Print Statement | | | 6/24/2016 | | DONE |
|
|
|
|
Second Notice | | 5/21/2016 | 6/15/2016 | | DONE |
|
|
|
|
Elevation Cert Rec'd-Final | | | 5/16/2016 | | DONE |
|
|
|
|
First Notice | | 5/9/2016 | 5/11/2016 | | DONE |
|
|
|
Mailed 5-12-16
|
BLD-Final | 4/29/2016 | 4/29/2016 | 4/29/2016 | P | PASS |
Dave Hannah
|
|
|
Bob Phone #: ###-####
|
FIRE-Final Inspection | 4/28/2016 | 4/29/2016 | 4/29/2016 | A | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguishers are in place with current inspections, exit signs/egress lighting/discharge landing lighting verfied, all operated correctly. Final life fire safety inspection passed/complete.
|
Permanent Occupancy | | | 4/29/2016 | | DONE |
|
|
|
|
FIRE-Final Inspection | 4/28/2016 | 4/28/2016 | 4/28/2016 | P | FAIL |
Jim Page
|
|
|
None of the exit signs/emergency lighting/discharge landing illumination located in the west section storage unit corridors could be verified for proper operation, there was tripped circuit breaker on lighting circuit and emergency power source was depleted, all exit lighting/emergency egress needs to be operable at time of final inspection. Discharge landing illumination needs to be tested/verified for proper operation , interior emergency lighting on these fixtures were operable when AC power source was isolated, multiple lights on discharge landings did not illuminate, inoperable discharge landing lights need to be repaired and operating at time of final inspection.
|
Override - Condition Holds | 4/28/2016 | 1/1/1900 | 4/28/2016 | | |
|
|
|
fire final ONLY
|
Override - Condition Holds | 4/26/2016 | 1/1/1900 | 4/26/2016 | | |
|
|
|
life safety
|
Zoning Approval | 4/25/2016 | 4/25/2016 | 4/25/2016 | | PASS |
Josh Wilson
|
|
|
|
FIRE-Final Inspection | 4/21/2016 | 4/21/2016 | 4/21/2016 | P | FAIL |
Troy Cobbley
|
|
|
No small documents on site so Bob and I did a quick walk through. I noted missing sticker and indicator at the office exit. Opticons at the two gates will need to be tested by the fire dept prior to a sign off.
|
BLD-Other | 3/3/2016 | 3/4/2016 | 3/4/2016 | A | PASS |
Dave Hannah
|
|
|
Bob-firewall Phone #: ###-#### int side of 2hr fire walls ok
|
BLD-Other | 3/1/2016 | 3/2/2016 | 3/2/2016 | A | PASS |
Dave Hannah
|
|
|
Fire wall // Bob Phone #: ###-####
|
BLD-Energy code compliance | 3/1/2016 | 3/1/2016 | 3/2/2016 | P | PASS |
Dave Hannah
|
|
|
Bob-Fire wall Phone #: ###-####
|
BLD-Energy code compliance | 2/29/2016 | 2/29/2016 | 2/29/2016 | P | PART |
Dave Hannah
|
|
|
Bob Phone #: ###-#### walls and 2/3rds on the ceiling
|
BLD-Framing/Rough-in | 2/23/2016 | 2/23/2016 | 2/24/2016 | P | PART |
Dave Hannah
|
|
|
Bob Phone #: ###-#### draft stops ok back firewall in attic ok
|
BLD-Framing/Rough-in | 2/18/2016 | 2/18/2016 | 2/18/2016 | P | PART |
Mike Jordan
|
|
|
Bob Phone #: ###-####. roof trusses and draft stops. Needs to seal around penetrations in draft stops.
