Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD15-02494
StatusFinaled
Name ESI
Site Address 195 S CAPITOL BLVD
Project NameBoise Centre East
Customer Number 
ePlanReviewYes
Description
THE DISTRICT CONVENTION CENTER FOR GBAD – BOISE CENTRE EAST AT CITY CENTER PLAZA – 1ST, 2ND, AND 4TH STORIES AND 5TH LEVEL) (10-5-16 PLAN MODIFICATION TO REMOVE THE CONVENTION CENTER KITCHEN FROM THE TENANT IMPROVEMENT SCOPE OF WORK AND TO DO THAT WORK UNDER NEW PERMIT BLD16-03512.) The fire sprinkler system is used for occupancy and to comply with the high-rise requirements of the building code.

1st Story Delivery: To construct a 525 square foot delivery area having direct access at grade to the exit passageway located between City Center Plaza and the Grove Hotel/CenturyLink Arena. Deliveries for the convention center will be brought from Capitol Blvd. to the delivery area through the exit passageway. Delivery vehicles are not allowed to be parked within the exit passageway. An interior elevator will connect the delivery area to the commercial kitchen located on the level directly above. Work is to include finishes, a freight elevator, a walk-in cooler, and a walk-in freezer. An 8” deep floor depression will be provided for the cooler and for the freezer to accommodate insulated floors. Condensate will drain to a floor sink.

1st Story Convention Center Elevator Lobby: To construct a 1,019 square foot grade level elevator lobby (343 square foot vestibule and 676 square foot lobby) to serve the convention center located on the 4th story above. The exterior entrance is connected directly to The Grove at grade. The non-rated lobby is also the continuation of a 2-hr fire-resistance-rated stairway enclosure to the outside. Work is to include suspended acoustical ceilings, suspended gypsum board ceilings, and finishes.

2nd Story (lower) Kitchen: To construct a 5,745 square foot commercial kitchen on the lower 2nd story to serve the convention center located on the 4th story above. Service elevators connect the kitchen to the convention center. Work is to include interior nonbearing walls, two restrooms accessible to the disabled, two grease hood, walk-in coolers, a walk-in freezers, kitchen equipment, suspended acoustical ceilings, and finishes. An 8” deep floor depression will be provided for the coolers and for the freezers to accommodate insulated floors. Condensate will drain to a floor sink.

2nd Story (upper) Escalator/Elevator Lobby and Pre-function / Bridge Connection: To construct a 2,977 square foot Elevator/Escalator Lobby and Pre-function area and a 1,692 square foot Bridge Connection area (4,669 square feet total) on the upper 2nd story to serve as access to the convention center located on the 4th story above. Occupants will generally arrive to this area across a bridge connected to the existing convention center. Escalators and elevators give access from the upper 2nd story to the convention center located on the 4th story above. The Elevator/Escalator Lobby and Pre-function area has access to two exits. The Bridge Connection will have access to one exit at one end and to another exit located within the existing convention center at the other end. Exit signs, emergency lighting, and panic hardware are required. Work is to include suspended acoustical ceilings, suspended gypsum board ceilings and soffits, and finishes.

