Third Notice | | 1/15/2017 | 2/13/2017 | | DONE |
Christina Prado
|
|
|
emailed to ESI rep
|
Print Occupancy Form | | | 2/9/2017 | | DONE |
|
|
|
|
Second Notice | | 12/22/2016 | 1/10/2017 | | DONE |
|
|
|
Mailed 1-11
|
First Notice | | 12/12/2016 | 12/12/2016 | | DONE |
|
|
|
Mailed 12-13-16
|
Permanent Occupancy | | | 12/2/2016 | | DONE |
|
|
|
|
BLD-Final | 11/16/2016 | 11/16/2016 | 11/16/2016 | P | PASS |
Dave Hannah
|
|
|
Ok for permanent occupancy once bond is posted.
|
FIRE-Alarm Testing | 11/10/2016 | 11/10/2016 | 11/10/2016 | P | DONE |
Troy Cobbley
|
|
|
Fire Alarm Test of Horn strobes down Block 22 performed by Lee.
|
BLD-Final | 11/10/2016 | 11/10/2016 | 11/10/2016 | P | PART |
Dave Hannah
|
|
|
BuildingFinal for Commercial Kitchen. In follow up to pre walk this week. On the books just to be safe. Call Adam with any questions. thanks akj. Phone #: ###-#### Inspection requested via web by Adam Johnson ok for perm occ after shell and core is finaled ok to occ/use
|
FIRE-Final Inspection | 11/10/2016 | 11/10/2016 | 11/10/2016 | P | PASS |
Troy Cobbley
|
|
|
Fire Life Safety inspection passed. Fire Alarm inspection performed and documented under FIR16-00128.
|
FIRE-Final Inspection | 11/9/2016 | 11/9/2016 | 11/9/2016 | P | PART |
Troy Cobbley
|
|
|
Final life safety field inspection completed for Commercial Kitchen area only of GBAD tenant. Pending approval of structural field inspector; OK for occupancy.
|
OVERRIDE | | | 10/5/2016 | | |
|
|
|
|
Plan assigned to (CJW) | 9/22/2016 | 9/22/2016 | 10/5/2016 | | PASS |
Carl Westfall
|
|
|
|
Routing - PLAN CHECK | 9/23/2016 | | 10/5/2016 | | PASS |
Carl Westfall
|
|
|
|
CHANGE STATUS TO (ISS) | | | 10/5/2016 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/5/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/5/2016 | | DONE |
|
|
|
plan mod fees waived as per letter from city council attached
|
Routing - FIRE | 9/23/2016 | 9/23/2016 | 9/26/2016 | | PASS |
Katie Marron
|
|
|
Revised report attached to case.
|
Routing - PUBLIC WORKS | 9/23/2016 | | 9/26/2016 | | PASS |
Rachael Beierle
|
|
|
Banquet room credits remain with the space.No kitchen equipment was charged. only sqft of ballroom. 0.00 sewer permit will be issued on ne BLD.
|
BLD-Final | 9/21/2016 | 9/21/2016 | 9/22/2016 | P | PART |
Dave Hannah
|
|
|
Request to walk GBAD building for temp occ. Contact Adam on site. Jim has also been scheduled for PM today. All MEP''s have been acknowledged and signed off in the on site binder. Contact Adam when on site. Thanks. AKJ. Phone #: ###-#### Inspection requested via web by Adam Johnson ok for temp occ
|
Plan Modification Accepted | | | 9/22/2016 | | DONE |
|
|
|
Remove kitchen from scope of work
|
FIRE-Final Inspection | 9/20/2016 | 9/21/2016 | 9/21/2016 | P | PART |
Jim Page
|
|
|
Partial life fire safety inspection complete. Fire sprinkler inspection complete for level 5 wet system, level 4 wet system, level 3 dry system, level 2 wet system, level 2 dry system and level 1 elevator lobby, fire sprinklers systems noted will be active before TCO. Fire alarm inspection complete for same area's as fire sprinklers, noted as well that fire alarms for these area's will be active before TCO. Fire extinguishers are in place with current inspection tags on level 5, level 4 and level 1 elevator lobby. Life fire safety inspection complete for level 5, level 4, level 3 parking and level 2 parking. Remaining levels 1 and 2 of convention center will be inspected at a later date.
|
Telephone call | | | 9/7/2016 | | DONE |
|
|
|
received email from ACHD-need inspection before perm c of o can be issued
|
Temporary Occupancy | 9/6/2016 | 12/5/2016 | 9/6/2016 | | DONE |
Candy A. Nichols
|
|
|
for any questions please contact Angie B. Temp C of O for Clearwater side of the firewall. See conditions
|
CHANGE STATUS TO (ISS) | | | 9/6/2016 | | DONE |
|
|
|
only changed to temp c of o for the Clearwater side of firewall Temp C of O
|
BLD-Final | 9/1/2016 | 9/2/2016 | 9/2/2016 | A | PEND |
Dave Hannah
|
|
|
Nathan// 4th floor Phone #: ###-####
|
BLD-Conference | 9/1/2016 | 9/2/2016 | 9/2/2016 | A | PART |
Dave Hannah
|
|
|
Final inspection request for the District TI, 4th floor Clearwater only. Call Adam when onsite. Thanks. AKJ. Phone #: ###-#### Inspection requested via web by Adam Johnson ok for temp occ
|
FIRE-Final Inspection | 9/1/2016 | 9/1/2016 | 9/1/2016 | P | PART |
Jim Page
|
|
|
Fire sprinkler inspection complete for city center level 4, fire alarm inspection for city center level 4 complete, fire extinguishers for level 4 city center are in place and will get current inspection tags installed from a licensed contractor. Partial final life fire safety inspection for level 4 complete (city center side of building is complete). Level 4 convention center side will need fire sprinkler, fire alarm and life fire safety inspections performed at a later date.
