Permanent Occupancy | | | 9/30/2016 | | DONE |
|
|
|
|
Meeting | | | 9/30/2016 | | DONE |
|
|
|
emailed Dave Scaggs the perm C of O
|
BLD-Final | 9/16/2016 | 9/19/2016 | 9/19/2016 | A | PASS |
Mike Jordan
|
|
|
Dave Phone #: ###-####
|
Zoning Approval | 9/9/2016 | 9/9/2016 | 9/9/2016 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Aging Inspection | 7/20/2016 | 7/20/2016 | 7/20/2016 | | PASS |
Mike Jordan
|
|
|
|
Temporary Occupancy | 6/14/2016 | 9/12/2016 | 6/14/2016 | | DONE |
Candy A. Nichols
|
|
|
as pr Jason B-extension granted from 6-9-16 good for 90 days
|
Telephone call | | | 6/9/2016 | | DONE |
|
|
|
called and emailed Dave to let know temp expires today-he will email Jason B
|
BLD-Aging Inspection | 5/20/2016 | 5/20/2016 | 5/20/2016 | | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 3/11/2016 | 3/11/2016 | 3/11/2016 | P | PASS |
Mike Jordan
|
|
|
Kelly Phone #: ###-####. Ok for temp. occ. Will be ok for perm occ. once zoning signs perm,.
|
Temporary Occupancy | 3/11/2016 | 6/9/2016 | 3/11/2016 | | DONE |
Carlos Velazquez
|
|
|
|
Zoning Approval Temp | 3/11/2016 | 3/11/2016 | 3/11/2016 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Final | 3/10/2016 | 3/10/2016 | 3/10/2016 | P | NR |
Mike Jordan
|
|
|
Kelly Phone #: ###-####. Rescheduled for tomorrow in the pm. Needs zoning final (will be tomorrow at 10:30am)
|
FIRE-Final Inspection | 3/9/2016 | 3/9/2016 | 3/9/2016 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 2/22/2016 | 2/23/2016 | 2/23/2016 | A | NR |
Mike Jordan
|
|
|
Kelly Phone #: ###-####
|
BLD-Energy code compliance | 1/22/2016 | 1/22/2016 | 1/22/2016 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 1/21/2016 | 1/22/2016 | 1/22/2016 | A | PASS |
Mike Jordan
|
|
|
Kelly Phone #: ###-####
|
BLD-Framing/Rough-in | 1/19/2016 | 1/19/2016 | 1/19/2016 | P | FAIL |
Mike Jordan
|
|
|
Kelly Phone #: ###-####. Patch hole sin draft stop, Firecaulk missed penetrations in draft stop. Fire caulk top of wall in upstairs mech. rooms. OK to insulate. Correction notice posted.
|
BLD-Framing/Rough-in | 1/11/2016 | 1/12/2016 | 1/12/2016 | A | NR |
Mike Jordan
|
|
|
Kelly Phone #: ###-####. Needs fire sprinkler rough in inspection.
|
BLD-Wall Bracing | 12/2/2015 | 12/3/2015 | 12/3/2015 | A | PASS |
Mike Jordan
|
|
|
Kelly Phone #: ###-####
|
BLD-Wall Bracing | 11/10/2015 | 11/10/2015 | 11/10/2015 | P | PASS |
Mike Jordan
|
|
|
Shear // Kelly Phone #: ###-####
|
BLD-Foundation | 10/27/2015 | 10/28/2015 | 10/28/2015 | A | PASS |
Mike Jordan
|
|
|
Dave Phone #: ###-####. Interior thickend footings under slab on grade.
|
BLD-Energy code compliance | 10/19/2015 | 10/19/2015 | 10/19/2015 | P | PASS |
Mike Jordan
|
|
|
Rob Phone #: ###-####
|
BLD-Footing | 10/15/2015 | 10/16/2015 | 10/16/2015 | A | PASS |
Mike Jordan
|
|
|
Dave Phone #: ###-####
|
(F) Reprint permit | | | 10/16/2015 | | DONE |
|
|
|
|
BLD-Footing | 10/15/2015 | 10/15/2015 | 10/15/2015 | P | PASS |
Mike Jordan
|
|
|
Interior thickend footings.
|
BLD-Energy code compliance | 10/15/2015 | 10/15/2015 | 10/15/2015 | P | CANC |
Mike Jordan
|
|
|
Rob Phone #: ###-####
|
BLD-Foundation | 10/13/2015 | 10/14/2015 | 10/14/2015 | A | PASS |
Mike Jordan
|
|
|
Manuel Phone #: ###-####
|
BLD-Footing | 10/12/2015 | 10/13/2015 | 10/13/2015 | A | PASS |
Mike Jordan
|
|
|
Manuel Phone #: ###-####
|
Plan Reviewer's activity | | | 10/8/2015 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
revisons to footing calculations and 310 form. **10/8/15 ajs**
|
Issue PAID IN FULL permit | | | 9/21/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 9/17/2015 | | |
|
|
|
|
Telephone call | | | 9/17/2015 | | DONE |
|
|
|
called customer and notified him that permit is ready and forms needed
|
Print Occupancy Form | | | 9/17/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/17/2015 | | DONE |
|
|
|
Needs; GC Form, Rev Cert of Value, Responsible Person
|
Plan assigned to (AJS) | 8/10/2015 | 8/10/2015 | 9/16/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
New 4 Plex
|
Pending Assignment by TLW | | | 9/16/2015 | | PASS |
Tim L. Woodard
|
|
|
|
Routing - PLAN CHECK | 9/14/2015 | | 9/16/2015 | | PASS |
Adele J Schaffeld-Griffin
|
|
|
|
Routing - Design Review | 9/16/2015 | | 9/16/2015 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLANNING | 9/16/2015 | | 9/16/2015 | | PASS |
Andrea Tuning
|
|
|
|
1st review completed | | | 9/16/2015 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
Case Summary (BLD) | | | 9/16/2015 | | DONE |
Adele J Schaffeld-Griffin
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/16/2015 | | DONE |
|
|
|
|
Routing - FIRE | 9/14/2015 | 9/14/2015 | 9/14/2015 | | PASS |
Katie Marron
|
|
|
Attached comments to plans.
