BLD-Foundation | 8/21/2015 | 8/21/2015 | 8/21/2015 | P | PART |
Dave Hannah
|
|
|
Frank Phone #: ###-#### crawl space fill 18inchs below top of wall
|
BLD-Framing/Rough-in | 7/29/2015 | 7/29/2015 | 7/29/2015 | P | PART |
Bob Archibald
|
|
|
Eld Phone #: ###-####. This was a foundation inspection. Informed contractor to provide required foundation vents as per plan and also provide elevation certificate prior to anchoring house to foundation.
|
Override - Parcel Holds | 7/29/2015 | 1/1/1900 | 7/29/2015 | | |
|
|
|
Not a "Final" inspection. Frame ONLY.
|
BLD-Footing | 7/27/2015 | 7/28/2015 | 7/28/2015 | A | PASS |
Mike Jordan
|
|
|
Frank Phone #: ###-####
|
OVERRIDE | | | 7/23/2015 | | |
|
|
|
|
OVERRIDE | | | 7/23/2015 | | |
|
|
|
|
OVERRIDE | | | 7/23/2015 | | |
|
|
|
|
OVERRIDE | | | 7/23/2015 | | |
|
|
|
|
OVERRIDE | | | 7/23/2015 | | |
|
|
|
|
OVERRIDE | | | 7/23/2015 | | |
|
|
|
|
OVERRIDE | | | 7/23/2015 | | |
|
|
|
|
Case Summary (BLD) | | | 7/23/2015 | | DONE |
|
|
|
|
1st review completed | | | 7/23/2015 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/23/2015 | | DONE |
Tisha Gallop
|
|
|
|
Override - Parcel Holds | | | 7/23/2015 | | |
|
|
|
|
Permit Ready to Issue | | | 7/23/2015 | | DONE |
|
|
|
ALL REQUIREMENTS MET
|
Plan assigned to (LEG) Tisha | 7/6/2015 | | 7/23/2015 | | DONE |
Tisha Gallop
|
|
|
1st review 7/17; house move
|
Routing - PLAN CHECK | 7/6/2015 | | 7/23/2015 | | PASS |
Tisha Gallop
|
|
|
|
Inspection Record Card- Bld | | | 7/23/2015 | | DONE |
|
|
|
|
Telephone call | | | 7/23/2015 | | DONE |
Christina Prado
|
|
|
called Frank Eld to advise permit is ready and gave fees due
|
Override - Parcel Holds | | | 7/23/2015 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 7/23/2015 | | DONE |
Christina Prado
|
|
|
|
Routing PW Flood Plain | 7/17/2015 | | 7/22/2015 | | PASS |
Jim Wyllie
|
|
|
Two more Elevation Certificates are required; one prior to placement of the house on the foundation and one based upon finished construction.
Jim Wyllie / ###-####
|
Plan resubmittals received | | | 7/17/2015 | | DONE |
|
|
|
received one copy elevation certificate
|
Telephone call | | | 7/15/2015 | | DONE |
Tisha Gallop
|
|
|
sent e-mail to Frank Eld with questions on plan and notified him failed floodplain review, need elevation certificate.
|
Routing - PLANNING | 7/8/2015 | | 7/9/2015 | | PASS |
Josh Wilson
|
|
|
OK per CVA15-00009 and DRH15-00140
|
Routing - PUBLIC WORKS | 7/8/2015 | | 7/8/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Flood Plain | 7/7/2015 | | 7/7/2015 | | FAIL |
Jason C. Taylor
|
|
|
Elevation certificate was not submitted with application. Phone number not present on application to contact applicant. Plan cannot be approved until a completed elevation certificate is submitted. Jason Taylor ###-####.
|
Routing - Addressing | 7/6/2015 | | 7/7/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Intake Approval | | | 7/6/2015 | | PASS |
|
|
|
|
Application received | | 7/6/2015 | | | |
|
|
|
|