BLD-Final | 11/20/2015 | 11/23/2015 | 11/23/2015 | A | PASS |
Phil Shearer
|
|
|
|
DOC - Permit Finaled | 11/23/2015 | 11/23/2015 | 11/23/2015 | P | PASS |
Phil Shearer
|
|
|
|
BLD-Final | 11/19/2015 | 11/20/2015 | 11/20/2015 | P | CANC |
Phil Shearer
|
|
|
Dirk Phone #: ###-####
|
BLD-Energy code compliance | 9/22/2015 | 9/23/2015 | 9/23/2015 | P | PASS |
Mike Jordan
|
|
|
Dirk Phone #: ###-####
|
BLD-Framing/Rough-in | 9/21/2015 | 9/22/2015 | 9/22/2015 | P | PASS |
Phil Shearer
|
|
|
Dirk Phone #: ###-####
|
BLD-Wall Bracing | 9/3/2015 | 9/4/2015 | 9/4/2015 | A | PASS |
Phil Shearer
|
|
|
Shear // Dirk Phone #: ###-####
|
BLD-Foundation | 8/12/2015 | 8/12/2015 | 8/12/2015 | P | PASS |
Phil Shearer
|
|
|
Dane Phone #: ###-####
|
BLD-Foundation | 8/11/2015 | 8/12/2015 | 8/12/2015 | A | NR |
Phil Shearer
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 8/10/2015 | 8/11/2015 | 8/11/2015 | P | PASS |
Phil Shearer
|
|
|
Dane Phone #: ###-####
|
PubWorks Subgrade Approval | 8/11/2015 | 8/11/2015 | 8/11/2015 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Jason Taylor ###-####.
|
BLD-Footing | 8/7/2015 | 8/10/2015 | 8/10/2015 | P | NR |
Phil Shearer
|
|
|
Dane Phone #: ###-####
|
OVERRIDE | | | 8/6/2015 | | |
|
|
|
|
Plan assigned to (BJM) | 8/3/2015 | 8/3/2015 | 8/6/2015 | | DONE |
Brian McGowan
|
|
|
|
1st review completed | | | 8/6/2015 | | DONE |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 8/6/2015 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/6/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/6/2015 | | DONE |
|
|
|
ALL REQUIREMENTS MET
|
Inspection Record Card- Bld | | | 8/6/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/6/2015 | | DONE |
|
|
|
|
Telephone call | | | 8/6/2015 | | DONE |
Christina Prado
|
|
|
Called Dirk to advise permit is ready and gave fees due
|
Issue PAID IN FULL permit | | | 8/6/2015 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/31/2015 | | 8/6/2015 | | PASS |
Brian McGowan
|
|
|
|
Routing - Addressing | 7/24/2015 | | 8/6/2015 | | PASS |
Emily Dixon
|
|
|
|
Plan assigned to (LEG) Tisha | 7/24/2015 | | 8/3/2015 | | DEFR |
Tisha Gallop
|
|
|
8/7
|
Routing - MECHANICAL | 7/29/2015 | | 7/31/2015 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 7/29/2015 | | 7/29/2015 | | PASS |
Sue Cummings
|
|
|
|
Routing - PUBLIC WORKS | | | 7/29/2015 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/24/2015 | | DONE |
|
|
|
|
Intake Approval | | | 7/24/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/24/2015 | | DONE |
|
|
|
|
Application received | | 7/24/2015 | | | |
|
|
|
|