|
BLD-Other | 2/5/2016 | 2/8/2016 | 2/8/2016 | A | PASS |
Dave Hannah
|
|
|
firewall; Bob Phone #: ###-#### ok to cover ext prop line wall
|
BLD-Other | 2/5/2016 | 2/5/2016 | 2/6/2016 | P | PASS |
Dave Hannah
|
|
|
Bob-sheet rock wall Phone #: ###-####ext fire wall along prop line ok to keep going
|
BLD-Wall Bracing | 2/1/2016 | 2/2/2016 | 2/2/2016 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### west and south walls ok to cover
|
BLD-Framing/Rough-in | 1/26/2016 | 1/26/2016 | 1/26/2016 | P | CANC |
Phil Shearer
|
|
|
Bob// Shear Wall Phone #: ###-####
|
BLD-Wall Bracing | 1/26/2016 | 1/26/2016 | 1/26/2016 | P | PART |
Phil Shearer
|
|
|
Bob// Shear Wall Phone #: ###-####. Grid line 8,9,10 OK to cover
|
BLD-Wall Bracing | 1/25/2016 | 1/26/2016 | 1/26/2016 | A | PART |
Phil Shearer
|
|
|
Bob Phone #: ###-####. Wall on grid line 6, C, J are OK for cover
|
BLD-Other | 1/19/2016 | 1/19/2016 | 1/19/2016 | P | PASS |
Dave Hannah
|
|
|
Roof nailing - Bob Phone #: ###-#### outter buildings ok to cover roofs
|
BLD-Footing | 10/21/2015 | 10/21/2015 | 10/22/2015 | P | PASS |
Dave Hannah
|
|
|
Bob Phone #: ###-####
|
BLD-Foundation | 10/16/2015 | 10/19/2015 | 10/20/2015 | A | PASS |
Dave Hannah
|
|
|
stem wall; Bob Phone #: ###-####
|
BLD-Footing | 10/13/2015 | 10/14/2015 | 10/14/2015 | A | NR |
Dave Hannah
|
|
|
Bob Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/28/2015 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/28/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 9/21/2015 | | |
|
|
|
|
Routing PW Flood Plain | 9/18/2015 | | 9/21/2015 | | PASS |
Jim Wyllie
|
|
|
Approved in E-Plan Review. TLW
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/21/2015 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/21/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/21/2015 | | DONE |
Christina Prado
|
|
|
Need a ACHD for issuance
|
Plan assigned to (TLW) | 8/3/2015 | | 9/21/2015 | | PASS |
Tim L. Woodard
|
|
|
First review completed.
|
Routing Off Site - STRUCTURAL | 9/3/2015 | | 9/18/2015 | | PASS |
Tim L. Woodard
|
|
|
|
Routing PW Flood Plain | 9/3/2015 | | 9/18/2015 | | FAIL |
Jim Wyllie
|
|
|
|
Elevation Cert Rec'd-Prelim | | | 9/18/2015 | | FAIL |
|
|
|
Provide Elevation Certificates for all buildings in the floodplain. Jim Wyllie / ###-####
|
Plan resubmittals received | | | 9/18/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/18/2015 | | 9/18/2015 | | PASS |
Tim L. Woodard
|
|
|
|
Routing PW Drainage | 9/17/2015 | | 9/17/2015 | | PASS |
Jason C. Taylor
|
|
|
|
Routing - PLAN CHECK | 9/3/2015 | | 9/16/2015 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLANNING Land Div | 9/3/2015 | | 9/10/2015 | | PASS |
Dave Abo
|
|
|
Parcel "A"of ROS 10210
|
Routing - PLANNING | 9/3/2015 | | 9/9/2015 | | PASS |
Cody Riddle
|
|
|
|
Routing PW Drainage | 9/3/2015 | | 9/9/2015 | | FAIL |
Jason C. Taylor
|
|
|
See changemarks in ePlan
|
Routing - FIRE | 9/3/2015 | 9/3/2015 | 9/4/2015 | | PASS |
Katie Marron
|
|
|
Comments attached to case.