4th Story Convention Center: To construct a Convention Center that will occupy the entire 49,767 square foot 4th story. Work is to include interior nonbearing walls, folding partitions, interior doors, suspended acoustical ceilings, suspended gypsum board ceilings, gypsum board soffits, and finishes. An assisted use toilet room is required because more than 6 water closets are required to serve the occupant load of the convention center. Some door modifications to two stairway enclosures are required to deal with the accumulative occupant loads resulting from the main exit. Special Inspection is required for welding. CJW (see the Comments field for the remainder of the scope of work).
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 1/15/20172/13/2017 DONE
DetailsChristina Prado
emailed to ESI rep
Print Occupancy Form  2/9/2017 DONE
Second Notice 12/22/20161/10/2017 DONE
Mailed 1-11
First Notice 12/12/201612/12/2016 DONE
Mailed 12-13-16
Permanent Occupancy  12/2/2016 DONE
BLD-Final11/16/201611/16/201611/16/2016PPASS
DetailsDave Hannah
Ok for permanent occupancy once bond is posted.
FIRE-Alarm Testing11/10/201611/10/201611/10/2016PDONE
DetailsTroy Cobbley
Fire Alarm Test of Horn strobes down Block 22 performed by Lee.
BLD-Final11/10/201611/10/201611/10/2016PPART
DetailsDave Hannah
BuildingFinal for Commercial Kitchen. In follow up to pre walk this week. On the books just to be safe. Call Adam with any questions. thanks akj. Phone #: ###-#### Inspection requested via web by Adam Johnson ok for perm occ after shell and core is finaled ok to occ/use
FIRE-Final Inspection11/10/201611/10/201611/10/2016PPASS
DetailsTroy Cobbley
Fire Life Safety inspection passed. Fire Alarm inspection performed and documented under FIR16-00128.
FIRE-Final Inspection11/9/201611/9/201611/9/2016PPART
DetailsTroy Cobbley
Final life safety field inspection completed for Commercial Kitchen area only of GBAD tenant. Pending approval of structural field inspector; OK for occupancy.
OVERRIDE  10/5/2016  
Plan assigned to (CJW)9/22/20169/22/201610/5/2016 PASS
DetailsCarl Westfall
Routing - PLAN CHECK9/23/2016 10/5/2016 PASS
DetailsCarl Westfall
CHANGE STATUS TO (ISS)  10/5/2016 DONE
PLANS/APPL TAKEN TO FRONT DESK  10/5/2016 DONE
Permit Ready to Issue  10/5/2016 DONE
plan mod fees waived as per letter from city council attached
Routing - FIRE9/23/20169/23/20169/26/2016 PASS
DetailsKatie Marron
Revised report attached to case.
Routing - PUBLIC WORKS9/23/2016 9/26/2016 PASS
DetailsRachael Beierle
Banquet room credits remain with the space.No kitchen equipment was charged. only sqft of ballroom. 0.00 sewer permit will be issued on ne BLD.
BLD-Final9/21/20169/21/20169/22/2016PPART
DetailsDave Hannah
Request to walk GBAD building for temp occ. Contact Adam on site. Jim has also been scheduled for PM today. All MEP''s have been acknowledged and signed off in the on site binder. Contact Adam when on site. Thanks. AKJ. Phone #: ###-#### Inspection requested via web by Adam Johnson ok for temp occ
Plan Modification Accepted  9/22/2016 DONE
Remove kitchen from scope of work
FIRE-Final Inspection9/20/20169/21/20169/21/2016PPART
DetailsJim Page
Partial life fire safety inspection complete. Fire sprinkler inspection complete for level 5 wet system, level 4 wet system, level 3 dry system, level 2 wet system, level 2 dry system and level 1 elevator lobby, fire sprinklers systems noted will be active before TCO. Fire alarm inspection complete for same area's as fire sprinklers, noted as well that fire alarms for these area's will be active before TCO. Fire extinguishers are in place with current inspection tags on level 5, level 4 and level 1 elevator lobby. Life fire safety inspection complete for level 5, level 4, level 3 parking and level 2 parking. Remaining levels 1 and 2 of convention center will be inspected at a later date.
Telephone call  9/7/2016 DONE
received email from ACHD-need inspection before perm c of o can be issued
Temporary Occupancy9/6/201612/5/20169/6/2016 DONE
DetailsCandy A. Nichols
for any questions please contact Angie B. Temp C of O for Clearwater side of the firewall. See conditions
CHANGE STATUS TO (ISS)  9/6/2016 DONE
only changed to temp c of o for the Clearwater side of firewall Temp C of O
