Third Notice | | 12/15/2015 | 12/21/2015 | | DONE |
|
|
|
This permit finaled on the web by derek cooper
|
Third Notice | | 11/14/2015 | 12/10/2015 | | DONE |
|
|
|
|
Second Notice | | 10/22/2015 | 11/9/2015 | | DONE |
|
|
|
Mailed 11-10-15
|
First Notice | | 10/4/2015 | 10/12/2015 | | DONE |
|
|
|
Mailed 10-13-15
|
BLD-Final | 9/24/2015 | 9/24/2015 | 9/24/2015 | P | PASS |
Jim Sly
|
|
|
Zack Phone #: ###-#### OK for Perm Occ.
|
Permanent Occupancy | | | 9/24/2015 | | DONE |
|
|
|
|
BLD-Final | 9/22/2015 | 9/22/2015 | 9/22/2015 | P | PART |
Phil Shearer
|
|
|
Zach Phone #: ###-####. OK for TCO
|
BLD-Final | 9/18/2015 | 9/21/2015 | 9/22/2015 | P | CANC |
Phil Shearer
|
|
|
Zach Phone #: ###-####
|
BLD-Conference | 9/21/2015 | 9/21/2015 | 9/21/2015 | P | DONE |
Phil Shearer
|
|
|
Zach Phone #: ###-####
|
FIRE-Final Inspection | 9/18/2015 | 9/21/2015 | 9/21/2015 | A | PASS |
Jim Page
|
|
|
Life fire safety passed/complete
|
FIRE-Final Inspection | 9/18/2015 | 9/18/2015 | 9/18/2015 | P | CANC |
Jim Page
|
|
|
Cannot perform life fire safety inspection, this project has a FIR permit that is still in issued status, need to final the FIR permit before life fire safety inspection can be accomplished.
|
FIRE-Conference | 9/15/2015 | 9/16/2015 | 9/16/2015 | A | DONE |
Thomas Walsh
|
|
|
Preliminary fire inspection of TI area. Fire sprinklers already inspected (see FIR15-00611). Need exit signs installed per plans, and door hardware changed out - currently dead bolts installed on exit doors. Need fire extinguisher mounted.
|
BLD-Framing/Rough-in | 9/1/2015 | 9/1/2015 | 9/1/2015 | P | PASS |
Dave Hannah
|
|
|
Zack Phone #: ###-####
|
Print Occupancy Form | | | 7/22/2015 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/22/2015 | | DONE |
|
|
|
|
Plan assigned to (JG) | 7/16/2015 | 7/16/2015 | 7/21/2015 | | PASS |
Javier Guzman
|
|
|
1st review completed, Pingman Tools
|
Routing - PLAN CHECK | 7/21/2015 | | 7/21/2015 | | PASS |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/21/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/21/2015 | | DONE |
|
|
|
Need GC Form and Revised Cert of Value
|
Routing - PLAN CHECK | 7/16/2015 | | 7/20/2015 | | FAIL |
Javier Guzman
|
|
|
ePlan
|
1st review completed | | | 7/20/2015 | | DONE |
Javier Guzman
|
|
|
|
Routing - PUBLIC WORKS | 7/16/2015 | | 7/17/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Sewer Rating | 7/17/2015 | | 7/17/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Intake Approval | | | 7/16/2015 | | PASS |
Carl D Madsen
|
|
|
|
Routing - Addressing | 7/16/2015 | | 7/16/2015 | | PASS |
Emily Dixon
|
|
|
|
Intake Approval | | | 7/8/2015 | | FAIL |
|
|
|
No small documents have been uploaded please upload the submittal checklist with all required documents.
|
Application received | | | 7/7/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 7 2015 12:38PM
|