Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD15-02607
StatusFinaled
Name DOWNEY CONSTRUCTION INC
Site Address 4106 W GLENCOE PL
Project Name 
Customer Number 
ePlanReviewNo
Description
PLAN MODIFICATION TO INSTALL ADDITIONAL WINDOWS IN BEDROOMS. **DAF** Permit for the construction of a new 2,387 sq. ft., two story (first story 1,675 sq. ft., second story 712 sq. ft.) single family dwelling with 3 bedrooms, 2.5 bathrooms, approximately 313 sq. ft. of covered patio/porch and a 485 sq. ft. attached garage per the approved plans, plan review report and any notations. R-1C zoning and setbacks per planning. LEG
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/2/201512/3/201512/3/2015APASS
DetailsPhil Shearer
Kevin Phone #: ###-####
DOC - Permit Finaled12/3/201512/3/201512/3/2015PPASS
DetailsPhil Shearer
BLD-Framing/Rough-in10/7/201510/8/201510/8/2015APASS
DetailsPhil Shearer
Kevin call before going ###-####
(F) Reprint permit  10/6/2015 DONE
BLD-Energy code compliance10/2/201510/5/201510/5/2015APASS
DetailsPhil Shearer
Kevin Phone #: ###-####
BLD-Energy code compliance9/30/201510/1/201510/1/2015APART
DetailsJim Sly
Kevin Phone #: ###-####
Air seal pkg. installed.
BLD-Framing/Rough-in9/30/201510/1/201510/1/2015APASS
DetailsJim Sly
Kevin Phone #: ###-####
Plan Modification Accepted  9/29/2015 DONE
new manual j report
Routing - MECHANICAL9/29/2015 9/29/2015 PASS
DetailsTroy James
resubmitted manual j report
BLD-Wall Bracing9/21/20159/22/20159/22/2015APASS
DetailsPhil Shearer
Kevin Phone #: ###-####
BLD-Foundation8/26/20158/27/20158/27/2015APASS
DetailsPhil Shearer
Matt Phone #: ###-####
BLD-Footing8/25/20158/26/20158/26/2015PPASS
DetailsPhil Shearer
Matt-pour time 2 ish Phone #: ###-####
Issue PAID IN FULL permit  8/14/2015 DONE
OVERRIDE  8/12/2015  
Plan assigned to (DAF)8/6/20158/6/20158/12/2015 DONE
DetailsDavid Ferguson
7/29
1st review completed  8/12/2015 DONE
DetailsDavid Ferguson
PLANS/APPL TAKEN TO FRONT DESK  8/12/2015 DONE
Inspection Record Card- Bld  8/12/2015 DONE
Permit Ready to Issue  8/12/2015 DONE
ALL REQUIREMENTS MET
Telephone call  8/12/2015 DONE
called Kevin- left message that permit is ready for pick up and fees due
Routing - PLAN CHECK8/3/2015 8/12/2015 PASS
DetailsDavid Ferguson
Plan assigned to (LEG) Tisha7/29/2015 8/6/2015 DEFR
DetailsTisha Gallop
8/12
Routing - MECHANICAL8/4/2015 8/4/2015 PASS
DetailsTroy James
Routing - MECHANICAL7/31/2015 8/3/2015 FAIL
DetailsTroy James
emailed corrections
Routing - PLANNING7/30/2015 7/31/2015 PASS
DetailsTodd Tucker
Routing - PUBLIC WORKS7/29/2015 7/30/2015 PASS
DetailsConnie Baumgartner
Routing - Addressing7/28/2015 7/29/2015 PASS
DetailsEmily Dixon
Intake Approval  7/29/2015 PASS
waiting on lot split to be finalized- 7/29/15 lot split is complete
Recd Pcfee & Taken To Pln CK  7/28/2015 DONE
Plans ACCEPTED BY PLAN TECH  7/28/2015 DONE
Application received 7/27/2015