Third Notice | | 1/18/2016 | 2/11/2016 | | DONE |
|
|
|
|
Second Notice | | 12/20/2015 | 1/13/2016 | | DONE |
|
|
|
Mailed 1-14-16
|
First Notice | | 11/15/2015 | 12/10/2015 | | DONE |
|
|
|
mailed 12-11-15
|
Print Occupancy Form | | | 11/5/2015 | | DONE |
|
|
|
|
Permanent Occupancy | | | 11/5/2015 | | DONE |
|
|
|
|
BLD-Final | 10/13/2015 | 10/13/2015 | 10/13/2015 | P | PASS |
Jim Sly
|
|
|
Elaina Phone #: ###-#### OK for Perm Occ.
|
FIRE-Final Inspection | 10/13/2015 | 10/13/2015 | 10/13/2015 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 9/4/2015 | 9/4/2015 | 9/4/2015 | P | PART |
Jim Sly
|
|
|
Elaina ###-#### OK for Temp Occ. OK for Perm Occ. when Fire Perms.
|
FIRE-Final Inspection | 9/4/2015 | 9/4/2015 | 9/4/2015 | P | PART |
Jim Page
|
|
|
Previously noted items corrected, TCO authorized for 30 days per conversation with Scott Arellano. Fire alarm alarm system to be repaired/altered on a seperste FIR permit by authorized contractor, TCO contigent on fire alarm permit application/review.
|
BLD-Final | 9/1/2015 | 9/4/2015 | 9/4/2015 | A | CANC |
Jim Sly
|
|
|
Elaina Phone #: ###-####
|
Temporary Occupancy | 9/4/2015 | 12/3/2015 | 9/4/2015 | | DONE |
Brittany Hill
|
|
|
|
Telephone call | | | 8/31/2015 | | DONE |
Scott Arellano
|
|
|
Spoke with Elaina Becker with Saint Marks pre-school. Informed Elaina that a separate fire sprinkler permit and fire alarm permit will be required for the necessary modifications to the building fire protection systems. Once those permit applications have been submitted to the City for review and approval, an evaluation for temporary occupancy can take place.
|
FIRE-Final Inspection | 8/26/2015 | 8/28/2015 | 8/28/2015 | A | FAIL |
Troy Cobbley
|
|
|
Finish construction so the door hardware and new exit signs can be verified, provide permit/work to modify the existing fire alarm system, install smoke alarms as discussed (can be stand alone), provide emergency lighting for the exit path and exit discharge, sprinkler heads in daycare areas need to be quick responce/residential type and provide flash lights for emergency lighting within the day care as discussed. Elaina// please call before Phone #: ###-####
|
FIRE-Final Inspection | 8/26/2015 | 8/26/2015 | 8/26/2015 | P | CANC |
Troy Cobbley
|
|
|
Rescheduled for friday.
|
FIRE-Final Inspection | 8/26/2015 | 8/27/2015 | 8/26/2015 | A | CANC |
Troy Cobbley
|
|
|
To be rescheduled for Friday.
Elaina// please call before Phone #: ###-####
|
Issue PAID IN FULL permit | | | 8/26/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/26/2015 | | DONE |
|
|
|
|
(F) Reprint permit | | | 8/26/2015 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 7/6/2015 | 7/6/2015 | 7/27/2015 | | PASS |
Carl Westfall
|
|
|
ST MARK'S PRESCHOOL (July 24 - 15 days) Level 3 TI - ePlanReview
|
Routing Off Site - C.D.H | 7/6/2015 | | 7/27/2015 | | PASS |
Carl Westfall
|
|
|
According to Natasha with CDHD, this project is approved by them.
|
1st review completed | | | 7/27/2015 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/27/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/27/2015 | | DONE |
|
|
|
***ALL REQUIREMENTS MET*** NEED GC form and Certificate of value (FORMS IN DOCS)
***NEED A LETTER FROM THE OWNER(S) THAT THEY ARE LETTING MARK HOPKINS ACT AS THE GC***
|
Routing - PLAN CHECK | 7/6/2015 | | 7/24/2015 | | PASS |
Carl Westfall
|
|
|
Drawings approved with redlines.
|
Routing - FIRE | 7/6/2015 | 7/6/2015 | 7/6/2015 | | PASS |
Scott Arellano
|
|
|
Comments attached to plans
|
Routing - PLANNING | 7/6/2015 | | 7/6/2015 | | PASS |
Cody Riddle
|
|
|
Cody Riddle - CUP14-00022
Interior remodel only. The childcare facility is limited to no more than 24 children, and specified in CUP14-00022.
|
Intake Approval | | | 7/6/2015 | | PASS |
Jason Blais
|
|
|
Prescreen approved by Carl Madsen and plan review fees paid.
|
Pending Assignment by JCB | 7/6/2015 | | 7/6/2015 | | DONE |
Jason Blais
|
|
|
|
Routing - Addressing | 7/6/2015 | | 7/6/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 7/6/2015 | | 7/6/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Plan Reviewer's activity | | | 7/6/2015 | | DONE |
Jason Blais
|
|
|
Emailed architect to contact ACHD to determine if any additional impact fees are due. Will need written verification from ACHD prior to the building permit being issued.
|
Application received | | | 6/30/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 30 2015 6:42PM
|