BLD-Final | 1/5/2016 | 1/6/2016 | 1/6/2016 | P | PASS |
Phil Shearer
|
|
|
Matt Phone #: ###-####
|
DOC - Permit Finaled | 1/6/2016 | 1/6/2016 | 1/6/2016 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Energy code compliance | 10/16/2015 | 10/16/2015 | 10/16/2015 | P | PASS |
Phil Shearer
|
|
|
Matt Phone #: ###-####
|
BLD-Framing/Rough-in | 10/16/2015 | 10/16/2015 | 10/16/2015 | P | PASS |
Phil Shearer
|
|
|
Matt Phone #: ###-####
|
BLD-Framing/Rough-in | 10/13/2015 | 10/14/2015 | 10/14/2015 | A | PART |
Phil Shearer
|
|
|
Matt Phone #: ###-####. Point load T43 trusses. OK to insulate
|
BLD-Wall Bracing | 10/14/2015 | 10/14/2015 | 10/14/2015 | P | FAIL |
Phil Shearer
|
|
|
Matt Phone #: ###-####
|
BLD-Foundation | 8/27/2015 | 8/27/2015 | 8/27/2015 | P | PASS |
Phil Shearer
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 8/26/2015 | 8/26/2015 | 8/26/2015 | A | PASS |
Phil Shearer
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 8/25/2015 | 8/25/2015 | 8/25/2015 | P | NR |
Phil Shearer
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 8/24/2015 | 8/24/2015 | 8/24/2015 | P | NR |
Phil Shearer
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
PubWorks Subgrade Approval | 8/21/2015 | 8/21/2015 | 8/21/2015 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
Issue PAID IN FULL permit | | | 8/17/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/17/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 8/13/2015 | | |
|
|
|
|
Routing - PLAN CHECK | 8/13/2015 | | 8/13/2015 | | PASS |
Tisha Gallop
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/13/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/13/2015 | | DONE |
|
|
|
all requirments met
|
Plan assigned to (LEG) Tisha | 7/27/2015 | | 8/13/2015 | | DONE |
Tisha Gallop
|
|
|
1st review 8/11; plan check
|
Routing PW Grading-Hillside | 8/11/2015 | | 8/12/2015 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor at ###-####
|
1st review completed | | | 8/12/2015 | | FAIL |
Tisha Gallop
|
|
|
plan check
|
Plan resubmittals received | | | 8/12/2015 | | DONE |
Tisha Gallop
|
|
|
|
Routing - PLAN CHECK | 7/27/2015 | | 8/11/2015 | | FAIL |
Tisha Gallop
|
|
|
|
Routing - MECHANICAL | 7/27/2015 | | 7/31/2015 | | PASS |
Troy James
|
|
|
|
Routing - PUBLIC WORKS | 7/27/2015 | | 7/28/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/27/2015 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 7/27/2015 | | PASS |
Christina Prado
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/27/2015 | | DONE |
Christina Prado
|
|
|
|
Routing - PLANNING | 7/27/2015 | | 7/27/2015 | | PASS |
Sue Cummings
|
|
|
per ePlan
|
Routing - Addressing | 7/27/2015 | | 7/27/2015 | | PASS |
Emily Dixon
|
|
|
|
Application received | | | 7/24/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 24 2015 2:56PM
|