Third Notice | | 2/16/2016 | 2/26/2016 | | DONE |
|
|
|
This permit finaled on the web by Tara May
|
Third Notice | | 1/17/2016 | 2/11/2016 | | DONE |
|
|
|
|
Second Notice | | 12/20/2015 | 1/12/2016 | | DONE |
|
|
|
Mailed 1-13-16
|
First Notice | 12/2/2015 | 12/2/2015 | 12/10/2015 | | DONE |
Mike Jordan
|
|
|
Mailed 12-11-15
|
BLD-Final | 12/1/2015 | 12/2/2015 | 12/2/2015 | P | PASS |
Mike Jordan
|
|
|
Scott Phone #: ###-####
|
DOC - Permit Finaled | 12/2/2015 | 12/2/2015 | 12/2/2015 | P | PASS |
Mike Jordan
|
|
|
|
Zoning Approval | 12/2/2015 | 12/2/2015 | 12/2/2015 | | DONE |
Andrea Tuning
|
|
|
|
FIRE-Final Inspection | 10/9/2015 | 10/9/2015 | 10/9/2015 | P | PASS |
Jim Page
|
|
|
Life fire safety passed/complete
|
BLD-Final | 10/9/2015 | 10/9/2015 | 10/9/2015 | P | CANC |
Jim Page
|
|
|
|
BLD-Other | 10/9/2015 | 10/9/2015 | 10/9/2015 | A | PASS |
Bill VanDegrift
|
|
|
plumbing for the vinalla was permitted and inspected with the TI. Final ok
|
BLD-Conference | 10/6/2015 | 10/6/2015 | 10/6/2015 | P | DONE |
Mike Jordan
|
|
|
|
BLD-Final | 10/5/2015 | 10/6/2015 | 10/6/2015 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Stimpson
|
FIRE-Conference | 10/6/2015 | 10/6/2015 | 10/6/2015 | A | DONE |
Jim Page
|
|
|
Life fire safety conference complete, discussed items that will be inspected during final life fire safety inspection.
|
FIRE-Final Inspection | 10/5/2015 | 10/6/2015 | 10/6/2015 | A | CANC |
Jim Page
|
|
|
A FIR Permit that is associated with this BLD Permit is still in issued status, contractor will reschedule life fire safety inspection to be completed after FIR permit is inspected/finaled.
|
BLD-Ceiling Grid Inspection | 9/24/2015 | 9/25/2015 | 9/25/2015 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Stimpson. Kitchen and dinning areas ok,.
|
BLD-Other | 8/31/2015 | 8/31/2015 | 8/31/2015 | P | PASS |
Mike Jordan
|
|
|
This is for one hour demising wall fire caulking. Phone #: ###-#### Inspection requested via web by Scott Stimpson
|
BLD-Framing/Rough-in | 8/25/2015 | 8/26/2015 | 8/26/2015 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Scott Stimpson. Interior steel stud framed walls ok. Interior wood framed tenant demissing wall ok. Hardlids ok pending mech. and fire sprinkler rough in inspections.
|
Issue PAID IN FULL permit | | | 8/6/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 7/23/2015 | | |
|
|
|
|
Plan assigned to (CDM) | 7/7/2015 | 7/7/2015 | 7/23/2015 | | PASS |
Carl D Madsen
|
|
|
First review completed
|
Routing - Addressing | 7/14/2015 | | 7/23/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PLAN CHECK | 7/14/2015 | | 7/23/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/23/2015 | | DONE |
|
|
|
|
Case Summary (BLD) | | | 7/23/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/23/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/23/2015 | | DONE |
|
|
|
need RP- 7-23-15 done CAN
|
Telephone call | | | 7/23/2015 | | DONE |
|
|
|
called John to let know permit is ready and how much is owed-we need RP-left message on his phone -also called Eron with Radix he gave me the RP
|
Routing - PLANNING | 7/16/2015 | | 7/16/2015 | | PASS |
Andrea Tuning
|
|
|
|
Routing PW Solid Waste | 7/14/2015 | | 7/16/2015 | | PASS |
Megan Durrell
|
|
|
|
Routing - PUBLIC WORKS | 7/14/2015 | | 7/16/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Erosion and Sediment | 7/16/2015 | | 7/16/2015 | | PASS |
Andy J. Long
|
|
|
ESC plan waiver submitted and approved. Need to designate valid RP on permit.
|
Routing PW Sewer Rating | 7/14/2015 | | 7/14/2015 | | PASS |
Jennifer Bruner
|
|
|
Call West Boise Sewer District ###-####
|
Routing - PLAN CHECK | 7/7/2015 | | 7/12/2015 | | FAIL |
Carl D Madsen
|
|
|
|
1st review completed | | | 7/12/2015 | | FAIL |
|
|
|
E-Mailed Plan review report to John Day and Eron 7-12-15
|
Plans ACCEPTED BY PLAN TECH | | | 7/7/2015 | | DONE |
|
|
|
|
Intake Approval | | | 7/7/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/7/2015 | | DONE |
|
|
|
|
Application received | | 7/6/2015 | | | |
|
|
|
|