |
Christina Prado
|
|
|
|
OVERRIDE | | | 7/28/2015 | | |
|
|
|
|
Inspection Record Card- Bld | | | 7/28/2015 | | DONE |
|
|
|
|
Telephone call | | | 7/28/2015 | | DONE |
|
|
|
called Aaron- told him permit is ready for pick up and fees due
|
Routing - PLAN CHECK | 7/24/2015 | | 7/28/2015 | | PASS |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/28/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/28/2015 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 7/28/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/28/2015 | | DONE |
|
|
|
requirements met
|
Plan assigned to (LEG) Tisha | 6/24/2015 | | 7/28/2015 | | DONE |
Tisha Gallop
|
|
|
1st review 7/23 L2; plan check
|
Case Summary (BLD) | | | 7/24/2015 | | DONE |
|
|
|
|
Plan resubmittals received | | | 7/24/2015 | | DONE |
Christina Prado
|
|
|
Received two sets of revised plan sheets marked S1.3, A4.1, A1.0, A3.1, A1.1 & S1.2, as well as two sets revised foundation calcs, truss calcs and response letter; Plans stamped and take to LEG for additional review
|
1st review completed | | | 7/23/2015 | | FAIL |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 7/14/2015 | | 7/23/2015 | | FAIL |
Tisha Gallop
|
|
|
see plan review report e-mailed to Aaron MeGee/Element Homes
|
Routing PW Grading-Hillside | 7/14/2015 | | 7/14/2015 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
Prior to obtaining a final for the permit, the storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
|
Routing - PUBLIC WORKS | 7/14/2015 | | 7/14/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Plan resubmittals received | | | 7/14/2015 | | DONE |
Carlos Velazquez
|
|
|
Received one set of Site Grading & Drainage Plan per JCT's requiest; Plans stamped and taken to LEG for insertion into plan set.
|
Routing - PLAN CHECK | 7/8/2015 | | 7/8/2015 | | PEND |
Tisha Gallop
|
|
|
routed to PW due to resubmittal for grading received 7/6/15
|
Routing - FIRE | 7/7/2015 | | 7/8/2015 | | PASS |
Scott Arellano
|
|
|
Approved as shown. No comments attached.
|
Routing - Erosion and Sediment | 7/6/2015 | | 7/7/2015 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)
WUI Zone A; Permit for the construction of a new 2,649 sq. ft., one story with a basement level (first story 1,590 sq. ft., basement level 1,059 sq. ft.) single family dwelling with 4 bedrooms, 4 bathrooms, approximately 497 sq. ft. of covered patio/porch and a 727 sq. ft. attached garage
|
Plan resubmittals received | | | 7/6/2015 | | DONE |
Christina Prado
|
|
|
Received one set of Site Grading & Drainage Plan per JCT's requiest; Plans stamped and taken to LEG for insertion into plan set.
|
Routing - MECHANICAL | 7/2/2015 | | 7/6/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 7/2/2015 | | 7/2/2015 | | PASS |
Brent Moore
|
|
|
|
Routing - PUBLIC WORKS | 7/2/2015 | | 7/2/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Grading-Hillside | 6/25/2015 | | 7/2/2015 | | FAIL |
Jason C. Taylor
|
|
|
Need 3rd grading plan for files.
|
Routing PW Sewer Rating | 6/25/2015 | | 6/25/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/24/2015 | | DONE |
|
|
|
|
Intake Approval | | | 6/24/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/24/2015 | | DONE |
|
|
|
|
Routing - Addressing | 6/24/2015 | | 6/24/2015 | | PASS |
Emily Dixon
|
|
|
|
Application received | | 6/23/2015 | | | |
|
|
|
|