BLD-Final | 4/7/2016 | 4/12/2016 | 4/12/2016 | A | PASS |
Phil Shearer
|
|
|
Clint Phone #: ###-####
|
DOC - Permit Finaled | 4/12/2016 | 4/12/2016 | 4/12/2016 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Energy code compliance | 2/11/2016 | 2/16/2016 | 2/16/2016 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Framing/Rough-in | 2/11/2016 | 2/12/2016 | 2/12/2016 | A | PASS |
Phil Shearer
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Wall Bracing | 1/22/2016 | 1/25/2016 | 1/25/2016 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Wall
|
BLD-Foundation | 9/28/2015 | 9/29/2015 | 9/29/2015 | A | PASS |
Dave Hannah
|
|
|
Inspection request time 11:30 Phone #: ###-#### Inspection requested via web by tony L
|
BLD-Footing | 9/28/2015 | 9/28/2015 | 9/28/2015 | P | PASS |
Jim Storey
|
|
|
Inspection request time 12:30 Phone #: ###-#### Inspection requested via web by tony L placed wo insp
|
Issue PAID IN FULL permit | | | 8/11/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 7/23/2015 | | |
|
|
|
|
Plan assigned to (BJM) | 7/21/2015 | 7/21/2015 | 7/23/2015 | | DONE |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 7/23/2015 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/23/2015 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 7/23/2015 | | DONE |
|
|
|
ALL REQUIREMENTS MET
|
Inspection Record Card- Bld | | | 7/23/2015 | | DONE |
|
|
|
|
Telephone call | | | 7/23/2015 | | DONE |
|
|
|
called and left a message to notify the contractor that permit is ready and fees due
|
1st review completed | | | 7/22/2015 | | FAIL |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 7/15/2015 | | 7/22/2015 | | FAIL |
Brian McGowan
|
|
|
Need revised foundation plan for bearing locations under upper floor over third bay.
|
Plan assigned to (LEG) Tisha | 7/7/2015 | | 7/21/2015 | | DEFR |
Tisha Gallop
|
|
|
7/17
|
Routing - MECHANICAL | 7/9/2015 | | 7/15/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 7/9/2015 | | 7/9/2015 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - PUBLIC WORKS | 7/8/2015 | | 7/9/2015 | | PASS |
Connie Baumgartner
|
|
|
|
Routing - Addressing | 7/7/2015 | | 7/8/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/7/2015 | | DONE |
|
|
|
|
Intake Approval | | | 7/7/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/7/2015 | | DONE |
|
|
|
|
Application received | | 7/7/2015 | | | |
|
|
|
|
Routing - PLAN CHECK | 7/23/2015 | | | | PASS |
Brian McGowan
|
|
|
|