First Notice | | 8/16/2015 | 9/14/2015 | | DONE |
|
|
|
mailed 9-14-15
|
Permanent Occupancy | | | 8/6/2015 | | DONE |
|
|
|
|
BLD-Final | 8/4/2015 | 8/4/2015 | 8/4/2015 | P | PASS |
Mike Jordan
|
|
|
would like call ahead; David Phone #: ###-####
|
BLD-Final | 7/31/2015 | 7/31/2015 | 7/31/2015 | P | PART |
Mike Jordan
|
|
|
would like call ahead; David Phone #: ###-####. Ok for tempp oocc. Needs to install ADA service counter.
|
FIRE-Final Inspection | 7/30/2015 | 7/31/2015 | 7/31/2015 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 7/29/2015 | 7/30/2015 | 7/30/2015 | A | FAIL |
Troy Cobbley
|
|
|
Repair the exit signs at the front and rear exit doors.
|
BLD-Framing/Rough-in | 7/17/2015 | 7/17/2015 | 7/17/2015 | P | PASS |
Jim Sly
|
|
|
Inspection requested via web by Matt Guho
|
Issue PAID IN FULL permit | | | 7/15/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/15/2015 | | DONE |
|
|
|
|
Plan assigned to (AJS) | 7/10/2015 | | 7/14/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
1st review completed Vapor Lounge
|
Routing - PLAN CHECK | 7/10/2015 | | 7/14/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
1st review completed | | | 7/14/2015 | | FAIL |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - PLAN CHECK | 7/14/2015 | | 7/14/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/14/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/14/2015 | | DONE |
|
|
|
Need GC Form and Revised Cert of Value- ALL REQUIRMENTS MET 7-15-15 ///CEV
|
Routing - Design Review | 7/10/2015 | | 7/10/2015 | | PASS |
Sarah Schafer
|
|
|
Property is within a C-2 zone and over 300-feet from residential so the use is allowed. Vape lounges are treated as tobacco bars and must meet the same ordinance requirements.
|
Pending Assignment by TLW | 7/10/2015 | | 7/10/2015 | | DONE |
Tim L. Woodard
|
|
|
|
Intake Approval | | | 7/9/2015 | | |
|
|
|
|
Application received | | | 7/2/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 2 2015 6:29PM
|