Third Notice | | 3/15/2016 | 4/18/2016 | | DONE |
|
|
|
|
Second Notice | | 2/21/2016 | 3/10/2016 | | DONE |
|
|
|
Mailed 3-11-16
|
First Notice | | 1/21/2016 | 2/11/2016 | | DONE |
|
|
|
Mailed 2-12-16
|
Permanent Occupancy | | | 1/11/2016 | | DONE |
|
|
|
|
BLD-Aging Inspection | 12/23/2015 | 12/23/2015 | 12/28/2015 | | PASS |
Jim Sly
|
|
|
|
BLD-Final | 12/23/2015 | 12/28/2015 | 12/28/2015 | P | DONE |
Jim Sly
|
|
|
as per conversation with Jim Sly; final was completed on this date alongside the "aging inspection"
|
BLD-Final | 10/23/2015 | 10/23/2015 | 10/23/2015 | P | PART |
Jim Sly
|
|
|
OK for Temp Occ. OK for Perm Occ. when Plumbing signs off Perm.
|
BLD-Final | 10/23/2015 | 10/23/2015 | 10/23/2015 | P | PASS |
Jim Sly
|
|
|
Michelle Phone #: ###-####
|
DOC - Permit Finaled | 10/23/2015 | 10/23/2015 | 10/23/2015 | P | PASS |
Jim Sly
|
|
|
|
FIRE-Final Inspection | 10/23/2015 | 10/23/2015 | 10/23/2015 | P | PASS |
Jim Page
|
|
|
Previously noted items repaired, life fire safety passed/complete
|
Temporary Occupancy | 10/23/2015 | 1/21/2016 | 10/23/2015 | | DONE |
Candy A. Nichols
|
|
|
|
CHANGE STATUS TO (ISS) | | | 10/23/2015 | | DONE |
|
|
|
Jim Sly didn't mean to final
|
FIRE-Final Inspection | 10/21/2015 | 10/22/2015 | 10/22/2015 | A | FAIL |
Troy Cobbley
|
|
|
Need correct size of fire extinguishers, need lever type hardware on north restroom door, need to repair the exit signs, need access to the FDC approved and a permit is needed for the relocation of the fire alarm control panel.
|
BLD-Conference | 10/19/2015 | 10/20/2015 | 10/20/2015 | A | NR |
Jim Sly
|
|
|
Michelle Phone #: ###-#### Need Plumbing final, Fire sprinkl final and Fire/Life final.
|
CHANGE STATUS TO (ISS) | | | 10/5/2015 | | DONE |
|
|
|
Plan Mod
|
(F) Reprint permit | | | 10/5/2015 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 9/24/2015 | 9/24/2015 | 9/30/2015 | | PASS |
Carl D Madsen
|
|
|
Plan Mod.
|
Routing - PLAN CHECK | 9/24/2015 | | 9/30/2015 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/30/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/30/2015 | | DONE |
|
|
|
DO NOT RE-ISSUE--- PLAN MOD
|
Telephone call | | | 9/30/2015 | | DONE |
|
|
|
called John- left mesage of fees due and plan mod is ready
|
Plan Modification Accepted | | | 9/24/2015 | | DONE |
|
|
|
Plan Mod for a bathroom. Two copies of sheet a200 and A201
|
Telephone call | | | 9/23/2015 | | DONE |
|
|
|
Sent an email to John Day requesting him to fill out the Plan Mod application
|
Issue PAID IN FULL permit | | | 8/25/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/24/2015 | | DONE |
Christina Prado
|
|
|
***Applicant is owner; need updated GC Form.*** Need letter from property owner to allow applicant to act as GC, GC form is signed but must be accompanied with authorization letter. No revised value as applicant is acting as GC
|
Print Occupancy Form | | | 8/24/2015 | | DONE |
Christina Prado
|
|
|
|
Telephone call | | | 8/24/2015 | | DONE |
|
|
|
Spoke with Michelle to inform her that this permit is ready and the fee amount due.
|
Plan assigned to (CDM) | 7/23/2015 | 7/23/2015 | 8/23/2015 | | PASS |
Carl D Madsen
|
|
|
First review completed
|
Routing - PLAN CHECK | 8/7/2015 | | 8/23/2015 | | PASS |
Carl D Madsen
|
|
|
|
Case Summary (BLD) | | | 8/23/2015 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/23/2015 | | DONE |
|
|
|
|
Plan resubmittals received | | | 8/21/2015 | | DONE |
|
|
|
resubmittlas received 2 of sheet A201 & comment sheet-took to Carl M
|
Plan resubmittals received | | | 8/20/2015 | | DONE |
|
|
|
Two copies of Letter, Two copies of small floor plan A201, Three copies of sheest A201, A202 and A203. Taken to Carl M
|
Routing - PLANNING | 8/6/2015 | | 8/7/2015 | | PASS |
Sue Cummings
|
|
|
|
Plan resubmittals requested | | | 8/7/2015 | | DONE |
|
|
|
|
1st review completed | | | 8/7/2015 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 7/23/2015 | | 8/6/2015 | | FAIL |
Carl D Madsen
|
|
|
E-Mailed tenant.
|
Plans ACCEPTED BY PLAN TECH | | | 7/23/2015 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/23/2015 | | DONE |
|
|
|
|
Intake Approval | | | 7/23/2015 | | PASS |
|
|
|
|
Intake Approval | | | 7/16/2015 | | FAIL |
|
|
|
The plans were incomplete and modifications require structural engineering for new window openings and zoning approval for exterior alterations to the building.
|
Application received | | 7/14/2015 | | | |
|
|
|
|