BLD-Final | 11/16/2015 | 11/17/2015 | 11/17/2015 | A | PASS |
Tony Young
|
|
|
Colby Phone #: ###-####
|
DOC - Permit Finaled | 11/17/2015 | 11/17/2015 | 11/17/2015 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Energy code compliance | 10/19/2015 | 10/20/2015 | 10/20/2015 | A | PASS |
Jim Sly
|
|
|
Colby Phone #: ###-####
|
BLD-Framing/Rough-in | 10/15/2015 | 10/16/2015 | 10/16/2015 | P | PASS |
Dave Hannah
|
|
|
Colby Phone #: ###-####
|
BLD-Wall Bracing | 10/9/2015 | 10/9/2015 | 10/12/2015 | P | PASS |
Tony Young
|
|
|
Colby Phone #: ###-####
|
BLD-Foundation | 9/22/2015 | 9/23/2015 | 9/23/2015 | P | DONE |
Tony Young
|
|
|
John Phone #: ###-####
|
BLD-Foundation | 9/21/2015 | 9/22/2015 | 9/22/2015 | P | PART |
Mike Jordan
|
|
|
John Phone #: ###-####. Work in progress.
|
BLD-Footing | 9/18/2015 | 9/21/2015 | 9/21/2015 | P | PART |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/15/2015 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/15/2015 | | DONE |
|
|
|
|
OVERRIDE | | | 9/14/2015 | | |
|
|
|
|
Routing - MECHANICAL | 9/14/2015 | | 9/14/2015 | | PASS |
Troy James
|
|
|
|
Permit Ready to Issue | | | 9/14/2015 | | DONE |
Christina Prado
|
|
|
All requirements met
|
Routing - PLAN CHECK | 8/25/2015 | | 9/14/2015 | | PASS |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 9/11/2015 | | 9/11/2015 | | PASS |
Tisha Gallop
|
|
|
per BJM
|
1st review completed | | | 9/11/2015 | | DONE |
Brian McGowan
|
|
|
|
Plan assigned to (BJM) | 8/31/2015 | 8/31/2015 | 9/9/2015 | | DONE |
Brian McGowan
|
|
|
due 9/8 ePlan
|
Plan assigned to (LEG) Tisha | 8/25/2015 | | 8/31/2015 | | DEFR |
Tisha Gallop
|
|
|
9/8 ePlan
|
Routing - MECHANICAL | 8/25/2015 | | 8/26/2015 | | FAIL |
Troy James
|
|
|
|
Routing - PLANNING | 8/25/2015 | | 8/25/2015 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - Addressing | 8/25/2015 | | 8/25/2015 | | PASS |
Emily Dixon
|
|
|
|
Routing - PUBLIC WORKS | 8/25/2015 | | 8/25/2015 | | PASS |
Jennifer Bruner
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/25/2015 | | DONE |
|
|
|
|
Intake Approval | | | 8/25/2015 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/25/2015 | | DONE |
|
|
|
|
Application received | | | 7/29/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 29 2015 10:43AM
|
Intake Approval | | | 7/29/2015 | | FAIL |
|
|
|
NEED to upload engineered plans as well as individual sheets and needs RES check
|
Intake Approval | | | 7/29/2015 | | FAIL |
|
|
|
need building cross section
|