Print Statement | | | 1/14/2016 | | DONE |
|
|
|
|
Third Notice | | 12/15/2015 | 1/5/2016 | | DONE |
|
|
|
|
Print Statement | | | 1/5/2016 | | DONE |
|
|
|
|
Second Notice | | 11/19/2015 | 12/10/2015 | | DONE |
|
|
|
Mailed 12-11-15
|
First Notice | | 10/23/2015 | 11/9/2015 | | DONE |
|
|
|
sent in mail
|
Permanent Occupancy | | | 10/13/2015 | | DONE |
|
|
|
|
BLD-Final | 10/8/2015 | 10/9/2015 | 10/9/2015 | A | PASS |
Phil Shearer
|
|
|
Matt Phone #: ###-####
|
BLD-Final | 10/7/2015 | 10/8/2015 | 10/8/2015 | A | FAIL |
Phil Shearer
|
|
|
Matt Phone #: ###-####. Door knobs
|
BLD-Final | 9/14/2015 | 9/15/2015 | 9/15/2015 | P | NR |
Phil Shearer
|
|
|
Matt Phone #: ###-####
|
FIRE-Final Inspection | 9/14/2015 | 9/15/2015 | 9/15/2015 | A | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 9/9/2015 | 9/14/2015 | 9/14/2015 | P | CANC |
Phil Shearer
|
|
|
Matt Phone #: ###-####
|
FIRE-Final Inspection | 9/9/2015 | 9/14/2015 | 9/14/2015 | A | FAIL |
Troy Cobbley
|
|
|
Provide city approved plans, provide permit for the suppression system in the paint booth, provide sticker for the main keyed exit, provide single action hardware and remove the deadbolt at the east exit door
|
Print Occupancy Form | | | 8/26/2015 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/26/2015 | | DONE |
|
|
|
|
Plan assigned to (JG) | 8/3/2015 | 8/3/2015 | 8/21/2015 | | PASS |
Javier Guzman
|
|
|
1st review completed, Pending Mech, 8/19 Brasher's Autobody
|
Routing - MECHANICAL | 8/21/2015 | | 8/21/2015 | | PASS |
Troy James
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/21/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/21/2015 | | DONE |
|
|
|
need GC & Rev Cert of val 8-26-15-scanned GC form-just need rev cert of val CAN
|
Route to Impact Fee Review | 8/13/2015 | 8/16/2015 | 8/19/2015 | | PASS |
Cindy M. Gould
|
|
|
No impact fees the booth is a pre fabricated unit they are installing inside the building.
|
Routing PW Environmental | 8/3/2015 | | 8/13/2015 | | PASS |
Rick Christenson
|
|
|
|
1st review completed | | | 8/13/2015 | | FAIL |
Javier Guzman
|
|
|
Pending Mech
|
Routing - PLAN CHECK | 8/3/2015 | | 8/13/2015 | | PASS |
Javier Guzman
|
|
|
|
Routing - MECHANICAL | 8/3/2015 | | 8/13/2015 | | FAIL |
Troy James
|
|
|
need design for gas piping to spray booth
|
Routing - FIRE | 8/3/2015 | 8/3/2015 | 8/6/2015 | | PASS |
Katie Marron
|
|
|
Comments attached to case
|
Routing - Addressing | 8/3/2015 | | 8/3/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 8/3/2015 | | 8/3/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Pending Assignment by TLW | 8/3/2015 | | 8/3/2015 | | DONE |
Tim L. Woodard
|
|
|
|
Intake Approval | | | 7/31/2015 | | PASS |
|
|
|
|
Intake Approval | | | 7/16/2015 | | FAIL |
Javier Guzman
|
|
|
Please provide:
1. Mechanical engineered plans for the new paint booth
2. Paint booth details, manufacture, model type, specifications and UL listings
3. Clarification if the only work is to be the new paint booth
|
Application received | | | 7/13/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 13 2015 3:17PM
|