BLD-Final9/1/20169/2/20169/2/2016APEND
DetailsDave Hannah
Nathan// 4th floor Phone #: ###-####
BLD-Conference9/1/20169/2/20169/2/2016APART
DetailsDave Hannah
Final inspection request for the District TI, 4th floor Clearwater only. Call Adam when onsite. Thanks. AKJ. Phone #: ###-#### Inspection requested via web by Adam Johnson ok for temp occ
FIRE-Final Inspection9/1/20169/1/20169/1/2016PPART
DetailsJim Page
Fire sprinkler inspection complete for city center level 4, fire alarm inspection for city center level 4 complete, fire extinguishers for level 4 city center are in place and will get current inspection tags installed from a licensed contractor. Partial final life fire safety inspection for level 4 complete (city center side of building is complete). Level 4 convention center side will need fire sprinkler, fire alarm and life fire safety inspections performed at a later date.
BLD-Ceiling Grid Inspection8/25/20168/25/20168/29/2016PPASS
DetailsDave Hannah
Additional ceiling grid inspections at 4th floor CW, West side, and East side corridors, potential west side meeting rooms. Please call when heading to site. Thanks. akj Phone #: ###-#### Inspection requested via web by Adam Johnson
BLD-Ceiling Grid Inspection8/24/20168/25/20168/25/2016APART
DetailsDave Hannah
Adam// 4th floor Clearwater bldg Phone #: ###-#### ok
BLD-Conference8/23/20168/23/20168/24/2016PPASS
DetailsDave Hannah
Adam Phone #: ###-####
Issue PAID IN FULL permit  1/8/2016 DONE
Extend Review Timeline  1/7/2016 DONE
1st 180 days granted by Jason B. See attachment in documents
Telephone call  1/4/2016 DONE
Left a message for Joe informing him that this permit will expire on the 13th and if he would like an extension he'll need to email Jason B
Expiration Notice12/18/20151/12/201612/18/2015 DONE
DetailsBrittany Hill
Plan Reviewer's activity  11/20/2015 DONE
Routing completed
PLANS/APPL TAKEN TO FRONT DESK  11/20/2015 DONE
Permit Ready to Issue  11/20/2015 DONE
Needs; GC Form, Revised Cert of Value
**GC IN DOCUMENTS**--- per Alex DeYoung no documents needed and no fees are to be collected at this time/// KRS
Plan assigned to (CJW)7/23/2015 11/20/2015 PASS
DetailsCarl Westfall
(1st done) DISTRICT CONVENTION CENTER OF GBAD (Aug 12 - 15 days / 30 days - Sept 2) Level 3 TI
Routing - PLUMBING11/17/2015 11/19/2015 PASS
DetailsDaryl Spivey
3 single user toilet rooms added
Routing - FIRE11/16/2015 11/17/2015 PASS
DetailsScott Arellano
Attached updated Fire Review comments to plans. Electronic Case needs to be reassigned and then signed off in eplan by Fire.
Routing - PLAN CHECK11/13/2015 11/17/2015 PASS
DetailsCarl Westfall
Drawings approved with redlines
Routing PW Sewer Rating11/17/2015 11/17/2015 PASS
DetailsJennifer Bruner
3 single user restrooms added; no additional fees - rated by banquet area
Plan resubmittals received  11/13/2015 DONE
Routing - PLAN CHECK7/23/2015 9/29/2015 FAIL
DetailsCarl Westfall
Revised drawings required
1st review completed  9/29/2015 DONE
Plan resubmittals requested  9/29/2015 DONE
Meeting  9/24/2015 DONE
Meeting with Romeo Gervais, Jason Blais, Jenifer Gilliland, Ron Hill, Angie Brosious, and Derick O'Neill to discuss main exit provisions, etc. of the IBC.
Routing Off Site - C.D.H7/23/2015 8/28/2015 PASS
DetailsCarl Westfall
Joe Antonucci
Routing PW Environmental7/23/2015 8/13/2015 PASS
DetailsRick Christenson
Routing - MECHANICAL7/23/2015 7/30/2015 PASS
DetailsTroy James
Routing - FIRE7/23/20157/23/20157/28/2015 FAIL
DetailsScott Arellano
Emailed plan review report to architect. Attached comments to case.
Routing - PLUMBING7/23/2015 7/28/2015 PASS
DetailsDaryl Spivey
Red line markup on waste and vent for kitchen. Several fixtures not vented per ISPC.
Routing PW Sewer Rating7/23/2015 7/24/2015 PASS
DetailsJennifer Bruner
Routing - Addressing7/23/2015 7/23/2015 PASS
DetailsEmily Dixon
Suite number 400 added.
Routing - PUBLIC WORKS7/23/2015 7/23/2015 PASS
DetailsJennifer Bruner
Routing - Design Review7/23/2015 7/23/2015 PASS
DetailsSarah Schafer
Approved.
Intake Approval  7/23/2015 PASS
Pending Assignment by TLW7/23/2015 7/23/2015 DONE
DetailsTim L. Woodard
Application received  7/17/2015 DONE
Application submitted via PDS Online on Jul 17 2015 10:35AM