BLD-Conference | 11/15/2016 | 11/15/2016 | 11/15/2016 | A | PEND |
Tony Young
|
|
|
rock retaining walls appear to be in place,, will need hillside approval and engineer signoff
|
BLD-Aging Inspection | 11/7/2016 | 11/7/2016 | 11/15/2016 | | PEND |
Tony Young
|
|
|
|
OVERRIDE | | | 12/23/2015 | | |
|
|
|
|
Override - Parcel Holds | | | 12/23/2015 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 12/23/2015 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (LEG) Tisha | 7/6/2015 | | 12/23/2015 | | DONE |
Tisha Gallop
|
|
|
1st review 8/12 ePlan retaining wall; outside struc and hillside
|
Routing - PLAN CHECK | | | 12/23/2015 | | PASS |
Tisha Gallop
|
|
|
|
Routing PW Grading-Hillside | 12/22/2015 | | 12/23/2015 | | PASS |
Jason C. Taylor
|
|
|
Retaining wall engineering approved. JCT
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/23/2015 | | DONE |
|
|
|
yes esc, n/a energy
|
Override - Parcel Holds | | | 12/23/2015 | | |
|
|
|
|
Permit Ready to Issue | | | 12/23/2015 | | DONE |
Christina Prado
|
|
|
Need GC Form & RP for issuance
|
Plan resubmittals received | | | 12/22/2015 | | DONE |
|
|
|
in ePlan
|
Plan resubmittals received | | | 12/22/2015 | | DONE |
|
|
|
received (2) sets of calculations
|
Routing - PLAN CHECK | 7/6/2015 | | 8/12/2015 | | FAIL |
Tisha Gallop
|
|
|
per outside structural and hillside review
|
Routing Off Site - STRUCTURAL | 7/20/2015 | | 8/12/2015 | | FAIL |
Tisha Gallop
|
|
|
see review comments in documents
|
1st review completed | | | 8/12/2015 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLANNING | 7/6/2015 | | 7/9/2015 | | PASS |
Josh Wilson
|
|
|
Ok per DRH14-00164
|
Routing - Erosion and Sediment | 7/6/2015 | | 7/7/2015 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)
Review/approval of retaining walls for North Hill Subdivision: Demo of Existing Retaining Walls Only.
|
Routing PW Grading-Hillside | 7/7/2015 | | 7/7/2015 | | FAIL |
Jason C. Taylor
|
|
|
This submittal was for retaining wall approval for an outside structural engineer to review. Once structural approves design then PW Hillside will review. Jason Taylor
|
Plans ACCEPTED BY PLAN TECH | | | 7/6/2015 | | DONE |
|
|
|
|
Intake Approval | | | 7/6/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/6/2015 | | DONE |
|
|
|
|
Application received | | | 7/2/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 2 2015 11:48AM
|