BLD-Wall cover | 8/21/2015 | 8/24/2015 | 8/24/2015 | A | PASS |
Phil Shearer
|
|
|
Dennis Phone #: ###-####
|
BLD-Energy code compliance | 8/24/2015 | 8/24/2015 | 8/24/2015 | P | PASS |
Phil Shearer
|
|
|
Dennis Phone #: ###-####
|
BLD-Framing/Rough-in | 8/19/2015 | 8/20/2015 | 8/20/2015 | A | PASS |
Phil Shearer
|
|
|
Dennis Phone #: ###-####
|
BLD-Framing/Rough-in | 8/6/2015 | 8/7/2015 | 8/7/2015 | P | CANC |
Phil Shearer
|
|
|
Dennis Phone #: ###-####
|
BLD-Wall Bracing | 8/7/2015 | 8/7/2015 | 8/7/2015 | P | PASS |
Phil Shearer
|
|
|
Dennis Phone #: ###-####
|
Routing Walk-In (BLD) | 7/22/2015 | 7/22/2015 | 7/22/2015 | A | PASS |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 7/22/2015 | | DONE |
Javier Guzman
|
|
|
|
Inspection Record Card- Bld | | | 7/22/2015 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/22/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 7/22/2015 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/22/2015 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 7/22/2015 | | DONE |
Javier Guzman
|
|
|
I added into documents the revised engineering for the floor joist
|
Routing Walk-In (Zoning) | 7/21/2015 | 7/21/2015 | 7/21/2015 | P | DONE |
Leon Letson
|
|
|
|
Routing Walk-In (BLD) | 7/21/2015 | 7/21/2015 | 7/21/2015 | P | FAIL |
Javier Guzman
|
|
|
need revised engineering, engineered calculations did not match the submitted floor plan
|
1st review completed | | | 7/21/2015 | | FAIL |
Javier Guzman
|
|
|
|
Application received | | 7/21/2015 | | | |
|
|
|
|