|
BLD-Ceiling Grid Inspection | 8/25/2016 | 8/25/2016 | 8/29/2016 | P | PASS |
Dave Hannah
|
|
|
Additional ceiling grid inspections at 4th floor CW, West side, and East side corridors, potential west side meeting rooms. Please call when heading to site. Thanks. akj Phone #: ###-#### Inspection requested via web by Adam Johnson
|
BLD-Ceiling Grid Inspection | 8/24/2016 | 8/25/2016 | 8/25/2016 | A | PART |
Dave Hannah
|
|
|
Adam// 4th floor Clearwater bldg Phone #: ###-#### ok
|
BLD-Conference | 8/23/2016 | 8/23/2016 | 8/24/2016 | P | PASS |
Dave Hannah
|
|
|
Adam Phone #: ###-####
|
Issue PAID IN FULL permit | | | 1/8/2016 | | DONE |
|
|
|
|
Extend Review Timeline | | | 1/7/2016 | | DONE |
|
|
|
1st 180 days granted by Jason B. See attachment in documents
|
Telephone call | | | 1/4/2016 | | DONE |
|
|
|
Left a message for Joe informing him that this permit will expire on the 13th and if he would like an extension he'll need to email Jason B
|
Expiration Notice | 12/18/2015 | 1/12/2016 | 12/18/2015 | | DONE |
Brittany Hill
|
|
|
|
Plan Reviewer's activity | | | 11/20/2015 | | DONE |
|
|
|
Routing completed
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/20/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/20/2015 | | DONE |
|
|
|
Needs; GC Form, Revised Cert of Value
**GC IN DOCUMENTS**--- per Alex DeYoung no documents needed and no fees are to be collected at this time/// KRS
|
Plan assigned to (CJW) | 7/23/2015 | | 11/20/2015 | | PASS |
Carl Westfall
|
|
|
(1st done) DISTRICT CONVENTION CENTER OF GBAD (Aug 12 - 15 days / 30 days - Sept 2) Level 3 TI
|
Routing - PLUMBING | 11/17/2015 | | 11/19/2015 | | PASS |
Daryl Spivey
|
|
|
3 single user toilet rooms added
|
Routing - FIRE | 11/16/2015 | | 11/17/2015 | | PASS |
Scott Arellano
|
|
|
Attached updated Fire Review comments to plans. Electronic Case needs to be reassigned and then signed off in eplan by Fire.
|
Routing - PLAN CHECK | 11/13/2015 | | 11/17/2015 | | PASS |
Carl Westfall
|
|
|
Drawings approved with redlines
|
Routing PW Sewer Rating | 11/17/2015 | | 11/17/2015 | | PASS |
Jennifer Bruner
|
|
|
3 single user restrooms added; no additional fees - rated by banquet area
|
Plan resubmittals received | | | 11/13/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/23/2015 | | 9/29/2015 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
1st review completed | | | 9/29/2015 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 9/29/2015 | | DONE |
|
|
|
|
Meeting | | | 9/24/2015 | | DONE |
|
|
|
Meeting with Romeo Gervais, Jason Blais, Jenifer Gilliland, Ron Hill, Angie Brosious, and Derick O'Neill to discuss main exit provisions, etc. of the IBC.
|
Routing Off Site - C.D.H | 7/23/2015 | | 8/28/2015 | | PASS |
Carl Westfall
|
|
|
Joe Antonucci
|
Routing PW Environmental | 7/23/2015 | | 8/13/2015 | | PASS |
Rick Christenson
|
|
|
|
Routing - MECHANICAL | 7/23/2015 | | 7/30/2015 | | PASS |
Troy James
|
|
|
|
Routing - FIRE | 7/23/2015 | 7/23/2015 | 7/28/2015 | | FAIL |
Scott Arellano
|
|
|
Emailed plan review report to architect. Attached comments to case.
|
Routing - PLUMBING | 7/23/2015 | | 7/28/2015 | | PASS |
Daryl Spivey
|
|
|
Red line markup on waste and vent for kitchen. Several fixtures not vented per ISPC.
|
Routing PW Sewer Rating | 7/23/2015 | | 7/24/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 7/23/2015 | | 7/23/2015 | | PASS |
Emily Dixon
|
|
|
Suite number 400 added.
|
Routing - PUBLIC WORKS | 7/23/2015 | | 7/23/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Design Review | 7/23/2015 | | 7/23/2015 | | PASS |
Sarah Schafer
|
|
|
Approved.
|
Intake Approval | | | 7/23/2015 | | PASS |
|
|
|
|
Pending Assignment by TLW | 7/23/2015 | | 7/23/2015 | | DONE |
Tim L. Woodard
|
|
|
|
Application received | | | 7/17/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 17 2015 10:35AM
|