|
Routing PW Street Lights | 9/3/2015 | | 9/4/2015 | | PASS |
Mike D Hedge
|
|
|
|
Plan resubmittals received | | | 9/3/2015 | | DONE |
|
|
|
|
Route to Impact Fee Review | 8/28/2015 | 8/31/2015 | 9/1/2015 | | PASS |
Cindy M. Gould
|
|
|
|
Routing PW Flood Plain | 8/3/2015 | | 8/28/2015 | | FAIL |
Jim Wyllie
|
|
|
|
1st review completed | | | 8/28/2015 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 8/3/2015 | | 8/28/2015 | | FAIL |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 8/3/2015 | | 8/28/2015 | | FAIL |
Tim L. Woodard
|
|
|
|
Routing PW Solid Waste | 8/3/2015 | | 8/12/2015 | | PASS |
Megan Durrell
|
|
|
Trash enclosure corrections complete.
|
Routing PW Drainage | 8/3/2015 | | 8/7/2015 | | FAIL |
Jason C. Taylor
|
|
|
See Changemark in ePlan for details. JCT
|
Routing PW Sewer Design | 8/3/2015 | | 8/6/2015 | | PASS |
Kyle S. Rosenmeyer
|
|
|
Show existing permanent sewer easement in drawing. Easement is 20' wide, offset 3.5' to the north of the center of pipe.
|
Routing - Design Review | 8/3/2015 | | 8/6/2015 | | PASS |
Josh Wilson
|
|
|
|
Routing - FIRE | 8/3/2015 | 8/3/2015 | 8/5/2015 | | FAIL |
Katie Marron
|
|
|
Comments attached to case and emailed to architect.
|
Routing PW Geothermal | 8/3/2015 | | 8/5/2015 | | PASS |
Jon R. Gunnerson
|
|
|
No connection onto geothermal. Maintain adequate separation and pipeline integrity.
|
Routing - PLUMBING | 8/3/2015 | | 8/5/2015 | | PASS |
Daryl Spivey
|
|
|
1) asse 1070 mixing valve required at public lavs
2) increase 2" section of venting to 3" for cross sectional area requirement.
|
Routing - PLANNING | 8/3/2015 | | 8/4/2015 | | FAIL |
Cody Riddle
|
|
|
CUP15-00006 required a floodplain development permit prior to building permit issuance.
|
Routing - PUBLIC WORKS | 8/3/2015 | | 8/4/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Sewer Rating | 8/3/2015 | | 8/4/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing PW Street Lights | 8/3/2015 | | 8/4/2015 | | FAIL |
Mike D Hedge
|
|
|
Need to submit updated E1.0 as per discussion with Keith Adams at e2co on July 21 st.
|
Routing - Erosion and Sediment | 8/3/2015 | | 8/3/2015 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)
Urban self-storage facility consisting of climate-controlled and ambient storage, associated office and circulation areas in three buildings. (RIVER STREET STORAGE - Building "B")
|
Routing - PLANNING Land Div | 8/3/2015 | | 8/3/2015 | | FAIL |
Dave Abo
|
|
|
Property is involved with a current Record of Survey (ROS-00076). Prior to issuance of building permit, must complete Record of Survey process.
|
Routing - Addressing | 8/3/2015 | | 8/3/2015 | | PASS |
Emily Dixon
|
|
|
Buildings will all be addressed 1201 W River St.
|
Pending Assignment by TLW | 8/3/2015 | | 8/3/2015 | | DONE |
Tim L. Woodard
|
|
|
|
Intake Approval | | | 7/31/2015 | | PASS |
Tim L. Woodard
|
|
|
|
Intake Approval | | | 7/27/2015 | | FAIL |
Tim L. Woodard
|
|
|
Allison,
Please upload an additional two permits for buildings C and D on this site. Each building is required a different application so we can issue separate C of O permits and assign separate addresses.
Best regards,
Tim Woodard
twoodard@cityofboise.org
|
Application received | | | 7/21/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 21 2015 11:32AM
|