|
Plan resubmittals received | | | 9/14/2015 | | DONE |
|
|
|
received (2) copies of Horizontal Control Plan (C2)
|
Routing PW Solid Waste | 9/8/2015 | | 9/9/2015 | | PASS |
Megan Durrell
|
|
|
HOA required to sign service agreement for private roads.
Townhouses required to bring carts to Jewell or pay carry-out rates.
|
Routing - PUBLIC WORKS | 9/8/2015 | | 9/9/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - Addressing | 9/2/2015 | | 9/8/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing PW Sewer Rating | 9/8/2015 | | 9/8/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Routing - PLANNING Land Div | 9/2/2015 | | 9/2/2015 | | PASS |
Dave Abo
|
|
|
|
Routing - FIRE | | | 8/28/2015 | | FAIL |
Scott Arellano
|
|
|
Comments attached to plans
|
Routing - MECHANICAL | 8/17/2015 | | 8/25/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | | | 8/25/2015 | | PASS |
Daryl Spivey
|
|
|
|
Plan resubmittals received | | | 8/25/2015 | | DONE |
Christina Prado
|
|
|
Received two sets of revised plan sheet marked S0.1 as well as two sets response letter; Plan inserted by arch rep and taken to AJS for additional review
|
Routing - Erosion and Sediment | 8/14/2015 | | 8/17/2015 | | PASS |
Evan Jenkins
|
|
|
(Site Prep Inspection and Approval Required Prior to Earth Disturbance)
(CORDILLERA SUBDIVISION BLDG #7)
|
Routing - PUBLIC WORKS | 8/10/2015 | | 8/14/2015 | | FAIL |
Jennifer Bruner
|
|
|
See PW Solid Waste, and PW Sewer Rating.
|
Routing - PLANNING | 8/14/2015 | | 8/14/2015 | | FAIL |
Susan Riggs
|
|
|
The final plat has not been recorded, can't sign off plans until recorded SUB15-00014.
|
Routing - Design Review | | | 8/14/2015 | | FAIL |
Andrea Tuning
|
|
|
The applicant is requried to provide 9 covered bicycle parking spaces.
The planter island adjacent to the south property line is not a minimum of 8-feet in width (measured inside of curb to inside of curb). It also contains a Class I tree. This tree is required to be a Class II tree.
The three trees adjacent to the parking for the boccee court should be replaced with Class II trees.
Provide an effective landscape barrier to the north and south that is comprised of, but not limited to, a mix of evergreen and deciduous trees, shrubs, lawn, or other vegetative groundcover. This landscaping will be required to close 60 percent or more of the vertical surface area and prevent the passage of vision through the buffer within 5 years of planting the buffer.
The four trees adjacent to Five Mile Road shall be replaced with Class II or Class III trees.
|
Routing PW Sewer Rating | 8/13/2015 | | 8/14/2015 | | FAIL |
Beverly Mountain
|
|
|
correct address needed.
|
Routing PW Solid Waste | 8/13/2015 | | 8/13/2015 | | FAIL |
Megan Durrell
|
|
|
Need to discuss access issues, private lanes, carports, and adequate service for the number of units.
|
Routing PW Drainage | 8/12/2015 | | 8/13/2015 | | PASS |
Jason C. Taylor
|
|
|
Project approved under SUB15-00014 ODI#3559. No inspection or plan review required. Jason Taylor ###-####.
|
Routing PW Sewer Design | 8/10/2015 | | 8/12/2015 | | PASS |
Kyle S. Rosenmeyer
|
|
|
|
Intake Approval | | | 8/7/2015 | | PASS |
|
|
|
planning land division has approved the review of the plans while parcel is still being recorded
|
Routing - Addressing | 8/7/2015 | | 8/7/2015 | | FAIL |
Emily Dixon
|
|
|
Needs parcel number, address shall be 10701 W Jewell Ln.
|
Intake Approval | | | 7/27/2015 | | FAIL |
|
|
|
Pending "Verification of Legal Lot or Parcel" before we can start review. Plat needs to be approved
|
Plans ACCEPTED BY PLAN TECH | | | 7/27/2015 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/27/2015 | | DONE |
|
|
|
|
Intake Approval | | | 7/23/2015 | | FAIL |
|
|
|
|
First Notice | | 10/10/2016 | | | |
|
|
|
|
Application received | | 7/23/2015 | | | |
|
|
|
|
Routing - PLANNING Land Div | 8/7/2015 | | | | FAIL |
Dave Abo
|
|
|
|