Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD15-02185
StatusFinaled
Name CULPAN & COMPANY
Site Address 1849 S TRAVERTINE WAY
Project NameKing Residence
Customer Number 
ePlanReviewYes
Description
WUI Zone A; Permit for the construction of a new 5,433 sq. ft., two story (first story 3,950 sq. ft., second story 1,483 sq. ft.) single family dwelling with 4 bedrooms, 3 full bathrooms & 3 half bathrooms, approximately 1,525 sq. ft. of covered patio/porch and a 1,928 sq. ft. attached garage per the approved plans, engineering, ResCheck, ACCA report and any notations. R-1A/DA zoning and setbacks per planning. //leg A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at 384-3946

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at 384-3946.
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/16/20166/17/20166/17/2016PPASS
DetailsDave Hannah
Clive Phone #: ###-####-if no one is there call Clive for access and pleae where booties at garage door
DOC - Permit Finaled6/17/20166/17/20166/17/2016PPASS
DetailsDave Hannah
PubWorks Occupancy Approval6/17/20166/17/20166/17/2016 DONE
DetailsJason C. Taylor
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Jason Taylor ###-####.
Plan Modification Accepted  3/16/2016 DONE
plan modification to change decking material and exterior wall covering to Cumaru.
Routing - PLAN CHECK3/16/2016 3/16/2016 PASS
DetailsTisha Gallop
material approved by fire marshal for decking and exterior wall covering.
CHANGE STATUS TO (ISS)  3/16/2016 DONE
plan mod changed status to review. Small plan mod, no fee due.
BLD-Energy code compliance12/24/201512/28/201512/28/2015APASS
DetailsPhil Shearer
Clyde Phone #: ###-####
BLD-Framing/Rough-in12/17/201512/18/201512/18/2015APASS
DetailsJim Storey
plans in kitchen left to fire. Call for access // Clyde Phone #: ###-#### canlights not boxed in soffits for wui code insp.
Plan Modification Accepted  12/10/2015 DONE
new manual j report
Routing - MECHANICAL12/10/2015 12/10/2015 PASS
DetailsTroy James
resubmitted manual j report
BLD-Wall Bracing11/25/201511/25/201511/25/2015PPASS
DetailsPhil Shearer
Plans in kitchen near fireplace - Clive Phone #: ###-####
Inspection Record Card- Bld  11/10/2015 DONE
BLD-Foundation9/22/20159/22/20159/22/2015PPASS
DetailsJim Sly
Pat Phone #: ###-####
BLD-Footing9/15/20159/15/20159/15/2015PPASS
DetailsPhil Shearer
pat Phone #: ###-####
Issue PAID IN FULL permit  9/1/2015 DONE
Inspection Record Card- Bld  9/1/2015 DONE
Override - Parcel Holds  8/31/2015  
OVERRIDE  8/27/2015  
Override - Parcel Holds  8/27/2015  
Permit Ready to Issue  8/27/2015 DONE
ALL REQUIREMENTS MET
Plan assigned to (LEG) Tisha7/22/2015 8/27/2015 DONE
DetailsTisha Gallop
passed 8/25; pending hillside
Routing PW Grading-Hillside8/21/2015 8/26/2015 PASS
DetailsJason C. Taylor
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Jason Taylor at ###-####.
Routing - PLAN CHECK8/21/2015 8/25/2015 PASS
DetailsTisha Gallop
Plan resubmittals received  8/21/2015 DONE
Routing - MECHANICAL8/21/2015 8/21/2015 PASS
DetailsTroy James
1st review completed  8/13/2015 FAIL
DetailsTisha Gallop
pending approvals from Hillside, Mechanical, and Plan Check
Routing - PLAN CHECK7/22/2015 8/13/2015 FAIL
DetailsTisha Gallop
Routing - FIRE7/22/20157/22/20157/24/2015 PASS
DetailsScott Arellano
Applicated reviewed for fire department access and water availability.
Routing PW Grading-Hillside7/22/2015 7/24/2015 FAIL
DetailsJason C. Taylor
See notes in ePlan. JCT
Routing - Addressing7/22/2015 7/23/2015 PASS
DetailsEmily Dixon
Routing - PUBLIC WORKS7/22/2015 7/23/2015 PASS
DetailsConnie Baumgartner
Routing - Erosion and Sediment7/22/2015 7/23/2015 PASS
DetailsEvan Jenkins
(Site Prep Inspection and Approval Required Prior to Earth Disturbance) Narrative Authorized with Conditions

WUI Zone A; Permit for the construction of a new 5,433 sq. ft., two story (first story 3,950 sq. ft., second story 1,483 sq. ft.) single family dwelling with 4 bedrooms, 3 full bathrooms & 3 half bathrooms, approximately 1,050 sq. ft. of covered patio/porch and a 1,928 sq. ft. attached garage
Routing - MECHANICAL7/22/2015 7/23/2015 FAIL
DetailsTroy James
Plans ACCEPTED BY PLAN TECH  7/22/2015 DONE
DetailsChristina Prado
Intake Approval  7/22/2015 PASS
DetailsChristina Prado
Override - Parcel Holds  7/22/2015  
Recd Pcfee & Taken To Pln CK  7/22/2015 DONE
DetailsChristina Prado
Application received  6/24/2015 DONE
Application submitted via PDS Online on Jun 24 2015 7:36AM
PubWorks Subgrade Approval8/31/20158/31/2015   
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
Routing - PLANNING7/22/2015   PASS
DetailsLeon Letson
see redline
**Appeal period for Hillside Approval (CFH15-00039) ends 7/30/15 at 5 p.m.